TxDOT contract A00211316 bid tabulation

Bridge Maintenance, US 67 (At Bosque River to .). Let by Texas DOT on April 7, 2026, Erath, Fort Worth District. 6 bids received; low bid $2,983,533 by Blacksmith Ventures LLC, -29% against the engineer's estimate of $4,188,151.

Owner
Texas DOT
Letting
07 APR 2026
Pay items
58
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Blacksmith Ventures LLC$2,983,533Low-29%
2Gibson & Associates, Inc.$3,280,280+10%-22%
3The Truesdell Corporation$3,333,333+12%-20%
4Structural Integrity Group LLC$3,672,303+23%-12%
5Ragle Construction, Inc.$3,749,569+26%-10%
6Built Right Construction of Oklahoma, LLC$4,246,103+42%+1.0%
TxDOT contract A00211316: bids by rank

Engineer's estimate: $4,188,151.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Blacksmith Ventures LLC2. Gibson & Associates, Inc.3. The Truesdell Corporation4. Structural Integrity Group LLC5. Ragle Construction, Inc.6. Built Right Construction of Oklahoma, LLC
1Preparing row (100-7001)ACRE1.30$20,000$15,000$5,500.00$5,000.00$2,500.00$40,000$4,600.00
2Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001)SY3,325$8.71$6.58$6.50$7.50$7.50$6.25
3Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002)SY7,430$10.00$8.71$6.58$6.50$10.00$5.15$6.50
4Backfill (type A) (134-7001)STA5$243.00$200.00$1,100.00$1,000.00$750.00$550.00$675.00
5Soil ret BLKT(chan_permanent_4 PSF) (169-7032)SY81$2.00$2.00$11.00$10.00$10.00$7.25$20.00
6SP mixes SP-C sac-B PG70-28 (344-7025)TON419$250.00$350.00$391.33$290.00$300.00$350.00$400.00
7Tack coat (344-7077)GAL1,613$3.85$8.00$1.65$11.00$6.50$7.00$2.00
8Flowable backfill (401-7001)CY17$2,250.00$1,000.00$880.00$800.00$360.00$440.00$500.00
9Class C concrete (crashwall) (420-7050)CY128.20$500.00$1,265.00$880.00$1,590.00$995.00$1,100.00
10Silicone resin paint finish (427-7004)SF3,250$12.10$6.60$15.00$6.00$6.00$7.00
11Penetrating concrete surface treatment (428-7001)SY1,425$13.00$9.90$27.50$15.00$25.00$12.00$30.00
12Concrete structure repair(clean & coat WTH epoxy) (429-7001)SF70.70$75.00$66.00$60.00$110.00$200.00$250.00
13Concrete structure repair(deck rep(part depth)) (429-7003)SF6,450$100.00$55.00$5.00$45.00$30.00$20.00$225.00
14Concrete structure repair (vertical & overhead) (429-7007)SF857.70$200.00$91.00$170.50$155.00$468.00$150.00$225.00
15Concrete structure repair (standard) (429-7009)SF19.70$200.00$75.00$170.50$155.00$468.00$250.00$225.00
16Concrete structure repair (pan girder hole repair) (429-7010)EACH100$197.00$1.00$55.00$50.00$100.00$130.00$225.00
17Riprap (stone protection)(18 in) (432-7043)CY228$150.00$162.00$206.80$188.00$225.00$200.00$200.00
18Riprap (stone protection)(24 in) (432-7045)CY145$160.00$162.00$206.80$188.00$258.00$190.00$200.00
19Cleaning and sealing existing joints (CL3) (438-7004)LF75$42.00$33.00$60.00$68.00$18.00$50.00
20Cleaning and sealing existing joints (CL7) (438-7007)LF152$43.00$42.00$40.70$63.00$86.00$23.00$55.00
21Resizing and sealing joints (438-7009)LF298$46.71$60.00$81.40$110.00$110.00$64.00$70.00
22Clean and seal JNTS (pan girders) (CL3) (438-7011)LF503$60.00$42.00$33.00$60.00$64.00$30.00$65.00
23Clean and seal JNTS (pan girders) (CL7) (438-7012)LF284$42.00$42.00$40.70$60.00$117.00$37.00$65.00
24Polyester polymer concrete overlay (2") (439-7017)SY2,116$151.00$220.00$255.00$255.00$235.00$170.00
25Polyester polymer concrete overlay (1") (439-7021)SY5,435$200.00$151.00$115.00$150.00$121.00$120.00$90.00
26Header type expansion joint (454-7009)CF15.40$490.62$400.00$1,100.00$3,000.00$200.00$380.00$500.00
27Gabion mattresses (galvanized)(12 in) (459-7007)SY73$90.00$369.17$170.50$155.00$240.00$145.00$325.00
28Gabions (3' X 3')(galvanized) (459-7010)CY15$400.00$617.47$385.00$350.00$585.00$490.00$400.00
29Clean existing culverts (480-7002)CY675$19.25$88.00$80.00$135.00$20.00$200.00
30Mobilization (500-7001)LS1$350,000$340,000$459,000$330,486$350,000$370,000$200,000
31Barricades, signs and traffic handling (502-7001)MO10$4,000.00$3,000.00$20,250$1,700.00$14,400$35,000$3,000.00
32Portable changeable message sign (503-7002)EACH4$8,000.00$15,000$12,000$5,000.00$2,500.00$15,000$6,000.00
33Rock filter dams (install) (type 2) (506-7002)LF216.80$20.00$49.50$45.00$45.00$45.00$10.00
34Rock filter dams (remove) (506-7011)LF216.80$1.00$16.50$15.00$20.00$20.00$5.00
35Temporary sediment control fence (install) (506-7039)LF2,984.10$4.11$3.00$5.50$5.00$5.00$5.00$3.00
36Temporary sediment control fence (remove) (506-7041)LF2,984.10$1.10$0.10$1.10$1.00$0.50$0.50$1.00
37Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009)LF2,119$50.00$35.00$48.40$39.00$48.50$35.00$88.00
38Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010)LF80$120.00$27.50$48.40$38.00$48.50$35.00$90.00
39Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033)LF2,119$20.00$1.00$11.00$11.00$5.25$60.00$25.00
40Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034)LF80$20.00$1.00$11.00$11.00$5.25$60.00$30.00
41Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057)LF2,119$15.00$0.25$24.20$34.00$23.00$5.00$25.00
42Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058)LF80$30.00$0.25$24.20$34.00$23.00$5.00$25.00
43Work zone pavement marking removing (W)6"(solid) (662-7068)LF2,838$1.50$1.75$1.93$1.60$1.75$1.50$1.80
44Work zone pavement marking removing (Y)6"(solid) (662-7100)LF2,838$1.45$1.75$1.93$1.60$1.75$1.50$1.80
45Pavement sler 6" (666-7347)LF5,966$0.28$0.40$0.44$0.25$0.40$0.20$0.25
46Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408)LF750$0.59$2.00$2.20$0.75$2.00$0.70$0.85
47Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF2,998$0.47$1.20$1.32$0.75$1.20$0.59$0.75
48Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF5,996$0.46$1.20$1.32$0.75$1.20$0.59$0.75
49Eliminating existing PM & markers (6") (677-7002)LF11,352$0.64$0.85$0.94$0.60$0.85$0.55$0.65
50Spot tree trimming / brush removal (752-7002)LF512$30.00$15.75$16.50$15.00$7.50$35.00$20.00
51Tree trimming / brush removal(channels) (752-7003)ACRE0.30$15,000$11,000$10,000$1,640.00$19,250$2,500.00
52Drain inlet cleaning (764-7001)EACH20$65.00$20.00$350.00$270.00$150.00$250.00$200.00
53CNC crack repair (discrete)(inject) (780-7002)LF28$75.00$110.00$100.00$70.00$125.00$125.00
54Concrete CRCK repair(discrete)(rout and seal) (780-7003)LF607$120.00$75.00$36.30$33.00$45.00$35.00$25.00
55Steel bridge zone painting ref STR #1 (4010-7002)EACH1$120,000$115,000$179,680$120,000$163,345$375,000$185,000
56Steel bridge zone painting ref STR #2 (4010-7003)EACH1$85,000$85,085$75,000$77,350$219,000$90,000
57Bent cap/abutment cap cleaning (7001-7002)EACH2$500.00$1,100.00$1,000.00$2,000.00$1,150.00$1,000.00
58Remove & replace delineator/object mark (7034-7001)EACH2$100.00$150.00$200.00$225.00$195.00$500.00
TxDOT contract A00211316: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy