NS traffic sign U-type steel post, VDOT 700SX20-0019
Low bidders on VDOT contracts carried a median of $103.46 per LF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 4 bids fell between $27.98 and $110.36.
- Owner
- Virginia DOT
- Item
- 700SX20-0019
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “NS TRAFFIC SIGN U-TYPE STEEL POST”.
VDOT has bid this work under more than one code: 50900 on lettings from 17 DEC 2002 to 23 JUN 2021 (626 bids); 700SX20-0019 on lettings from 22 JUL 2026 to 22 JUL 2026 (4 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 1 | 3 | $9.90 | 9 | $15.00 |
| 2003 | 5 | 12 | $25.00 | 30 | $24.00 |
| 2004 | 1 | 1 | $12.00 | 3 | $15.00 |
| 2005 | 10 | 18 | $21.70 | 44 | $22.50 |
| 2006 | 10 | 19 | $27.23 | 49 | $33.00 |
| 2007 | 11 | 19 | $30.00 | 52 | $33.16 |
| 2008 | 12 | 21 | $31.77 | 60 | $33.00 |
| 2009 | 8 | 15 | $15.40 | 44 | $21.25 |
| 2010 | 11 | 12 | $23.34 | 36 | $23.34 |
| 2011 | 8 | 17 | $25.80 | 51 | $20.00 |
| 2012 | 2 | 2 | $27.00 | 6 | $26.75 |
| 2013 | 3 | 10 | $18.90 | 19 | $21.00 |
| 2014 | 4 | 13 | $45.54 | 38 | $36.11 |
| 2015 | 7 | 33 | $28.27 | 65 | $22.00 |
| 2016 | 14 | 29 | $31.00 | 78 | $28.73 |
| 2017 | 2 | 4 | $16.52 | 12 | $31.52 |
| 2018 | 1 | 2 | $25.15 | 6 | $30.90 |
| 2019 | 2 | 3 | $30.94 | 7 | $30.94 |
| 2020 | 3 | 3 | $90.00 | 8 | $70.14 |
| 2021 | 1 | 2 | $29.00 | 6 | $37.75 |
| 2026 | 1 | 1 | $103.46 | 4 | $68.72 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Hampton Roads | 81 | $26.70 | 188 | $25.40 |
| Northern Virginia | 46 | $22.94 | 131 | $25.00 |
| Staunton | 33 | $25.00 | 96 | $31.24 |
| Culpeper | 19 | $34.00 | 53 | $34.00 |
| Lynchburg | 15 | $25.40 | 45 | $18.00 |
| Fredericksburg | 17 | $44.00 | 44 | $42.50 |
| Salem | 16 | $27.28 | 35 | $27.28 |
| Richmond | 10 | $13.20 | 30 | $17.50 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 3 to 42 | 59 | $30.00 |
| 44 to 95 | 60 | $28.64 |
| 96 to 300 | 60 | $27.25 |
| 300 to 17,036 | 60 | $21.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| General Excavation, Inc. | 43 | 19 (44%) |
| B & B Signal Co., L.L.C. | 19 | 12 (63%) |
| Branch Highways, Inc. | 12 | 11 (92%) |
| Branscome Inc. | 19 | 9 (47%) |
| A & M Concrete Corp. | 12 | 8 (67%) |
| Howard Brothers Contractor, Inc. | 18 | 7 (39%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 22 JUL 2026 | C0000122147C01C | Richmond | 10 | $103.46 | $68.72 | 4 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 23 JUN 2021 | C0000118551N01 | Hampton Roads | 250 | $48.00 | $58.40 | 3 | Ces Consulting, LLC | VDOT |
| 23 JUN 2021 | C0000118551N01 | Hampton Roads | 150 | $10.00 | $11.00 | 3 | Ces Consulting, LLC | VDOT |
| 26 AUG 2020 | C0000112923P01 | Hampton Roads | 42 | $205.10 | $205.10 | 3 | Aldridge Electric, Inc. | VDOT |
| 24 JUN 2020 | C0000107797C01 | Richmond | 52 | $90.00 | $50.28 | 3 | Allan Myers Va, Inc. | VDOT |
| 26 FEB 2020 | C000116236N01 | Staunton | 57 | $23.00 | $29.50 | 2 | General Excavation, Inc. | VDOT |
| 21 AUG 2019 | C00114881N01 | Hampton Roads | 300 | $25.00 | $21.57 | 3 | Curtis Contracting, Inc. | VDOT |
| 27 FEB 2019 | C0000109376N01 | Staunton | 48 | $30.94 | $30.94 | 2 | Kickin Asphalt Paving and Excavating, LLC | VDOT |
| 27 FEB 2019 | C0000109376N01 | Staunton | 11 | $31.24 | $31.24 | 2 | Kickin Asphalt Paving and Excavating, LLC | VDOT |
| 28 MAR 2018 | 0000109377N01 | Staunton | 22 | $28.30 | $33.49 | 3 | Kickin Asphalt Paving and Excavating, LLC | VDOT |
| 28 MAR 2018 | 0000109377N01 | Staunton | 63 | $22.00 | $26.03 | 3 | Kickin Asphalt Paving and Excavating, LLC | VDOT |
| 22 FEB 2017 | C0000108057C01B | Staunton | 176 | $19.36 | $39.04 | 3 | Phillips Construction, LLC | VDOT |
| 22 FEB 2017 | C0000108057C01B | Staunton | 62 | $13.68 | $39.04 | 3 | Phillips Construction, LLC | VDOT |
| 22 FEB 2017 | C0000108057C01B | Staunton | 285 | $7.57 | $39.04 | 3 | Phillips Construction, LLC | VDOT |
| 25 JAN 2017 | C0000011908C04 | Salem | 510 | $24.00 | $20.00 | 3 | Fielder'S Choice Enterprises, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.