TxDOT contract A00215671 bid tabulation

Preventive Maintenance, SH 29 (FM 1660 to SH 95). Let by Texas DOT on April 7, 2026, Williamson, Austin District. 4 bids received; low bid $2,388,456 by Lone Star Paving Company, -6.9% against the engineer's estimate of $2,566,159.

Owner
Texas DOT
Letting
07 APR 2026
Pay items
46
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lone Star Paving Company$2,388,456Low-7.0%
2Hunter Industries, LTD.$2,670,296+12%+4.0%
3Texas Materials Group, Inc.$2,689,490+13%+5.0%
4Knife River Corporation - South$3,469,920+45%+35%
TxDOT contract A00215671: bids by rank

Engineer's estimate: $2,566,159.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Lone Star Paving Company2. Hunter Industries, LTD.3. Texas Materials Group, Inc.4. Knife River Corporation - South
1Removing concrete (riprap) (104-7006)SY45$25.00$25.00$72.60$25.00$73.45
2Backfill (type B) (134-7002)STA350.50$160.00$120.00$132.01$125.00$148.40
3D-GR HMA type D PG76-22 (341-7056)TON6,313$100.00$109.00$104.50$118.00$151.40
4D-GR HMA type D PG76-22 (level-UP) (341-7059)TON75$110.75$115.00$144.10$165.00$180.00
5Tom-C PG76-22 sac-B (347-7002)TON6,556$123.00$128.00$129.41$138.00$180.15
6Flexible pavement structure repair(4") (351-7003)SY4,567$32.00$33.00$32.92$33.95$40.85
7Flexible pavement structure repair(6") (351-7005)SY1,833$47.50$46.50$50.47$45.00$58.00
8Planing asphalt concrete pavement(2") (354-7051)SY57,449$2.00$0.99$2.20$1.75$2.35
9Riprap (mow strip)(4 in) (432-7013)CY37$570.00$705.00$758.01$705.00$975.00
10Cleaning and sealing existing joints (438-7001)LF120$32.00$30.00$36.22$30.00$33.35
11Joint sealant (454-7010)LF120$18.00$24.00$42.52$24.00$26.65
12Mobilization (500-7001)LS1$145,300$29,500$162,351$60,000$139,132
13Barricades, signs and traffic handling (502-7001)MO3$7,500.00$820.00$2,039.97$15,000$2,800.00
14Portable changeable message sign (503-7001)DAY346$75.00$5.00$73.86$55.00$140.00
15TMA (stationary) (505-7001)DAY84$250.00$10.00$142.05$175.00$895.00
16TMA (mobile operation) (505-7003)DAY17$225.00$5.00$255.68$900.00$985.00
17Temporary sediment control fence (install) (506-7039)LF100$3.50$6.00$10.50$6.00$17.00
18Temporary sediment control fence (remove) (506-7041)LF100$0.80$1.00$5.25$1.00$17.00
19Intrsct, drvways, & turnout (ACP) (530-7022)SY5,813$25.00$17.75$22.00$20.75$34.50
20Metal W-beam guard fence (timber post) (540-7001)LF537.50$25.00$32.00$25.19$31.65$26.65
21Metal beam guard fence trans (thrie-beam) (540-7005)EACH3$2,400.00$2,140.00$2,519.42$2,125.00$2,111.00
22Downstream anchor terminal section (540-7015)EACH1$1,600.00$1,510.00$1,364.69$1,500.00$1,445.00
23TL-3 31" short radius (complete) (540-7039)EACH1$10,000$36,000$29,393$12,000$31,110
24Remove metal beam guard fence (542-7001)LF571$2.75$2.80$2.62$2.80$2.80
25RM metal beam guard fence trans (thrie-beam) (542-7004)EACH3$300.00$176.00$262.44$175.00$1,288.00
26Guardrail end treatment (install) (544-7001)EACH4$3,175.00$3,770.00$3,306.74$3,750.00$3,500.00
27Guardrail end treatment (remove) (544-7003)EACH4$300.00$151.00$262.44$150.00$278.00
28Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH14$33.60$16.80$43.04$25.00$45.55
29Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF68,928$0.22$0.19$0.19$0.19$0.20
30Work zone pavement marking non-removing (W)24"(solid) (662-7017)LF173$2.50$3.00$2.10$3.00$2.25
31Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH2$40.00$75.00$52.49$75.00$55.60
32Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF1,860$0.25$0.19$0.19$0.19$0.20
33Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF63,812$0.24$0.19$0.19$0.19$0.20
34Work zone pavement marking non-removing (Y)24"(solid) (662-7042)LF127$1.90$3.00$2.10$3.00$2.25
35Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH46$2.25$1.00$1.72$1.04$1.00
36Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH3,324$1.00$1.00$1.72$1.04$1.00
37Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF173$6.00$8.00$15.75$8.00$16.65
38Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH2$135.00$200.00$236.20$200.00$250.00
39Reflectorized pavement marking type I (Y)24"(solid)(090MIL) (666-7122)LF127$5.00$8.00$14.70$8.00$15.55
40Reflectorized profile pavement marking type I(W)6"(solid)(090MIL) (666-7265)LF68,928$0.75$0.72$0.75$0.71$0.79
41Reflectorized profile pavement marking type I(Y)6"(solid)(090MIL) (666-7269)LF63,812$0.75$0.72$0.75$0.71$0.79
42Reflectorized profile pavement marking type I(Y)6"(broken)(090MIL) (666-7273)LF1,860$0.65$0.72$0.75$0.71$0.79
43PRFB rumble strip (BLK)(1')(centerline) (668-7002)LF6,676$3.25$3.25$3.41$3.25$3.60
44PRFB rumble strip (BLK)(1')(edgeline) (668-7137)LF13,786$3.00$3.25$3.41$3.25$3.60
45Reflectorized pavement marker type II-A-A (672-7004)EACH932$4.65$3.50$5.25$3.25$5.55
46Bonding course (3007-7001)GAL20,886$3.30$3.20$3.52$4.00$0.25
TxDOT contract A00215671: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy