TxDOT contract A00217902 bid tabulation
Reconstruct Existing Roadway, FM 4 (1st Street to 3rd Street). Let by Texas DOT on July 1, 2026, Johnson, Fort Worth District. 4 bids received; low bid $3,499,716 by Jay Mills Contracting, Incorporated, -3.6% against the engineer's estimate of $3,629,091.
- Owner
- Texas DOT
- Letting
- 01 JUL 2026
- Pay items
- 92
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jay Mills Contracting, Incorporated | $3,499,716 | Low | -4.0% |
| 2 | Prater Dirt Work LLC | $3,765,501 | +8.0% | +4.0% |
| 3 | Knife River Corporation - South | $3,810,088 | +9.0% | +5.0% |
| 4 | Ed Bell Construction Company | $4,098,939 | +17% | +13% |
Engineer's estimate: $3,629,091.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jay Mills Contracting, Incorporated | 2. Prater Dirt Work LLC | 3. Knife River Corporation - South | 4. Ed Bell Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 8 | $1,500.00 | $5,800.00 | $20,000 | $2,500.00 | $35,000 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 126 | $21.00 | $62.50 | $50.00 | $42.00 | |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 487 | $30.00 | $21.00 | $62.50 | $40.00 | $31.50 |
| 4 | Removing concrete (curb & gutter) (104-7017) | LF | 1,415 | $40.00 | $20.00 | $18.75 | $15.00 | $15.75 |
| 5 | Removing concrete (flume) (104-7041) | SY | 28 | $10.00 | $30.00 | $125.00 | $50.00 | $105.00 |
| 6 | Remove (9") TRT/untrt base & asphalt pavement (105-7029) | SY | 5,730 | $6.00 | $26.00 | $14.50 | $7.50 | $21.00 |
| 7 | Excavation (roadway) (110-7001) | CY | 1,077 | $13.00 | $50.00 | $75.00 | $40.00 | $25.00 |
| 8 | Embankment (final)(DC)(type C) (132-7006) | CY | 261 | $17.00 | $50.00 | $250.00 | $40.00 | $90.00 |
| 9 | Backfill (type A) (134-7001) | STA | 0.70 | $265.00 | $6,000.00 | $10,000 | $2,750.00 | $4,200.00 |
| 10 | Furn & place topsoil (4") (160-7002) | SY | 14 | $15.00 | $110.00 | $500.00 | $35.00 | $105.00 |
| 11 | Block sodding (162-7002) | SY | 14 | $4.00 | $50.00 | $33.00 | $25.00 | $73.50 |
| 12 | Vegetative watering (168-7001) | TGL | 0.50 | $5.50 | $1,000.00 | $2,500.00 | $1,000.00 | $1,050.00 |
| 13 | Lime (commercial lime slurry) (260-7004) | TON | 95 | $325.00 | $362.00 | $325.00 | $350.00 | $525.00 |
| 14 | Lime TRT (existing material)(8") (260-7007) | SY | 5,746 | $7.00 | $10.00 | $15.00 | $6.50 | $12.50 |
| 15 | Prime coat (MC-30) (310-7004) | GAL | 895 | $6.00 | $10.00 | $30.25 | $12.00 | $29.29 |
| 16 | D-GR HMA type-B PG64-22 (341-7001) | TON | 1,464 | $140.00 | $295.00 | $246.00 | $175.00 | $238.08 |
| 17 | SP mixes SP-C sac-B PG70-28 (344-7025) | TON | 113 | $150.00 | $535.00 | $516.00 | $450.00 | $498.95 |
| 18 | Tack coat (344-7077) | GAL | 167 | $2.00 | $4.40 | $33.00 | $5.00 | $31.95 |
| 19 | Concrete pavement (CPCD) (8") (360-7018) | SY | 4,773 | $200.00 | $110.00 | $131.00 | $185.00 | $150.00 |
| 20 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 30 | $310.00 | $635.00 | $440.00 | $680.00 | $266.25 |
| 21 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 44 | $530.00 | $637.00 | $500.00 | $685.00 | $426.00 |
| 22 | Riprap (concrete)(CL B) (432-7005) | CY | 1 | $2,500.00 | $1,440.00 | $3,000.00 | $2,100.00 | |
| 23 | Cleaning and sealing joints (foam) (438-7010) | LF | 134 | $45.00 | $210.00 | $200.00 | $110.00 | $105.00 |
| 24 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 9,394.51 | $15.00 | $11.60 | $14.00 | $12.50 | $13.65 |
| 25 | Rail (handrail)(type B) (450-7059) | LF | 98 | $131.00 | $220.00 | $170.00 | $147.00 | |
| 26 | Removing structure (pipe) (496-7007) | LF | 8 | $24.00 | $30.00 | $200.00 | $75.00 | $105.00 |
| 27 | Mobilization (500-7001) | LS | 1 | $329,917 | $280,000 | $360,000 | $380,000 | $400,000 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 16 | $8,000.00 | $30,000 | $22,000 | $12,000 | $31,500 |
| 29 | Portable changeable message sign (503-7002) | EACH | 2 | $7,500.00 | $16,500 | $200.00 | $30,000 | $25,000 |
| 30 | TMA (stationary) (505-7001) | DAY | 235 | $190.00 | $203.50 | $300.00 | $500.00 | $200.00 |
| 31 | Temporary sediment control fence (install) (506-7039) | LF | 480 | $4.00 | $7.15 | $5.00 | $10.00 | $10.50 |
| 32 | Temporary sediment control fence (remove) (506-7041) | LF | 480 | $1.00 | $3.85 | $1.65 | $1.50 | $5.25 |
| 33 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 200 | $10.45 | $8.20 | $10.00 | $10.50 | |
| 34 | Biodegradable erosion control logs (remove) (506-7046) | LF | 200 | $3.85 | $1.65 | $1.50 | $5.25 | |
| 35 | Constructing detours (508-7001) | SY | 86 | $300.00 | $130.00 | $150.00 | $150.00 | |
| 36 | Remove and relay pavers (528-7003) | SY | 4,583 | $100.00 | $50.00 | $30.00 | $82.00 | $84.00 |
| 37 | Replacement pavers (528-7004) | SY | 4,233 | $100.00 | $55.00 | $64.00 | $95.00 | $15.75 |
| 38 | Concrete curb & gutter (type II) (529-7009) | LF | 1,606 | $90.00 | $35.00 | $36.00 | $46.00 | $52.50 |
| 39 | Driveways (concrete) (530-7006) | SY | 175 | $125.00 | $150.00 | $195.00 | $168.00 | |
| 40 | Concrete sidewalks (4") (531-7001) | SY | 1,171 | $52.00 | $70.00 | $91.20 | $89.00 | $84.00 |
| 41 | Curb ramps (type 1) (531-7005) | EACH | 16 | $3,700.00 | $2,600.00 | $2,520.00 | $3,000.00 | $2,500.00 |
| 42 | Curb ramps (type 6) (531-7009) | EACH | 1 | $2,600.00 | $3,360.00 | $4,750.00 | $2,500.00 | |
| 43 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 3 | $5,500.00 | $5,700.00 | $11,000 | $6,100.00 | $5,005.50 |
| 44 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 235 | $30.00 | $18.00 | $21.00 | $19.00 | $26.63 |
| 45 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 625 | $50.00 | $41.00 | $29.00 | $44.00 | $37.28 |
| 46 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 40 | $26.00 | $23.50 | $27.00 | $25.00 | $31.95 |
| 47 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 155 | $36.00 | $61.00 | $40.00 | $65.00 | $79.88 |
| 48 | Electrical conductor (no.8) bare (620-7007) | LF | 760 | $2.50 | $2.05 | $3.50 | $2.15 | $1.65 |
| 49 | Electrical conductor (no.8) insulated (620-7008) | LF | 1,520 | $3.00 | $2.45 | $4.00 | $2.61 | $1.76 |
| 50 | Electrical conductor (no.6) bare (620-7009) | LF | 395 | $3.00 | $2.35 | $4.00 | $2.47 | $1.86 |
| 51 | Electrical conductor (no.6) insulated (620-7010) | LF | 290 | $2.90 | $4.25 | $3.09 | $2.08 | |
| 52 | Ground box type D (162922) (624-7007) | EACH | 6 | $1,600.00 | $900.00 | $1,150.00 | $975.00 | $1,278.00 |
| 53 | Remove electrical services (628-7002) | EACH | 1 | $615.00 | $390.00 | $1,100.00 | $500.00 | $580.43 |
| 54 | Elc SRV type A 120/240 060(NS)AL(E)PS(U) (628-7003) | EACH | 1 | $6,850.00 | $10,050 | $13,000 | $10,750 | $7,135.50 |
| 55 | Elc SRV type D 120/240 060(NS)SS(E)SP(O) (628-7148) | EACH | 1 | $8,800.00 | $12,500 | $9,500.00 | $7,029.00 | |
| 56 | Aluminum signs (type A) (636-7001) | SF | 38.80 | $40.00 | $44.00 | $45.00 | $50.00 | $72.31 |
| 57 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 7 | $800.00 | $570.00 | $450.00 | $725.00 | $548.48 |
| 58 | Relocate SM RD SN sup&AM type S80 (644-7067) | EACH | 4 | $850.00 | $770.00 | $715.00 | $950.00 | $744.44 |
| 59 | Relocate SM RD SN sup&AM type TWT (644-7068) | EACH | 2 | $430.00 | $550.00 | $330.00 | $725.00 | $531.44 |
| 60 | Remove SM RD SN sup&AM (644-7073) | EACH | 3 | $151.00 | $110.00 | $165.00 | $125.00 | $105.44 |
| 61 | Work zone pavement marking removing (W)4"(solid) (662-7064) | LF | 8,573 | $0.50 | $1.40 | $3.00 | $1.50 | $5.25 |
| 62 | Work zone pavement marking removing (Y)4"(solid) (662-7097) | LF | 7,500 | $0.50 | $1.40 | $3.00 | $1.50 | $5.25 |
| 63 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 833 | $1.25 | $1.00 | $1.54 | $1.10 | $1.49 |
| 64 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 648 | $0.50 | $0.70 | $1.65 | $0.75 | $1.60 |
| 65 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 472 | $0.75 | $0.70 | $1.65 | $0.75 | $1.60 |
| 66 | Prefabricated PM type C (W)(12")(solid) (668-7087) | LF | 436 | $5.00 | $8.05 | $6.05 | $9.00 | $5.86 |
| 67 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 146 | $15.00 | $15.40 | $12.10 | $17.00 | $11.72 |
| 68 | Prefabricated PM type C (W)(RR crossing) (668-7108) | EACH | 1 | $625.00 | $1,430.00 | $853.60 | $1,500.00 | $826.44 |
| 69 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 110 | $4.25 | $5.50 | $6.88 | $6.00 | $6.66 |
| 70 | Traffic button type Y (672-7008) | EACH | 300 | $4.50 | $5.50 | $5.50 | $6.00 | $5.33 |
| 71 | Eliminating existing PM & markers (4") (677-7001) | LF | 2,720 | $0.50 | $0.60 | $1.10 | $0.65 | $1.07 |
| 72 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $38,000 | $30,000 | $48,000 | $32,000 | $38,340 |
| 73 | Removing traffic signals (680-7004) | EACH | 2 | $10,000 | $4,885.00 | $4,500.00 | $5,200.00 | $5,325.00 |
| 74 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 8 | $400.00 | $370.00 | $450.00 | $390.00 | $324.83 |
| 75 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 8 | $400.00 | $370.00 | $450.00 | $390.00 | $324.83 |
| 76 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 8 | $400.00 | $370.00 | $450.00 | $390.00 | $324.83 |
| 77 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $1,000.00 | $860.00 | $1,300.00 | $920.00 | $734.85 |
| 78 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 8 | $250.00 | $285.00 | $250.00 | $300.00 | $175.73 |
| 79 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 505 | $3.00 | $2.35 | $3.50 | $2.50 | $2.82 |
| 80 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 185 | $3.00 | $3.25 | $5.00 | $3.50 | $2.82 |
| 81 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 80 | $3.50 | $2.90 | $5.00 | $3.10 | $3.67 |
| 82 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 405 | $4.00 | $3.80 | $5.00 | $4.10 | $3.67 |
| 83 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 300 | $3.50 | $7.20 | $11.00 | $7.70 | $7.24 |
| 84 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 2 | $10,244 | $14,100 | $20,000 | $15,000 | $14,058 |
| 85 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 2 | $11,701 | $14,700 | $20,000 | $16,000 | $14,697 |
| 86 | Pedestrian pole assembly (687-7001) | EACH | 4 | $3,858.00 | $4,750.00 | $4,100.00 | $5,000.00 | $2,662.50 |
| 87 | Pedestrian detect push button (APS) (688-7001) | EACH | 8 | $1,075.00 | $1,100.00 | $1,200.00 | $1,150.00 | $1,038.38 |
| 88 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $3,931.00 | $4,121.50 | $5,000.00 | $4,400.00 | $4,047.00 |
| 89 | Removal of control cabinet(pole MNT) (690-7041) | EACH | 1 | $970.00 | $1,100.00 | $1,000.00 | $596.40 | |
| 90 | ITS com CBL (ethernet) (6005-7001) | LF | 30 | $3.00 | $2.00 | $4.50 | $3.00 | $2.98 |
| 91 | Bbu system (external battery cabinet) (6007-7001) | EACH | 1 | $9,205.00 | $10,500 | $10,000 | $10,863 | |
| 92 | RVDS (presence detection only) (6008-7001) | EACH | 4 | $6,600.00 | $7,775.00 | $12,000 | $8,300.00 | $12,082 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 1, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.