TxDOT contract A00210089 bid tabulation
METAL BEAM GUARD FENCE REPAIR, IH0035 (VARIOUS LOCATIONS IN to TRAVIS AND WILLIAMSON COUNTY). Let by Texas DOT on April 3, 2025, Travis, Austin District. 3 bids received; low bid $2,534,513 by BK Field Operations LLC, -32% against the engineer's estimate of $3,745,615.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 55
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BK Field Operations LLC | $2,534,513 | Low | -32% |
| 2 | Roy Jorgensen Associates, Inc. | $4,432,991 | +75% | +18% |
| 3 | T&L Cleaning Services LLC | $4,517,650 | +78% | +21% |
Engineer's estimate: $3,745,615.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. BK Field Operations LLC | 2. Roy Jorgensen Associates, Inc. | 3. T&L Cleaning Services LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 10 | $67.00 | $100.00 | $25.00 | $100.00 |
| 2 | Riprap (mow strip)(4 in) (432-7013) | CY | 40 | $875.00 | $200.00 | $725.00 | $500.00 |
| 3 | Rail (handrail)(type B) (450-7059) | LF | 150 | $120.00 | $80.00 | $225.00 | $300.00 |
| 4 | Retrofit rail (type T221) (451-7004) | LF | 200 | $380.00 | $1.00 | $650.00 | $250.00 |
| 5 | Mobilization (callout 1) (500-7003) | EACH | 2,000 | $280.00 | $1.00 | $0.01 | $1.00 |
| 6 | Portable changeable message sign (503-7001) | DAY | 80 | $100.00 | $200.00 | $150.00 | $150.00 |
| 7 | TMA (stationary) (505-7001) | DAY | 700 | $200.00 | $1.00 | $1.00 | $1.00 |
| 8 | Temporary sediment control fence (install) (506-7039) | LF | 20 | $4.00 | $2.00 | $5.00 | $5.00 |
| 9 | Temporary sediment control fence (remove) (506-7041) | LF | 20 | $2.00 | $1.00 | $3.00 | $5.00 |
| 10 | Metal W-beam guard fence (timber post) (540-7001) | LF | 5,000 | $30.00 | $0.10 | $15.00 | $30.00 |
| 11 | Metal W-beam guard fence (steel post) (540-7002) | LF | 500 | $30.00 | $1.00 | $20.00 | $40.00 |
| 12 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 15 | $2,000.00 | $1.00 | $1,300.00 | $1,800.00 |
| 13 | Driveway terminal anchor section (540-7014) | EACH | 5 | $1,500.00 | $1.00 | $1.00 | $2,000.00 |
| 14 | Downstream anchor terminal section (540-7015) | EACH | 60 | $1,500.00 | $1,000.00 | $1,750.00 | $1,800.00 |
| 15 | Metal beam guard fence trans (anchor plate) (540-7029) | EACH | 10 | $600.00 | $1,000.00 | $1,500.00 | $700.00 |
| 16 | Remove metal beam guard fence (542-7001) | LF | 5,000 | $5.00 | $0.10 | $2.00 | $1.00 |
| 17 | Remove terminal anchor section (542-7002) | EACH | 40 | $250.00 | $1,250.00 | $750.00 | $100.00 |
| 18 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 15 | $250.00 | $1.00 | $500.00 | $2,000.00 |
| 19 | Guardrail end treatment (install) (544-7001) | EACH | 25 | $3,000.00 | $1.00 | $3,200.00 | $2,500.00 |
| 20 | Chain link fence (install) (8') (550-7005) | LF | 200 | $60.00 | $1.00 | $25.00 | $10.00 |
| 21 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 200 | $53.00 | $1,000.00 | $50.00 | $30.00 |
| 22 | Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036) | EACH | 100 | $60.00 | $1,000.00 | $30.00 | $30.00 |
| 23 | Replace rail element (W-beam) (770-7001) | LF | 20,000 | $20.00 | $5.00 | $28.00 | $28.00 |
| 24 | Replace rail element (thrie-beam) (770-7002) | LF | 300 | $45.00 | $120.00 | $40.00 | $30.00 |
| 25 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 150 | $45.00 | $35.00 | $450.00 | $30.00 |
| 26 | Replace short radius sys (TL-2) (770-7004) | EACH | 3 | $5,000.00 | $1.00 | $1.00 | $15,000 |
| 27 | Replace short radius sys (TL-3) (770-7005) | EACH | 3 | $5,000.00 | $1.00 | $1.00 | $25,000 |
| 28 | Replace timber post W/O concrete FND (770-7006) | EACH | 1,000 | $100.00 | $200.00 | $225.00 | $30.00 |
| 29 | Replace steel post W/O concrete FND (770-7007) | EACH | 1,000 | $100.00 | $1.00 | $80.00 | $50.00 |
| 30 | Replace timber post W/ concrete FND (770-7008) | EACH | 500 | $50.00 | $300.00 | $200.00 | $60.00 |
| 31 | Replace steel post W/ concrete FND (770-7009) | EACH | 500 | $50.00 | $1.00 | $90.00 | $100.00 |
| 32 | Realign posts (770-7010) | EACH | 600 | $20.00 | $1.00 | $20.00 | $10.00 |
| 33 | Repair of terminal anchors posts (770-7011) | EACH | 50 | $100.00 | $1.00 | $100.00 | $50.00 |
| 34 | Replace terminal anchor posts (770-7012) | EACH | 250 | $55.10 | $1.00 | $200.00 | $50.00 |
| 35 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 450 | $2,750.00 | $1,900.00 | $3,200.00 | $5,000.00 |
| 36 | Repl single gdrail terminal impact head (770-7015) | EACH | 150 | $95.00 | $1,740.00 | $2,000.00 | $1,000.00 |
| 37 | Replace single gdrail terminal rail (770-7016) | LF | 4,500 | $25.00 | $25.00 | $38.00 | $30.00 |
| 38 | Replace single gdrail terminal post (770-7017) | EACH | 600 | $25.00 | $60.00 | $120.00 | $50.00 |
| 39 | Replace blockout (770-7018) | EACH | 2,500 | $10.00 | $6.00 | $27.50 | $10.00 |
| 40 | Repair steel post with base plate (770-7019) | EACH | 30 | $325.00 | $100.00 | $325.00 | $200.00 |
| 41 | Replace SGT cable anchor (770-7022) | EACH | 50 | $25.00 | $600.00 | $80.00 | $70.00 |
| 42 | Replace SGT cable assembly (770-7023) | EACH | 50 | $25.00 | $600.00 | $80.00 | $70.00 |
| 43 | Replace SGT strut (770-7024) | EACH | 40 | $30.00 | $100.00 | $80.00 | $70.00 |
| 44 | Replace downstream anchor terminal (770-7026) | EACH | 150 | $50.00 | $1.00 | $1,150.00 | $150.00 |
| 45 | Repair rail element (curved rail) (770-7027) | LF | 1,500 | $35.00 | $40.00 | $45.00 | $30.00 |
| 46 | Replace posts (TL-4)(gibraltar) (771-7005) | EACH | 150 | $200.00 | $1.00 | $180.00 | $180.00 |
| 47 | Replace posts (TL-4)(trinity) (771-7007) | EACH | 150 | $200.00 | $590.00 | $360.00 | $220.00 |
| 48 | Cable splice / turnbuckle (TL-4) (771-7010) | EACH | 1 | $2,500.00 | $2,000.00 | $3,000.00 | $100.00 |
| 49 | Repair or replace cable barrier terminal sec(TL-4) (771-7014) | EACH | 50 | $1,750.00 | $200.00 | $1,250.00 | $1,500.00 |
| 50 | Replace cable (TL-4) (771-7016) | LF | 350 | $8.00 | $0.10 | $4.00 | $1.00 |
| 51 | Replace (narrow quad) (774-7026) | EACH | 6 | $10,000 | $10,000 | $27,500 | $25,000 |
| 52 | Repair (narrow quad) (774-7027) | LF | 4 | $1,000.00 | $1,400.00 | $5,000.00 | $2,500.00 |
| 53 | Replace (wide quad) (774-7031) | EACH | 2 | $17,000 | $1.00 | $5,000.00 | $40,000 |
| 54 | Repair (wide quad) (774-7032) | LF | 5 | $1,050.00 | $1,000.00 | $5,000.00 | $5,000.00 |
| 55 | Repair (T101) (776-7006) | LF | 40 | $55.00 | $30.00 | $500.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.