NS water utility 6" water meter & vault, VDOT 520SX20-0086
Low bidders on VDOT contracts carried a median of $67,000 per EACH for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 2 bids fell between $57,227 and $63,742.
- Owner
- Virginia DOT
- Item
- 520SX20-0086
- Unit
- EACH
- Data through
- 28 OCT 2026
VDOT prints this item as “NS WATER UTILITY 6" WATER METER & VAULT”.
VDOT has bid this work under more than one code: 40992 on lettings from 26 FEB 2002 to 28 JUL 2021 (542 bids); 520SX20-0086 on lettings from 22 APR 2026 to 22 APR 2026 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 5 | 16 | $4,237.50 | 48 | $4,150.00 |
| 2003 | 1 | 7 | $8,700.00 | 21 | $10,185 |
| 2004 | 4 | 10 | $1,906.42 | 29 | $1,700.00 |
| 2005 | 3 | 23 | $2,200.00 | 67 | $2,155.59 |
| 2006 | 4 | 11 | $4,766.39 | 32 | $5,500.00 |
| 2007 | 9 | 14 | $3,036.00 | 41 | $3,372.00 |
| 2008 | 5 | 12 | $1,363.50 | 36 | $1,413.50 |
| 2009 | 4 | 11 | $6,000.00 | 33 | $8,630.64 |
| 2010 | 9 | 15 | $1,260.00 | 45 | $1,625.00 |
| 2011 | 4 | 4 | $5,266.88 | 18 | $5,470.00 |
| 2012 | 1 | 1 | $9,402.04 | 3 | $9,402.04 |
| 2013 | 5 | 6 | $2,725.00 | 18 | $1,950.00 |
| 2014 | 2 | 3 | $5,000.00 | 9 | $3,250.00 |
| 2015 | 9 | 13 | $3,400.00 | 34 | $3,564.40 |
| 2016 | 3 | 6 | $2,620.16 | 17 | $3,079.33 |
| 2017 | 2 | 6 | $3,430.00 | 18 | $3,380.00 |
| 2018 | 2 | 2 | $7,456.00 | 6 | $3,855.86 |
| 2019 | 2 | 6 | $3,795.05 | 14 | $4,722.32 |
| 2020 | 2 | 3 | $3,500.00 | 8 | $3,900.00 |
| 2021 | 4 | 13 | $6,000.00 | 39 | $5,796.00 |
| 2026 | 1 | 1 | $67,000 | 2 | $60,485 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Northern Virginia | 52 | $3,883.00 | 162 | $3,907.00 |
| Hampton Roads | 42 | $2,742.00 | 117 | $2,984.00 |
| Salem | 27 | $3,500.00 | 80 | $3,450.00 |
| Richmond | 21 | $3,920.00 | 61 | $3,500.00 |
| Bristol | 10 | $9,051.02 | 30 | $9,817.50 |
| Staunton | 10 | $3,588.25 | 29 | $3,080.40 |
| Fredericksburg | 10 | $3,614.66 | 28 | $3,678.00 |
| Lynchburg | 9 | $1,812.84 | 25 | $2,435.87 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 1 | 45 | $8,500.00 |
| 1 to 2 | 46 | $3,545.05 |
| 2 to 4 | 46 | $3,820.50 |
| 4 to 108 | 46 | $2,929.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Martin and Gass, Incorporated | 35 | 13 (37%) |
| General Excavation, Inc. | 25 | 10 (40%) |
| Allegheny Construction Company, Inc. | 29 | 9 (31%) |
| Warwick Plumbing & Heating Corporation | 17 | 9 (53%) |
| The Kennedy Company of Va, Inc. | 19 | 7 (37%) |
| W. C. English, Incorporated | 10 | 7 (70%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 APR 2026 | C0000119163C01 | Lynchburg | 1 | $67,000 | $60,485 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 2 | $6,000.00 | $6,000.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 1 | $4,500.00 | $4,000.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 28 JUL 2021 | C0000000688C02 | Salem | 14 | $4,100.00 | $4,100.00 | 3 | Allegheny Construction Company, Inc. | VDOT |
| 23 JUN 2021 | C0000108654C01 | Richmond | 1 | $18,000 | $45,000 | 3 | J. R. Caskey, Inc. | VDOT |
| 23 JUN 2021 | C0000108654C01 | Richmond | 2 | $47,847 | $40,000 | 3 | J. R. Caskey, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 2 | $26,055 | $26,055 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 2 | $2,860.49 | $2,860.49 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 14 | $3,321.43 | $5,500.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 2 | $3,950.20 | $2,535.75 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 2 | $7,758.73 | $5,796.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 1 | $8,631.59 | $7,003.50 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000110433B43 | Northern Virginia | 1 | $15,340 | $15,340 | 3 | Clearwater Construction, Inc. | VDOT |
| 20 JAN 2021 | C0000109988C01 | Richmond | 1 | $3,300.00 | $3,500.00 | 3 | Abernathy Construction Corporation | VDOT |
| 22 APR 2020 | C0000107061C01 | Salem | 2 | $4,300.00 | $4,700.00 | 3 | Kanawha Stone Company, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.