NS envir. protection transportation and disposal of contaminated soil, VDOT 522SX20-0008
Low bidders on VDOT contracts carried a median of $119.79 per TON for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 3 bids fell between $457.90 and $991.50.
- Owner
- Virginia DOT
- Item
- 522SX20-0008
- Unit
- TON
- Data through
- 28 OCT 2026
VDOT prints this item as “NS ENVIR. PROTECTION TRANSPORTATION AND DISPOSAL OF CONTAMINATED SOIL”.
VDOT has bid this work under more than one code: 70525 on lettings from 25 MAR 2009 to 28 JUL 2021 (126 bids); 522SX20-0008 on lettings from 22 OCT 2025 to 22 OCT 2025 (3 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2009 | 2 | 2 | $96.25 | 6 | $111.24 |
| 2011 | 2 | 1 | $198.00 | 5 | $104.50 |
| 2012 | 2 | 2 | $74.25 | 6 | $85.10 |
| 2013 | 1 | 1 | $100.00 | 3 | $100.00 |
| 2014 | 3 | 5 | $83.00 | 15 | $76.00 |
| 2015 | 4 | 5 | $42.00 | 12 | $83.93 |
| 2016 | 5 | 5 | $34.00 | 12 | $77.00 |
| 2017 | 4 | 6 | $129.00 | 18 | $83.50 |
| 2018 | 6 | 7 | $100.00 | 21 | $69.90 |
| 2019 | 3 | 3 | $225.00 | 6 | $100.19 |
| 2020 | 5 | 5 | $125.00 | 12 | $115.62 |
| 2021 | 3 | 3 | $60.00 | 9 | $93.00 |
| 2025 | 1 | 1 | $119.79 | 3 | $796.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Richmond | 27 | $98.00 | 74 | $84.75 |
| Salem | 5 | $125.00 | 14 | $125.00 |
| Lynchburg | 4 | $100.00 | 11 | $100.00 |
| Fredericksburg | 3 | $100.00 | 9 | $100.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 5 to 136 | 11 | $157.50 |
| 140 to 315 | 12 | $71.50 |
| 367 to 580 | 11 | $100.00 |
| 677 to 1,607 | 12 | $69.95 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Branscome Inc. | 8 | 5 (63%) |
| J. L. Kent & Sons, Inc. | 10 | 4 (40%) |
| Curtis Contracting, Inc. | 5 | 3 (60%) |
| J. R. Caskey, Inc. | 8 | 2 (25%) |
| Fielder'S Choice Enterprises, Inc. | 11 | 1 (9%) |
| Central Contracting Company, Inc. | 5 | 0 (0%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 OCT 2025 | C0000120443M01 | Richmond | 28 | $119.79 | $796.00 | 3 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 441 | $175.00 | $140.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 23 JUN 2021 | C0000107081C01 | Culpeper | 309 | $12.00 | $84.53 | 3 | J. L. Kent & Sons, Inc. | VDOT |
| 24 MAR 2021 | C000106197C01 | Richmond | 167.52 | $60.00 | $83.50 | 3 | Jireh Construction Company, Inc. | VDOT |
| 18 NOV 2020 | C0000109704M01 | Lynchburg | 189 | $125.00 | $105.00 | 2 | Pearson Construction, Inc. | VDOT |
| 21 OCT 2020 | C0000109537C01 | Lynchburg | 438 | $100.00 | $106.25 | 3 | MCC Acquisition, LC DBA Virginia-Carolina Paving Co. | VDOT |
| 23 SEP 2020 | C0000109321C01 | Richmond | 381 | $200.00 | $142.25 | 2 | Allan Myers Va, Inc. | VDOT |
| 27 MAY 2020 | C0000109311C01B | Richmond | 285 | $100.00 | $100.00 | 3 | Jireh Construction Company, Inc. | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 6 | $180.00 | $365.00 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 24 APR 2019 | C0000107796C01B | Richmond | 158 | $225.00 | $225.00 | 1 | Allan Myers Va, Inc. | VDOT |
| 24 APR 2019 | C0000109546M01 | Lynchburg | 49 | $100.00 | $100.00 | 3 | El-X Enterprises | VDOT |
| 20 MAR 2019 | C0000111711C01 | Hampton Roads | 520 | $300.00 | $200.19 | 2 | Allan Myers Va, Inc. | VDOT |
| 19 DEC 2018 | C000103084C501 | Fredericksburg | 130 | $158.69 | $158.69 | 3 | Henderson Construction Co., Inc. | VDOT |
| 19 DEC 2018 | C000104661C01 | Richmond | 420 | $68.00 | $56.70 | 3 | Shoosmith Construction, Inc. | VDOT |
| 22 AUG 2018 | C0000090018C01 | Richmond | 833 | $69.90 | $37.20 | 3 | J. L. Kent & Sons, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.