TxDOT contract A00217902 bid tabulation

Reconstruct Existing Roadway, FM 4 (1st Street to 3rd Street). Let by Texas DOT on July 1, 2026, Johnson, Fort Worth District. 4 bids received; low bid $3,499,716 by Jay Mills Contracting, Incorporated, -3.6% against the engineer's estimate of $3,629,091.

Owner
Texas DOT
Letting
01 JUL 2026
Pay items
92
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jay Mills Contracting, Incorporated$3,499,716Low-4.0%
2Prater Dirt Work LLC$3,765,501+8.0%+4.0%
3Knife River Corporation - South$3,810,088+9.0%+5.0%
4Ed Bell Construction Company$4,098,939+17%+13%
TxDOT contract A00217902: bids by rank

Engineer's estimate: $3,629,091.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jay Mills Contracting, Incorporated2. Prater Dirt Work LLC3. Knife River Corporation - South4. Ed Bell Construction Company
1Preparing row (100-7002)STA8$1,500.00$5,800.00$20,000$2,500.00$35,000
2Removing concrete (driveways) (104-7011)SY126$21.00$62.50$50.00$42.00
3Removing concrete (sidewalk, ramp or shared use path) (104-7013)SY487$30.00$21.00$62.50$40.00$31.50
4Removing concrete (curb & gutter) (104-7017)LF1,415$40.00$20.00$18.75$15.00$15.75
5Removing concrete (flume) (104-7041)SY28$10.00$30.00$125.00$50.00$105.00
6Remove (9") TRT/untrt base & asphalt pavement (105-7029)SY5,730$6.00$26.00$14.50$7.50$21.00
7Excavation (roadway) (110-7001)CY1,077$13.00$50.00$75.00$40.00$25.00
8Embankment (final)(DC)(type C) (132-7006)CY261$17.00$50.00$250.00$40.00$90.00
9Backfill (type A) (134-7001)STA0.70$265.00$6,000.00$10,000$2,750.00$4,200.00
10Furn & place topsoil (4") (160-7002)SY14$15.00$110.00$500.00$35.00$105.00
11Block sodding (162-7002)SY14$4.00$50.00$33.00$25.00$73.50
12Vegetative watering (168-7001)TGL0.50$5.50$1,000.00$2,500.00$1,000.00$1,050.00
13Lime (commercial lime slurry) (260-7004)TON95$325.00$362.00$325.00$350.00$525.00
14Lime TRT (existing material)(8") (260-7007)SY5,746$7.00$10.00$15.00$6.50$12.50
15Prime coat (MC-30) (310-7004)GAL895$6.00$10.00$30.25$12.00$29.29
16D-GR HMA type-B PG64-22 (341-7001)TON1,464$140.00$295.00$246.00$175.00$238.08
17SP mixes SP-C sac-B PG70-28 (344-7025)TON113$150.00$535.00$516.00$450.00$498.95
18Tack coat (344-7077)GAL167$2.00$4.40$33.00$5.00$31.95
19Concrete pavement (CPCD) (8") (360-7018)SY4,773$200.00$110.00$131.00$185.00$150.00
20Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF30$310.00$635.00$440.00$680.00$266.25
21Drilled shaft (traffic signal pole) (30 in) (416-7043)LF44$530.00$637.00$500.00$685.00$426.00
22Riprap (concrete)(CL B) (432-7005)CY1$2,500.00$1,440.00$3,000.00$2,100.00
23Cleaning and sealing joints (foam) (438-7010)LF134$45.00$210.00$200.00$110.00$105.00
24STR steel (miscellaneous non-bridge) (442-7007)LB9,394.51$15.00$11.60$14.00$12.50$13.65
25Rail (handrail)(type B) (450-7059)LF98$131.00$220.00$170.00$147.00
26Removing structure (pipe) (496-7007)LF8$24.00$30.00$200.00$75.00$105.00
27Mobilization (500-7001)LS1$329,917$280,000$360,000$380,000$400,000
28Barricades, signs and traffic handling (502-7001)MO16$8,000.00$30,000$22,000$12,000$31,500
29Portable changeable message sign (503-7002)EACH2$7,500.00$16,500$200.00$30,000$25,000
30TMA (stationary) (505-7001)DAY235$190.00$203.50$300.00$500.00$200.00
31Temporary sediment control fence (install) (506-7039)LF480$4.00$7.15$5.00$10.00$10.50
32Temporary sediment control fence (remove) (506-7041)LF480$1.00$3.85$1.65$1.50$5.25
33Biodegradable erosion control logs (install) (18") (506-7045)LF200$10.45$8.20$10.00$10.50
34Biodegradable erosion control logs (remove) (506-7046)LF200$3.85$1.65$1.50$5.25
35Constructing detours (508-7001)SY86$300.00$130.00$150.00$150.00
36Remove and relay pavers (528-7003)SY4,583$100.00$50.00$30.00$82.00$84.00
37Replacement pavers (528-7004)SY4,233$100.00$55.00$64.00$95.00$15.75
38Concrete curb & gutter (type II) (529-7009)LF1,606$90.00$35.00$36.00$46.00$52.50
39Driveways (concrete) (530-7006)SY175$125.00$150.00$195.00$168.00
40Concrete sidewalks (4") (531-7001)SY1,171$52.00$70.00$91.20$89.00$84.00
41Curb ramps (type 1) (531-7005)EACH16$3,700.00$2,600.00$2,520.00$3,000.00$2,500.00
42Curb ramps (type 6) (531-7009)EACH1$2,600.00$3,360.00$4,750.00$2,500.00
43In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH3$5,500.00$5,700.00$11,000$6,100.00$5,005.50
44Conduit (PVC) (schedule 80) (2") (618-7054)LF235$30.00$18.00$21.00$19.00$26.63
45Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF625$50.00$41.00$29.00$44.00$37.28
46Conduit (PVC) (schedule 80) (4") (618-7064)LF40$26.00$23.50$27.00$25.00$31.95
47Conduit (PVC) (schedule 80) (4") (bore) (618-7065)LF155$36.00$61.00$40.00$65.00$79.88
48Electrical conductor (no.8) bare (620-7007)LF760$2.50$2.05$3.50$2.15$1.65
49Electrical conductor (no.8) insulated (620-7008)LF1,520$3.00$2.45$4.00$2.61$1.76
50Electrical conductor (no.6) bare (620-7009)LF395$3.00$2.35$4.00$2.47$1.86
51Electrical conductor (no.6) insulated (620-7010)LF290$2.90$4.25$3.09$2.08
52Ground box type D (162922) (624-7007)EACH6$1,600.00$900.00$1,150.00$975.00$1,278.00
53Remove electrical services (628-7002)EACH1$615.00$390.00$1,100.00$500.00$580.43
54Elc SRV type A 120/240 060(NS)AL(E)PS(U) (628-7003)EACH1$6,850.00$10,050$13,000$10,750$7,135.50
55Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148)EACH1$8,800.00$12,500$9,500.00$7,029.00
56Aluminum signs (type A) (636-7001)SF38.80$40.00$44.00$45.00$50.00$72.31
57Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH7$800.00$570.00$450.00$725.00$548.48
58Relocate SM RD SN sup&AM type S80 (644-7067)EACH4$850.00$770.00$715.00$950.00$744.44
59Relocate SM RD SN sup&AM type TWT (644-7068)EACH2$430.00$550.00$330.00$725.00$531.44
60Remove SM RD SN sup&AM (644-7073)EACH3$151.00$110.00$165.00$125.00$105.44
61Work zone pavement marking removing (W)4"(solid) (662-7064)LF8,573$0.50$1.40$3.00$1.50$5.25
62Work zone pavement marking removing (Y)4"(solid) (662-7097)LF7,500$0.50$1.40$3.00$1.50$5.25
63Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF833$1.25$1.00$1.54$1.10$1.49
64Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF648$0.50$0.70$1.65$0.75$1.60
65Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF472$0.75$0.70$1.65$0.75$1.60
66Prefabricated PM type C (W)(12")(solid) (668-7087)LF436$5.00$8.05$6.05$9.00$5.86
67Prefabricated PM type C (W)(24")(solid) (668-7089)LF146$15.00$15.40$12.10$17.00$11.72
68Prefabricated PM type C (W)(RR crossing) (668-7108)EACH1$625.00$1,430.00$853.60$1,500.00$826.44
69Reflectorized pavement marker type II-A-A (672-7004)EACH110$4.25$5.50$6.88$6.00$6.66
70Traffic button type Y (672-7008)EACH300$4.50$5.50$5.50$6.00$5.33
71Eliminating existing PM & markers (4") (677-7001)LF2,720$0.50$0.60$1.10$0.65$1.07
72Install highway traffic signal (isolated) (680-7002)EACH1$38,000$30,000$48,000$32,000$38,340
73Removing traffic signals (680-7004)EACH2$10,000$4,885.00$4,500.00$5,200.00$5,325.00
74Vehicle signal section (12")LED(green) (682-7001)EACH8$400.00$370.00$450.00$390.00$324.83
75Vehicle signal section (12")LED(yel) (682-7003)EACH8$400.00$370.00$450.00$390.00$324.83
76Vehicle signal section (12")LED(red) (682-7005)EACH8$400.00$370.00$450.00$390.00$324.83
77Pedestrian signal section (LED)(countdown) (682-7018)EACH8$1,000.00$860.00$1,300.00$920.00$734.85
78Backplate W/ref border(3 sec)(vent)aluminum (682-7042)EACH8$250.00$285.00$250.00$300.00$175.73
79Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007)LF505$3.00$2.35$3.50$2.50$2.82
80Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009)LF185$3.00$3.25$5.00$3.50$2.82
81Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF80$3.50$2.90$5.00$3.10$3.67
82Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033)LF405$4.00$3.80$5.00$4.10$3.67
83Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042)LF300$3.50$7.20$11.00$7.70$7.24
84Ins traffic signal PL AM(S)1 arm(28')lum (686-7031)EACH2$10,244$14,100$20,000$15,000$14,058
85Ins traffic signal PL AM(S)1 arm(32')lum (686-7035)EACH2$11,701$14,700$20,000$16,000$14,697
86Pedestrian pole assembly (687-7001)EACH4$3,858.00$4,750.00$4,100.00$5,000.00$2,662.50
87Pedestrian detect push button (APS) (688-7001)EACH8$1,075.00$1,100.00$1,200.00$1,150.00$1,038.38
88Pedestrian detector controller unit (688-7003)EACH1$3,931.00$4,121.50$5,000.00$4,400.00$4,047.00
89Removal of control cabinet(pole MNT) (690-7041)EACH1$970.00$1,100.00$1,000.00$596.40
90ITS com CBL (ethernet) (6005-7001)LF30$3.00$2.00$4.50$3.00$2.98
91Bbu system (external battery cabinet) (6007-7001)EACH1$9,205.00$10,500$10,000$10,863
92RVDS (presence detection only) (6008-7001)EACH4$6,600.00$7,775.00$12,000$8,300.00$12,082
TxDOT contract A00217902: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy