Lime (hyd, com, or QK(slurry)), TxDOT 260-6016
Low bidders on TxDOT contracts carried a median of $212.00 per TON for this item, from 07 MAY 2020 to 10 JUL 2024, across 57 low bids. Half of all 270 bids fell between $180.00 and $289.00.
- Owner
- Texas DOT
- Item
- 260-6016
- Unit
- TON
- Data through
- 19 NOV 2026
TxDOT prints this item as “LIME (HYD, COM, OR QK(SLURRY))”.
TxDOT has bid this work under another code: 2606016 on lettings from 07 MAY 2020 to 10 JUL 2024 (273 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 9 | 9 | $182.00 | 60 | $181.72 |
| 2021 | 23 | 23 | $185.00 | 121 | $193.63 |
| 2022 | 7 | 7 | $230.00 | 24 | $242.50 |
| 2023 | 9 | 9 | $300.91 | 30 | $346.00 |
| 2024 | 9 | 9 | $332.00 | 35 | $332.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Dallas District | 11 | $297.98 | 56 | $256.28 |
| Fort Worth District | 9 | $291.50 | 54 | $200.00 |
| Beaumont District | 13 | $210.00 | 50 | $207.50 |
| San Antonio District | 7 | $245.00 | 36 | $202.65 |
| Houston District | 4 | $184.56 | 23 | $182.47 |
| Bryan District | 3 | $166.00 | 18 | $160.00 |
| Waco District | 3 | $200.00 | 10 | $183.70 |
| Yoakum District | 3 | $312.18 | 8 | $357.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 10 to 229 | 14 | $258.00 |
| 230 to 695 | 14 | $232.50 |
| 766 to 3,606 | 14 | $184.56 |
| 3,937 to 11,464 | 15 | $230.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 24 | 9 (38%) |
| Ragle Construction, Inc. | 9 | 5 (56%) |
| Sema Construction, Inc. | 7 | 5 (71%) |
| Harper Brothers Construction LLC | 12 | 4 (33%) |
| Texas Materials Group, Inc. | 13 | 2 (15%) |
| Angel Brothers Holdings Corp. | 7 | 2 (29%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 JUL 2024 | 07243207 | Dallas District | 589 | $371.00 | $380.50 | $310.00 | 6 | Harper Brothers Construction LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 7,057 | $400.00 | $376.00 | $320.00 | 2 | Zachry Construction Corporation | TxDOT |
| 09 JUL 2024 | 07243006 | Pharr District | 302 | $320.00 | $260.00 | $350.00 | 2 | Foremost Paving, Inc. | TxDOT |
| 05 JUN 2024 | 06243025 | Dallas District | 75 | $320.00 | $400.00 | $340.00 | 3 | Select Maintenance, L.L.C. | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 4,378 | $312.18 | $312.18 | $320.00 | 3 | Pulice Construction, Inc. | TxDOT |
| 03 MAY 2024 | 05243202 | Fort Worth District | 3,347 | $325.00 | $347.00 | $300.00 | 5 | Zachry Construction Corporation | TxDOT |
| 02 MAY 2024 | 05243001 | Beaumont District | 3,937 | $450.00 | $450.00 | $200.00 | 1 | Williams Brothers Construction Co., Inc. | TxDOT |
| 05 MAR 2024 | 03243004 | Dallas District | 203 | $350.00 | $322.62 | $300.00 | 7 | Indus Road & Bridge, Inc. | TxDOT |
| 04 JAN 2024 | 01243001 | Dallas District | 4,909 | $332.00 | $305.50 | $320.00 | 6 | Mario Sinacola & Sons Excavating, Inc. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 5,092 | $400.00 | $365.00 | $275.00 | 3 | Williams Brothers Construction Co., Inc. | TxDOT |
| 06 SEP 2023 | 09233001 | Beaumont District | 362 | $482.96 | $457.21 | $295.70 | 4 | Pulice Construction, Inc. | TxDOT |
| 06 SEP 2023 | 09233015 | Fort Worth District | 229 | $298.00 | $350.00 | $300.00 | 3 | Ed Bell Construction Company | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 2,666 | $375.00 | $348.75 | $300.00 | 2 | Jordan Foster Construction, LLC | TxDOT |
| 28 JUN 2023 | 06233602 | Yoakum District | 9,535 | $250.00 | $335.00 | $200.00 | 2 | Webber, LLC | TxDOT |
| 01 JUN 2023 | 06233002 | San Antonio District | 9,358 | $340.85 | $340.85 | $252.00 | 3 | Webber, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.