TxDOT contract A00208872 bid tabulation
Install/Replace Signs, Various (Various Locations in Hallettsville to LaGrange, Calhoun and Austin County). Let by Texas DOT on March 5, 2026, De Witt, Yoakum District. 6 bids received; low bid $2,600,761 by Vaca Underground Utilities Inc, +1.7% against the engineer's estimate of $2,556,537.
- Owner
- Texas DOT
- Letting
- 05 MAR 2026
- Pay items
- 131
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Vaca Underground Utilities Inc | $2,600,761 | Low | +2.0% |
| 2 | E-Z Bel Construction, LLC | $2,911,966 | +12% | +14% |
| 3 | Allstate Signal & Construction, LLC | $3,177,591 | +22% | +24% |
| 4 | Third Coast Services LLC | $3,208,537 | +23% | +26% |
| 5 | Creacom, Inc. | $3,827,144 | +47% | +50% |
| 6 | Mica Corporation | $4,681,869 | +80% | +83% |
Engineer's estimate: $2,556,537.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Vaca Underground Utilities Inc | 2. E-Z Bel Construction, LLC | 3. Allstate Signal & Construction, LLC | 4. Third Coast Services LLC | 5. Creacom, Inc. | 6. Mica Corporation |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (pavers) (104-7010) | SY | 518 | $140.00 | $20.00 | $73.45 | $50.47 | $59.32 | $45.00 | |
| 2 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 118 | $100.00 | $20.00 | $66.11 | $149.11 | $175.26 | $94.00 | |
| 3 | Removing concrete (curb) (104-7016) | LF | 8 | $30.00 | $10.00 | $33.90 | $84.88 | $99.77 | $72.00 | |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 1,408 | $30.00 | $10.00 | $27.12 | $18.35 | $21.57 | $38.50 | |
| 5 | Removing concrete (miscellaneous) (104-7046) | SY | 305 | $175.00 | $15.00 | $50.85 | $79.14 | $93.03 | $110.00 | |
| 6 | Remove (12") TRT/untrt base & asphalt pavement (105-7032) | SY | 2,976 | $15.00 | $6.00 | $39.55 | $27.53 | $32.36 | $42.00 | |
| 7 | Block sodding (162-7002) | SY | 1,101 | $75.00 | $7.50 | $7.68 | $16.63 | $24.27 | $17.00 | |
| 8 | Prime coat (MC-30) (310-7004) | GAL | 284 | $20.00 | $2.75 | $16.90 | $5.73 | $6.74 | $25.00 | |
| 9 | D-GR HMA type-B PG70-22 (341-7006) | TON | 983 | $125.00 | $155.00 | $263.39 | $276.42 | $393.66 | $240.00 | |
| 10 | D-GR HMA type D sac-B PG70-22 (341-7050) | TON | 186 | $125.00 | $375.27 | $311.57 | $356.71 | $419.28 | $275.00 | |
| 11 | Tack coat (341-7082) | GAL | 1,002 | $15.00 | $3.59 | $10.49 | $6.88 | $8.09 | $11.00 | |
| 12 | Temporary special shoring (403-7001) | SF | 538 | $20.00 | $50.00 | $5.00 | $50.85 | $20.65 | $24.27 | $39.00 |
| 13 | Drilled shaft (sign mounts) (36 in) (416-7030) | LF | 62 | $625.00 | $300.00 | $400.00 | $404.03 | $396.59 | $309.76 | $505.00 |
| 14 | Drilled shaft (sign mounts) (42 in) (416-7031) | LF | 80 | $725.00 | $400.00 | $420.00 | $559.32 | $399.96 | $383.25 | $665.00 |
| 15 | Drilled shaft (sign mounts) (48 in) (416-7032) | LF | 15.50 | $750.00 | $675.00 | $700.00 | $707.73 | $485.48 | $658.19 | $905.00 |
| 16 | Drilled shaft (sign mounts) (54 in) (416-7033) | LF | 36.50 | $800.00 | $800.00 | $720.00 | $839.71 | $947.93 | $576.72 | $936.00 |
| 17 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 125 | $250.00 | $350.00 | $406.22 | $310.55 | $216.88 | $562.00 | |
| 18 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 22 | $650.00 | $580.00 | $694.59 | $445.21 | $369.37 | $705.00 | |
| 19 | Class C concrete (rail foundation) (420-7052) | CY | 126 | $420.00 | $800.00 | $700.00 | $565.00 | $814.36 | $957.19 | $1,650.00 |
| 20 | Class C concrete (sign column) (420-7057) | CY | 46 | $1,600.00 | $750.00 | $4,100.00 | $3,390.00 | $4,874.69 | $7,195.12 | $1,925.00 |
| 21 | Class C concrete (sign footing) (420-7151) | CY | 20 | $1,800.00 | $650.00 | $1,776.00 | $1,695.00 | $1,605.78 | $1,887.43 | $1,540.00 |
| 22 | Riprap (concrete)(4 in) (432-7001) | CY | 34 | $200.00 | $1,000.00 | $1,000.00 | $772.92 | $708.84 | $833.17 | $880.00 |
| 23 | Riprap (mow strip)(4 in) (432-7013) | CY | 56 | $700.00 | $400.00 | $1,000.00 | $909.65 | $1,525.49 | $1,085.27 | $880.00 |
| 24 | Rail (type SSTR) (450-7024) | LF | 810 | $125.00 | $250.00 | $75.00 | $141.25 | $149.11 | $258.85 | $330.00 |
| 25 | RC pipe (CL III)(24 in) (464-7005) | LF | 15 | $150.00 | $645.00 | $508.50 | $458.79 | $539.27 | $220.00 | |
| 26 | Inlet (complete)(pco)(4FT)(none) (465-7017) | EACH | 2 | $12,000 | $13,000 | $7,910.00 | $7,799.51 | $9,167.54 | $22,000 | |
| 27 | Adjusting manholes (479-7001) | EACH | 2 | $1,800.00 | $2,900.00 | $1,864.50 | $1,548.43 | $1,820.03 | $4,400.00 | |
| 28 | Adjusting inlets (479-7002) | EACH | 1 | $1,800.00 | $1,800.00 | $11,583 | $2,982.17 | $3,505.23 | $5,500.00 | |
| 29 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,700.00 | $2,000.00 | $2,712.00 | $1,204.34 | $1,415.58 | $2,750.00 | |
| 30 | Mobilization (500-7001) | LS | 1 | $240,000 | $150,000 | $261,000 | $311,250 | $320,854 | $267,899 | $445,130 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $2,500.00 | $4,000.00 | $2,500.00 | $12,667 | $4,823.71 | $10,794 | $35,725 |
| 32 | Portable changeable message sign (503-7002) | EACH | 4 | $6,000.00 | $5,500.00 | $7,000.00 | $425.00 | $310.35 | $1,583.43 | $23,760 |
| 33 | TMA (stationary) (505-7001) | DAY | 18 | $200.00 | $250.00 | $700.00 | $575.00 | $1,110.24 | $427.64 | $510.00 |
| 34 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 540 | $10.00 | $1.00 | $10.00 | $5.65 | $18.12 | $12.13 | $16.50 |
| 35 | Biodegradable erosion control logs (remove) (506-7046) | LF | 540 | $2.50 | $1.00 | $3.00 | $1.81 | $9.21 | $2.70 | $3.30 |
| 36 | Concrete curb (type II) (529-7002) | LF | 215 | $35.00 | $30.00 | $50.00 | $50.85 | $86.02 | $101.11 | $110.00 |
| 37 | Concrete curb & gutter (type II) (529-7009) | LF | 1,425 | $30.00 | $30.00 | $50.85 | $78.00 | $91.68 | $138.00 | |
| 38 | Driveways (concrete) (530-7006) | SY | 122 | $130.00 | $160.00 | $163.85 | $252.34 | $296.60 | $275.00 | |
| 39 | Concrete sidewalks (5") (531-7002) | SY | 516 | $75.00 | $100.00 | $152.55 | $172.05 | $202.23 | $220.00 | |
| 40 | Curb ramps (type 1) (531-7015) | SY | 18 | $250.00 | $270.00 | $339.00 | $745.54 | $876.31 | $525.00 | |
| 41 | Curb ramps (type 2) (531-7016) | SY | 45 | $250.00 | $170.00 | $254.25 | $745.54 | $876.31 | $525.00 | |
| 42 | Curb ramps (type 7) (531-7020) | SY | 51 | $250.00 | $350.00 | $237.30 | $642.31 | $754.98 | $525.00 | |
| 43 | Curb ramps (type 20) (531-7022) | SY | 24 | $250.00 | $300.00 | $322.05 | $562.02 | $660.60 | $525.00 | |
| 44 | Curb ramps (type 21) (531-7023) | SY | 21 | $250.00 | $320.00 | $299.45 | $630.84 | $741.49 | $525.00 | |
| 45 | Concrete median (536-7002) | SY | 234 | $110.00 | $150.00 | $186.45 | $227.10 | $266.94 | $495.00 | |
| 46 | Metal W-beam guard fence (timber post) (540-7001) | LF | 500 | $25.00 | $34.00 | $32.46 | $32.88 | $39.00 | $39.23 | $38.50 |
| 47 | Downstream anchor terminal section (540-7015) | EACH | 2 | $1,500.00 | $2,134.00 | $1,826.00 | $1,339.05 | $2,179.27 | $1,597.57 | $2,200.00 |
| 48 | Guardrail end treatment (install) (544-7001) | EACH | 2 | $3,200.00 | $3,992.00 | $3,645.00 | $3,881.55 | $4,243.85 | $4,630.96 | $4,125.00 |
| 49 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 3 | $32,000 | $31,573 | $30,125 | $31,086 | $35,557 | $42,031 | $36,300 |
| 50 | Relocate RD IL asm (shoe-base) (610-7002) | EACH | 2 | $500.00 | $3,200.00 | $3,755.00 | $1,831.80 | $1,906.59 | $2,770.00 | |
| 51 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 510 | $15.00 | $28.00 | $17.20 | $15.19 | $16.14 | $18.70 | |
| 52 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 570 | $20.00 | $33.00 | $21.20 | $22.10 | $18.73 | $44.15 | |
| 53 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 535 | $17.00 | $39.00 | $24.12 | $17.46 | $19.05 | $21.25 | |
| 54 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 570 | $25.00 | $48.00 | $29.37 | $24.37 | $19.41 | $46.70 | |
| 55 | Electrical conductor (no.8) bare (620-7007) | LF | 2,155 | $1.75 | $2.50 | $2.61 | $2.40 | $1.78 | $2.85 | |
| 56 | Electrical conductor (no.8) insulated (620-7008) | LF | 2,950 | $1.85 | $3.50 | $2.78 | $2.66 | $2.12 | $2.85 | |
| 57 | Electrical conductor (no.6) bare (620-7009) | LF | 45 | $2.00 | $3.25 | $3.20 | $2.94 | $3.55 | $3.40 | |
| 58 | Electrical conductor (no.6) insulated (620-7010) | LF | 75 | $2.25 | $3.65 | $3.53 | $3.29 | $3.70 | $3.40 | |
| 59 | Ground box type D (162922)W/apron (624-7008) | EACH | 11 | $1,500.00 | $1,500.00 | $1,380.00 | $1,412.62 | $1,148.69 | $2,550.00 | |
| 60 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 2 | $7,500.00 | $10,000 | $13,750 | $9,843.71 | $10,154 | $13,270 | |
| 61 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $7,500.00 | $11,500 | $10,485 | $11,496 | $8,000.06 | $11,995 | |
| 62 | Aluminum signs (type A) (636-7001) | SF | 168 | $40.00 | $50.00 | $70.27 | $31.87 | $79.96 | $34.25 | |
| 63 | Aluminum signs (type O) (636-7003) | SF | 1,717 | $30.00 | $35.00 | $35.00 | $32.12 | $33.05 | $34.55 | $37.60 |
| 64 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 3 | $1,309.00 | $1,200.00 | $785.35 | $776.08 | $2,022.25 | $996.00 | |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 1 | $1,440.00 | $1,300.00 | $960.50 | $865.99 | $2,022.25 | $1,080.00 | |
| 66 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 2 | $1,309.00 | $1,600.00 | $1,118.70 | $1,057.50 | $2,022.25 | $1,260.00 | |
| 67 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 1 | $1,636.00 | $2,000.00 | $1,570.70 | $1,293.36 | $1,820.03 | $1,852.00 | |
| 68 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 6 | $500.00 | $589.00 | $1,000.00 | $745.80 | $656.99 | $606.68 | $1,162.00 |
| 69 | Remove SM RD SN sup&AM (644-7073) | EACH | 10 | $131.00 | $100.00 | $124.30 | $215.31 | $134.82 | $279.00 | |
| 70 | Remove lrsa (647-7003) | EACH | 2 | $375.00 | $348.00 | $2,000.00 | $830.55 | $348.49 | $2,299.51 | $1,670.00 |
| 71 | Install overhead sign support(30 FT cant)(span only) (650-7034) | EACH | 2 | $35,000 | $21,000 | $35,000 | $30,887 | $20,934 | $30,583 | $35,105 |
| 72 | Install overhead sign support(35 FT cant) (650-7038) | EACH | 1 | $46,000 | $34,000 | $60,500 | $46,440 | $38,844 | $41,663 | $56,840 |
| 73 | Install overhead sign support(40 FT cant) (650-7045) | EACH | 2 | $50,000 | $36,000 | $60,000 | $48,994 | $38,568 | $44,073 | $60,125 |
| 74 | Install overhead sign support(55 FT BRDG) (650-7064) | EACH | 1 | $85,000 | $65,000 | $97,000 | $69,504 | $66,657 | $70,833 | $74,335 |
| 75 | Remove overhd sign sup (650-7193) | EACH | 2 | $5,000.00 | $926.00 | $4,500.00 | $3,850.00 | $2,090.88 | $7,830.41 | $9,055.00 |
| 76 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 79 | $4.00 | $3.00 | $1.24 | $1.26 | $4.04 | $3.30 | |
| 77 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 30 | $5.00 | $4.00 | $2.26 | $2.29 | $5.39 | $4.40 | |
| 78 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 5,981 | $3.00 | $2.00 | $0.99 | $1.01 | $3.83 | $2.20 | |
| 79 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 300 | $1.00 | $0.85 | $0.66 | $0.67 | $1.15 | $0.95 | |
| 80 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 2,798 | $1.00 | $0.85 | $0.47 | $0.48 | $1.15 | $0.95 | |
| 81 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 1,986 | $1.00 | $0.85 | $0.54 | $0.55 | $1.15 | $0.95 | |
| 82 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 200 | $1.00 | $0.85 | $0.66 | $0.67 | $1.15 | $0.95 | |
| 83 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 7,956 | $1.00 | $0.85 | $0.43 | $0.44 | $1.23 | $0.95 | |
| 84 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 4,552 | $2.00 | $1.75 | $0.99 | $1.01 | $2.36 | $1.95 | |
| 85 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 2,918 | $2.00 | $1.75 | $0.99 | $1.01 | $2.36 | $1.95 | |
| 86 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 518 | $2.00 | $1.75 | $1.24 | $1.26 | $2.36 | $1.95 | |
| 87 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 8,574 | $2.00 | $1.75 | $0.99 | $1.01 | $2.36 | $1.95 | |
| 88 | Prefabricated PM type C (W)(12")(solid) (668-7087) | LF | 89 | $10.00 | $7.75 | $10.17 | $10.32 | $10.45 | $1.95 | |
| 89 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 572 | $20.00 | $15.50 | $18.08 | $18.35 | $20.90 | $17.05 | |
| 90 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 11 | $458.00 | $350.00 | $169.50 | $172.05 | $471.86 | $385.00 | |
| 91 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 1 | $655.00 | $500.00 | $395.50 | $401.45 | $674.08 | $550.00 | |
| 92 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 9 | $524.00 | $400.00 | $282.50 | $286.75 | $539.27 | $440.00 | |
| 93 | Prefabricated PM type C (W)(18")(yld tri) (668-7110) | EACH | 6 | $46.00 | $35.00 | $39.55 | $40.14 | $47.19 | $38.50 | |
| 94 | Prefabricated PM type C (Y)(12")(solid) (668-7125) | LF | 460 | $10.00 | $7.75 | $9.04 | $9.18 | $10.45 | $8.55 | |
| 95 | Reflectorized pavement marker type I-C (672-7002) | EACH | 72 | $10.00 | $7.50 | $10.74 | $10.90 | $10.11 | $8.25 | |
| 96 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 286 | $10.00 | $7.50 | $10.74 | $10.90 | $10.11 | $8.25 | |
| 97 | Removing traffic signals (680-7004) | EACH | 1 | $4,500.00 | $4,500.00 | $4,750.00 | $2,296.56 | $6,457.15 | $8,345.00 | |
| 98 | Ins HY traffic signal (DPT sup CNT & cab)(iso) (680-7005) | EACH | 3 | $20,000 | $8,500.00 | $17,500 | $14,842 | $9,980.29 | $64,500 | |
| 99 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 22 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 100 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 7 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 101 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 22 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 102 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 10 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 103 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 22 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 104 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 5 | $340.00 | $375.00 | $367.00 | $318.15 | $302.21 | $490.00 | |
| 105 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 12 | $707.00 | $800.00 | $845.00 | $902.34 | $733.15 | $1,010.00 | |
| 106 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 20 | $209.00 | $200.00 | $182.00 | $150.31 | $170.08 | $195.00 | |
| 107 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 7 | $275.00 | $300.00 | $256.00 | $215.81 | $202.44 | $240.00 | |
| 108 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 1,700 | $2.50 | $3.15 | $2.99 | $2.56 | $2.13 | $5.15 | |
| 109 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 425 | $3.00 | $4.00 | $3.93 | $3.26 | $5.02 | $5.85 | |
| 110 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 1,450 | $9.00 | $10.00 | $11.83 | $8.34 | $7.38 | $7.10 | |
| 111 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 1,490 | $2.00 | $3.25 | $2.75 | $2.39 | $2.12 | $3.85 | |
| 112 | Install RDSD flash beacon assembly (685-7001) | EACH | 1 | $2,350.00 | $4,000.00 | $4,500.00 | $3,110.00 | $6,772.73 | $6,163.72 | $17,700 |
| 113 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 1 | $14,000 | $17,000 | $14,882 | $13,224 | $16,152 | $14,180 | |
| 114 | Ins traffic signal PL AM(S)1 arm(32') (686-7033) | EACH | 1 | $12,000 | $15,000 | $13,634 | $12,162 | $15,186 | $13,985 | |
| 115 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 1 | $15,000 | $18,000 | $15,973 | $14,147 | $17,301 | $16,080 | |
| 116 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 2 | $16,000 | $19,000 | $16,452 | $14,462 | $18,216 | $16,370 | |
| 117 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 2 | $18,500 | $20,000 | $18,092 | $15,536 | $19,565 | $17,910 | |
| 118 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $19,500 | $22,000 | $18,767 | $15,875 | $19,985 | $18,220 | |
| 119 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 1 | $33,000 | $50,000 | $29,212 | $33,356 | $38,437 | $36,100 | |
| 120 | Ins traffic PL AM(1) arm (44')(lum)(HNGD) (686-7310) | EACH | 1 | $20,000 | $32,000 | $20,724 | $21,013 | $27,190 | $23,660 | |
| 121 | Pedestrian pole assembly (687-7001) | EACH | 6 | $1,400.00 | $2,500.00 | $2,615.00 | $3,425.25 | $3,053.93 | $3,980.00 | |
| 122 | Pedestrian detect push button (APS) (688-7001) | EACH | 12 | $1,000.00 | $1,300.00 | $926.00 | $793.93 | $1,238.71 | $1,285.00 | |
| 123 | Pedestrian detector controller unit (688-7003) | EACH | 3 | $4,500.00 | $6,500.00 | $4,470.00 | $3,313.78 | $4,777.39 | $4,380.00 | |
| 124 | Install of ground boxes (690-7008) | EACH | 1 | $1,550.00 | $2,000.00 | $1,000.00 | $1,250.00 | $1,216.55 | $1,215.75 | $2,550.00 |
| 125 | Bbu system (external battery cabinet) (6007-7001) | EACH | 3 | $9,500.00 | $13,000 | $10,105 | $8,738.17 | $11,155 | $8,600.00 | |
| 126 | RVDS (presence detection only) (6008-7001) | EACH | 11 | $10,800 | $14,500 | $8,801.50 | $7,435.98 | $10,014 | $10,550 | |
| 127 | Ground box (adjust) (6013-7007) | EACH | 2 | $700.00 | $390.00 | $3,000.00 | $1,000.00 | $552.86 | $1,135.89 | $2,425.00 |
| 128 | CCTV field equipment (digital) (6018-7005) | EACH | 1 | $5,000.00 | $7,000.00 | $5,800.00 | $7,867.23 | $5,034.54 | $13,595 | |
| 129 | Spread spectrum radio (6043-7001) | EACH | 3 | $2,200.00 | $7,000.00 | $2,510.00 | $2,388.88 | $2,768.63 | $8,390.00 | |
| 130 | Coaxial cable (6043-7002) | LF | 350 | $11.00 | $3.00 | $5.10 | $6.81 | $7.69 | $25.55 | |
| 131 | Antenna (uni-directional) (6043-7003) | EACH | 3 | $1,100.00 | $1,300.00 | $1,360.00 | $1,965.66 | $1,608.42 | $4,355.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2026. Compiled by Mirage Metrics.