Intersection Improvement, FM 1138 (FM 1138 at CR 541 to .). Let by Texas DOT on June 4, 2025, Collin, Dallas District. 7 bids received; low bid $1,429,322 by Jagoe-Public Company, -43% against the engineer's estimate of $2,499,670.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 63
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jagoe-Public Company | $1,429,322 | Low | -43% |
| 2 | D. L. Lennon Incorporated - Contractor | $1,471,330 | +3.0% | -41% |
| 3 | Quality Excavation, LLC | $1,522,314 | +7.0% | -39% |
| 4 | Highway 19 Construction LLC | $1,552,057 | +9.0% | -38% |
| 5 | A. K. Gillis & Sons, LLC | $1,668,331 | +17% | -33% |
| 6 | Texas Materials Group, Inc. | $1,687,937 | +18% | -32% |
| 7 | Grey Sky Construction LLC | $2,535,023 | +77% | +1.0% |
Engineer's estimate: $2,499,670.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jagoe-Public Company | 2. D. L. Lennon Incorporated - Contractor | 3. Quality Excavation, LLC | 4. Highway 19 Construction LLC | 5. A. K. Gillis & Sons, LLC | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13.95 | $3,000.00 | $6,000.00 | $2,320.00 | $5,800.00 | $5,000.00 | $2,000.00 | $2,000.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 17 | $150.00 | $110.00 | $10.00 | $80.00 | $30.00 | $25.00 | $50.00 |
| 3 | Remove (10"-14") TRT/untrt base & asphalt pavement (105-7010) | SY | 1,490 | $22.00 | $35.00 | $47.50 | $35.00 | $18.00 | $24.88 | $18.45 |
| 4 | Excavation (roadway) (110-7001) | CY | 2,572 | $75.00 | $40.00 | $43.00 | $24.75 | $30.00 | $50.00 | $15.00 |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 389 | $100.00 | $40.00 | $43.00 | $49.00 | $80.00 | $70.00 | $90.00 |
| 6 | Backfill (type A or B) (134-7004) | STA | 13.95 | $250.00 | $1,200.00 | $3,000.00 | $2,900.00 | $500.00 | $1,000.00 | $1,500.00 |
| 7 | Blading (150-7001) | STA | 13.95 | $420.00 | $100.00 | $3,000.00 | $955.00 | $450.00 | $750.00 | $100.00 |
| 8 | Drill seed (permanent_rural_clay) (164-7010) | SY | 7,766 | $1.00 | $0.30 | $0.55 | $0.40 | $5.00 | $0.55 | $0.54 |
| 9 | Drill seed (temporary_warm_cool) (164-7015) | SY | 7,766 | $1.00 | $0.05 | $0.55 | $0.38 | $5.00 | $0.55 | $0.54 |
| 10 | Vegetative watering (168-7001) | TGL | 2,311 | $300.00 | $2.50 | $0.01 | $92.00 | $10.00 | $5.00 | $0.10 |
| 11 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 3,131 | $40.00 | $50.00 | $71.25 | $40.00 | $71.00 | $64.38 | $47.24 |
| 12 | Lime (commercial lime slurry) (260-7004) | TON | 146 | $550.00 | $325.00 | $550.00 | $340.00 | $450.00 | $325.00 | $320.00 |
| 13 | Lime TRT (existing material)(15") (260-7030) | SY | 3,291 | $15.00 | $25.00 | $8.90 | $39.00 | $20.00 | $8.50 | $26.72 |
| 14 | Prime coat (AE-P) (310-7001) | GAL | 892 | $5.00 | $2.00 | $22.00 | $12.34 | $12.00 | $8.71 | $6.00 |
| 15 | SP mixes SP-B PG64-22 (344-7001) | TON | 542 | $250.00 | $180.00 | $182.50 | $186.39 | $180.00 | $209.37 | $200.00 |
| 16 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 774 | $300.00 | $200.00 | $163.00 | $164.05 | $160.00 | $148.00 | $200.00 |
| 17 | Tack coat (344-7077) | GAL | 556 | $15.00 | $2.00 | $2.00 | $2.18 | $10.00 | $2.00 | $6.00 |
| 18 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 3,410 | $15.00 | $5.00 | $8.98 | $4.75 | $8.00 | $5.45 | $4.00 |
| 19 | Flowable backfill (401-7001) | CY | 4 | $500.00 | $750.00 | $265.00 | $400.00 | $500.00 | $500.00 | $550.00 |
| 20 | Riprap (concrete)(4 in) (432-7001) | CY | 53 | $500.00 | $1,300.00 | $800.00 | $790.00 | $750.00 | $700.00 | $575.00 |
| 21 | Riprap (mow strip)(4 in) (432-7013) | CY | 30 | $500.00 | $1,500.00 | $650.00 | $770.00 | $550.00 | $700.00 | $625.00 |
| 22 | RC pipe (CL III)(18 in) (464-7003) | LF | 82 | $110.00 | $140.00 | $70.00 | $123.00 | $75.00 | $58.00 | $97.50 |
| 23 | RC pipe (CL III)(24 in) (464-7005) | LF | 52 | $120.00 | $200.00 | $85.00 | $185.00 | $110.00 | $95.00 | $112.33 |
| 24 | RC pipe (CL III)(36 in) (464-7009) | LF | 12 | $500.00 | $500.00 | $200.00 | $522.00 | $180.00 | $185.00 | $202.34 |
| 25 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 6 | $1,500.00 | $2,400.00 | $825.00 | $1,050.00 | $1,110.00 | $1,000.00 | $2,250.00 |
| 26 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 4 | $2,350.00 | $3,000.00 | $1,200.00 | $1,650.00 | $1,550.00 | $2,000.00 | $2,950.00 |
| 27 | Set (removing & reinstall) (467-7472) | EACH | 1 | $2,500.00 | $2,500.00 | $500.00 | $1,483.00 | $750.00 | $2,500.00 | $2,550.00 |
| 28 | Removing structure (set) (496-7004) | EACH | 10 | $500.00 | $35.00 | $200.00 | $354.00 | $500.00 | $250.00 | $735.00 |
| 29 | Removing structure (pipe) (496-7007) | LF | 115 | $50.00 | $60.00 | $7.00 | $24.00 | $50.00 | $10.00 | $26.30 |
| 30 | Mobilization (500-7001) | LS | 1 | $227,243 | $158,500 | $163,550 | $150,000 | $250,000 | $344,132 | $168,000 |
| 31 | Barricades, signs and traffic handling (502-7001) | MO | 4 | $20,000 | $20,000 | $11,500 | $3,500.00 | $20,000 | $48,275 | $107,500 |
| 32 | Portable changeable message sign (503-7002) | EACH | 2 | $22,500 | $12,500 | $15,000 | $5,500.00 | $17,000 | $17,500 | $25,000 |
| 33 | TMA (stationary) (505-7001) | DAY | 58 | $1,500.00 | $100.00 | $350.00 | $315.00 | $1,000.00 | $500.00 | $175.00 |
| 34 | TMA (mobile operation) (505-7002) | HR | 58 | $300.00 | $35.00 | $100.00 | $175.00 | $100.00 | $500.00 | $175.00 |
| 35 | Rock filter dams (install) (type 2) (506-7002) | LF | 30 | $120.00 | $100.00 | $70.00 | $38.21 | $85.00 | $70.00 | $97.54 |
| 36 | Rock filter dams (remove) (506-7011) | LF | 30 | $50.00 | $22.00 | $30.00 | $13.10 | $10.00 | $30.00 | $23.07 |
| 37 | Construction exits (install) (type 1) (506-7020) | SY | 172 | $150.00 | $20.00 | $45.00 | $39.31 | $35.00 | $45.00 | $56.92 |
| 38 | Construction exits (remove) (506-7024) | SY | 172 | $30.00 | $10.00 | $15.00 | $10.92 | $10.00 | $15.00 | $19.75 |
| 39 | Temporary sediment control fence (install) (506-7039) | LF | 473 | $30.00 | $8.00 | $6.00 | $3.93 | $5.00 | $6.00 | $6.88 |
| 40 | Temporary sediment control fence (remove) (506-7041) | LF | 473 | $15.00 | $2.75 | $2.00 | $1.31 | $1.00 | $2.00 | $1.96 |
| 41 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 187 | $25.00 | $24.00 | $6.00 | $6.55 | $10.00 | $6.00 | $14.45 |
| 42 | Biodegradable erosion control logs (remove) (506-7046) | LF | 187 | $10.00 | $2.75 | $2.00 | $1.36 | $1.00 | $2.00 | $1.96 |
| 43 | Driveways (ACP) (530-7010) | SY | 230 | $100.00 | $38.00 | $100.70 | $120.00 | $95.00 | $124.63 | $250.00 |
| 44 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 2,590 | $3.00 | $2.50 | $15.97 | $2.13 | $2.50 | $2.92 | $1.95 |
| 45 | Metal W-beam guard fence (timber post) (540-7001) | LF | 400 | $50.00 | $30.00 | $26.25 | $30.57 | $35.00 | $36.55 | $36.55 |
| 46 | TL-3 31" short radius (complete) (540-7039) | EACH | 2 | $20,000 | $24,000 | $23,125 | $28,224 | $1,800.00 | $23,845 | $23,845 |
| 47 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,500.00 | $3,500.00 | $3,050.00 | $3,755.87 | $3,100.00 | $3,355.00 | $3,355.00 |
| 48 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 1 | $400.00 | $500.00 | $1,000.00 | $349.38 | $450.00 | $325.00 | $325.00 |
| 49 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 1 | $400.00 | $600.00 | $2,000.00 | $393.06 | $600.00 | $425.00 | $425.00 |
| 50 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 4 | $1,000.00 | $900.00 | $2,000.00 | $742.44 | $350.00 | $769.00 | $769.00 |
| 51 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 10 | $100.00 | $50.00 | $45.00 | $33.85 | $35.00 | $25.00 | $25.00 |
| 52 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 3,804 | $0.50 | $1.50 | $0.65 | $1.47 | $0.55 | $0.55 | $1.35 |
| 53 | Work zone pavement marking non-removing (Y)8"(solid) (662-7039) | LF | 700 | $0.60 | $2.00 | $2.00 | $2.18 | $0.75 | $0.75 | $2.00 |
| 54 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 76 | $10.00 | $3.25 | $10.00 | $4.00 | $2.00 | $2.45 | $1.00 |
| 55 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 389 | $12.00 | $3.25 | $10.00 | $3.92 | $2.00 | $2.45 | $1.00 |
| 56 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 144 | $30.00 | $4.00 | $3.00 | $3.77 | $1.50 | $1.50 | $3.45 |
| 57 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 700 | $40.00 | $2.25 | $2.00 | $2.18 | $1.50 | $1.50 | $2.00 |
| 58 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 4 | $220.00 | $275.00 | $225.00 | $245.66 | $250.00 | $250.00 | $225.00 |
| 59 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $250.00 | $275.00 | $320.00 | $272.96 | $275.00 | $275.00 | $250.00 |
| 60 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 1,995 | $1.50 | $1.25 | $1.25 | $1.08 | $0.84 | $0.84 | $0.99 |
| 61 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 3,804 | $1.50 | $1.25 | $1.25 | $1.08 | $0.84 | $0.84 | $0.99 |
| 62 | Reflectorized pavement marker type I-C (672-7002) | EACH | 38 | $20.00 | $9.00 | $7.50 | $8.73 | $4.50 | $4.50 | $8.00 |
| 63 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 201 | $35.00 | $9.00 | $7.50 | $8.73 | $4.50 | $4.50 | $8.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.