TxDOT contract A00212635 bid tabulation
METAL BEAM GUARD FENCE REPAIR, US0059 (VARIOUS ROADWAYS to VARIOUS ROADWAYS). Let by Texas DOT on February 20, 2025, Bowie, Atlanta District. 4 bids received; low bid $715,078 by Lakey, Inc., -13% against the engineer's estimate of $825,243.
- Owner
- Texas DOT
- Letting
- 20 FEB 2025
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lakey, Inc. | $715,078 | Low | -13% |
| 2 | B & MS Construction, Inc. | $730,955 | +2.0% | -11% |
| 3 | Catocon, Inc. | $945,769 | +32% | +15% |
| 4 | Odum Services, LLC | $1,485,400 | +108% | +80% |
Engineer's estimate: $825,243.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lakey, Inc. | 2. B & MS Construction, Inc. | 3. Catocon, Inc. | 4. Odum Services, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 40 | $100.00 | $275.00 | $40.00 | $100.00 | $125.00 |
| 2 | Riprap (mow strip)(4 in) (432-7013) | CY | 100 | $100.00 | $600.00 | $400.00 | $400.00 | $1,250.00 |
| 3 | Mobilization (callout) (500-7002) | EACH | 20 | $500.00 | $500.00 | $500.00 | $100.00 | $2,500.00 |
| 4 | Portable changeable message sign (503-7001) | DAY | 10 | $334.00 | $10.00 | $100.00 | $1.00 | $500.00 |
| 5 | TMA (stationary) (505-7001) | DAY | 100 | $200.00 | $250.00 | $200.00 | $100.00 | $250.00 |
| 6 | Metal W-beam guard fence (timber post) (540-7001) | LF | 250 | $29.00 | $29.00 | $35.00 | $35.00 | $35.00 |
| 7 | Downstream anchor terminal section (540-7015) | EACH | 5 | $1,390.00 | $1,900.00 | $1,300.00 | $1,200.00 | $1,850.00 |
| 8 | Remove metal beam guard fence (542-7001) | LF | 500 | $3.25 | $2.75 | $5.00 | $1.00 | $5.00 |
| 9 | Remove terminal anchor section (542-7002) | EACH | 5 | $300.00 | $366.00 | $1,500.00 | $1.00 | $250.00 |
| 10 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $1,500.00 | $3,200.00 | $2,000.00 | $1,000.00 | $3,150.00 |
| 11 | Guardrail end treatment (remove) (544-7003) | EACH | 5 | $300.00 | $220.00 | $1,500.00 | $1.00 | $350.00 |
| 12 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (658-7015) | EACH | 50 | $30.00 | $36.43 | $1.00 | $1.00 | $30.00 |
| 13 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 50 | $30.00 | $24.75 | $1.00 | $1.00 | $30.00 |
| 14 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 50 | $30.00 | $38.50 | $10.00 | $1.00 | $42.00 |
| 15 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 50 | $30.00 | $48.48 | $2.00 | $1.00 | $42.00 |
| 16 | Replace rail element (W-beam) (770-7001) | LF | 1,500 | $20.00 | $23.00 | $25.00 | $40.00 | $25.00 |
| 17 | Replace rail element (thrie-beam) (770-7002) | LF | 25 | $40.00 | $25.00 | $35.00 | $40.00 | $30.00 |
| 18 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 15 | $50.00 | $20.00 | $40.00 | $125.00 | $560.00 |
| 19 | Replace timber post W/O concrete FND (770-7006) | EACH | 200 | $40.00 | $5.50 | $55.00 | $44.00 | $70.00 |
| 20 | Replace steel post W/O concrete FND (770-7007) | EACH | 100 | $50.00 | $52.50 | $55.00 | $40.00 | $75.00 |
| 21 | Replace timber post W/ concrete FND (770-7008) | EACH | 100 | $50.00 | $5.50 | $42.00 | $1.00 | $10.00 |
| 22 | Replace steel post W/ concrete FND (770-7009) | EACH | 100 | $50.00 | $65.00 | $70.00 | $65.00 | $10.00 |
| 23 | Realign posts (770-7010) | EACH | 100 | $7.00 | $22.50 | $25.00 | $30.00 | $50.00 |
| 24 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 50 | $2,000.00 | $3,900.00 | $4,000.00 | $4,000.00 | $3,150.00 |
| 25 | Repl single gdrail terminal impact head (770-7015) | EACH | 25 | $700.00 | $925.00 | $900.00 | $1,000.00 | $1,400.00 |
| 26 | Replace single gdrail terminal rail (770-7016) | LF | 250 | $32.00 | $27.50 | $30.00 | $40.00 | $48.00 |
| 27 | Replace single gdrail terminal post (770-7017) | EACH | 50 | $135.00 | $165.00 | $125.00 | $100.00 | $50.00 |
| 28 | Replace blockout (770-7018) | EACH | 50 | $150.00 | $20.00 | $30.00 | $200.00 | $25.00 |
| 29 | Repair steel post with base plate (770-7019) | EACH | 10 | $25.00 | $65.00 | $200.00 | $200.00 | $25.00 |
| 30 | Replace SGT object marker (770-7021) | EACH | 10 | $77.75 | $1.00 | $45.00 | $50.00 | $50.00 |
| 31 | Replace SGT cable anchor (770-7022) | EACH | 10 | $80.00 | $1.00 | $70.00 | $50.00 | $50.00 |
| 32 | Replace SGT cable assembly (770-7023) | EACH | 10 | $175.00 | $1.00 | $70.00 | $50.00 | $50.00 |
| 33 | Replace SGT strut (770-7024) | EACH | 10 | $500.00 | $1.00 | $65.00 | $50.00 | $50.00 |
| 34 | Raise rail (770-7025) | LF | 1,000 | $1.00 | $1.00 | $8.00 | $1.00 | $15.00 |
| 35 | Remove (narrow quad) (774-7025) | EACH | 4 | $1,000.00 | $1,000.00 | $1,500.00 | $1.00 | $1,250.00 |
| 36 | Replace (narrow quad) (774-7026) | EACH | 4 | $20,000 | $15,000 | $18,000 | $18,000 | $25,250 |
| 37 | Repair (narrow quad nose) (774-7028) | EACH | 4 | $750.00 | $10,000 | $350.00 | $1,500.00 | $4,000.00 |
| 38 | Repair (narrow quad bay) (774-7029) | EACH | 4 | $550.00 | $10,000 | $500.00 | $1,000.00 | $3,500.00 |
| 39 | Remove (wide quad) (774-7030) | EACH | 4 | $1,000.00 | $1,000.00 | $250.00 | $1.00 | $1,250.00 |
| 40 | Replace (wide quad) (774-7031) | EACH | 4 | $20,000 | $13,750 | $2,000.00 | $25,000 | $34,300 |
| 41 | Repair (wide quad nose) (774-7033) | EACH | 4 | $750.00 | $1,000.00 | $385.00 | $1,000.00 | $4,000.00 |
| 42 | Repair (wide quad bay) (774-7034) | EACH | 4 | $775.00 | $1,000.00 | $650.00 | $1,500.00 | $3,500.00 |
| 43 | Remove (narrow tracc) (774-7048) | EACH | 4 | $1,000.00 | $1,000.00 | $400.00 | $1.00 | $1,250.00 |
| 44 | Replace (narrow tracc) (774-7049) | EACH | 4 | $20,000 | $1,000.00 | $2,500.00 | $22,000 | $30,300 |
| 45 | Remove (wide tracc) (774-7050) | EACH | 4 | $500.00 | $500.00 | $510.00 | $1.00 | $1,250.00 |
| 46 | Replace (wide tracc) (774-7051) | EACH | 4 | $20,000 | $300.00 | $11,500 | $20,000 | $53,750 |
| 47 | Repair (wide tracc nose) (774-7053) | EACH | 4 | $500.00 | $500.00 | $650.00 | $1,500.00 | $4,000.00 |
| 48 | Repair (wide tracc bay) (774-7054) | EACH | 4 | $500.00 | $50.00 | $300.00 | $1,000.00 | $3,500.00 |
| 49 | Remove (fastracc) (774-7055) | EACH | 4 | $1,000.00 | $1,000.00 | $650.00 | $1.00 | $1,250.00 |
| 50 | Replace (fastracc) (774-7056) | EACH | 4 | $20,000 | $100.00 | $25,000 | $30,000 | $38,250 |
| 51 | Remove (matt) (774-7063) | EACH | 4 | $1,000.00 | $2,000.00 | $600.00 | $1.00 | $1,250.00 |
| 52 | Replace (matt) (774-7064) | EACH | 4 | $20,000 | $4,000.00 | $1,500.00 | $5,000.00 | $17,000 |
| 53 | Repair (T101) (776-7006) | LF | 500 | $46.00 | $45.00 | $45.00 | $30.00 | $25.00 |
| 54 | Repair (steel post W/ base plate)(T101) (776-7007) | EACH | 20 | $25.00 | $110.00 | $200.00 | $200.00 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.