NS traffic signalization antenna cable, VDOT 700SX20-0009
Low bidders on VDOT contracts carried a median of $12.96 per LF for this item, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 4 bids fell between $4.25 and $9.48.
- Owner
- Virginia DOT
- Item
- 700SX20-0009
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “NS TRAFFIC SIGNALIZATION ANTENNA CABLE”.
VDOT has bid this work under more than one code: 52001 on lettings from 26 FEB 2002 to 17 NOV 2021 (636 bids); 700SX20-0009 on lettings from 17 DEC 2025 to 27 MAY 2026 (4 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 7 | 28 | $5.57 | 82 | $5.57 |
| 2003 | 5 | 6 | $6.75 | 14 | $6.80 |
| 2004 | 7 | 18 | $2.97 | 42 | $2.97 |
| 2005 | 5 | 15 | $8.00 | 37 | $5.60 |
| 2006 | 6 | 20 | $4.95 | 56 | $5.50 |
| 2007 | 5 | 16 | $1.96 | 36 | $1.83 |
| 2008 | 3 | 5 | $22.38 | 15 | $21.00 |
| 2009 | 8 | 24 | $2.35 | 72 | $2.02 |
| 2010 | 10 | 30 | $1.97 | 90 | $1.93 |
| 2011 | 5 | 11 | $1.64 | 32 | $1.62 |
| 2012 | 3 | 5 | $6.20 | 9 | $6.20 |
| 2013 | 7 | 10 | $11.27 | 25 | $6.00 |
| 2014 | 9 | 15 | $4.50 | 44 | $5.04 |
| 2015 | 6 | 7 | $50.00 | 16 | $32.62 |
| 2016 | 5 | 9 | $14.50 | 22 | $12.93 |
| 2017 | 2 | 4 | $7.25 | 12 | $3.59 |
| 2018 | 1 | 1 | $6.72 | 2 | $4.86 |
| 2019 | 1 | 1 | $2.00 | 2 | $1.84 |
| 2020 | 4 | 6 | $3.22 | 13 | $3.30 |
| 2021 | 2 | 3 | $1.75 | 9 | $3.99 |
| 2025 | 1 | 1 | $19.91 | 2 | $12.46 |
| 2026 | 1 | 1 | $6.00 | 2 | $4.00 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Hampton Roads | 57 | $1.70 | 165 | $1.75 |
| Richmond | 45 | $10.00 | 120 | $8.98 |
| Fredericksburg | 44 | $2.50 | 118 | $2.95 |
| Salem | 33 | $6.00 | 82 | $3.95 |
| Staunton | 32 | $6.00 | 79 | $5.55 |
| Culpeper | 11 | $6.30 | 31 | $6.00 |
| Northern Virginia | 9 | $5.00 | 25 | $3.70 |
| Lynchburg | 4 | $1.84 | 12 | $1.76 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 5 to 50 | 59 | $25.00 |
| 60 to 470 | 59 | $6.00 |
| 475 to 1,500 | 59 | $1.70 |
| 1,500 to 22,000 | 59 | $1.46 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Branscome Inc. | 27 | 17 (63%) |
| Blakemore Construction Corporation | 30 | 15 (50%) |
| Midasco, Incorporated | 22 | 15 (68%) |
| Richardson-Wayland Electrical Co. LLC | 56 | 14 (25%) |
| General Excavation, Inc. | 31 | 13 (42%) |
| Key Construction Company, Incorporated | 15 | 13 (87%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 MAY 2026 | C0000119644C01 | Staunton | 390 | $6.00 | $4.00 | 2 | Arthur Construction Co., Inc. | VDOT |
| 17 DEC 2025 | C0000119474C01 | Salem | 250 | $19.91 | $12.46 | 2 | Richardson-Wayland-Ferreira, LLC | VDOT |
| 17 NOV 2021 | C0000106670C01 | Fredericksburg | 775 | $3.99 | $4.50 | 3 | J. L. Kent & Sons, Inc. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 1,500 | $1.05 | $2.59 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 27 OCT 2021 | C0000119130C01 | Staunton | 1,500 | $1.75 | $1.93 | 3 | B & B Signal Co., L.L.C. | VDOT |
| 18 NOV 2020 | C0000109814C01 | Northern Virginia | 235 | $2.00 | $2.00 | 3 | Tavares Concrete Co., Inc. | VDOT |
| 22 JUL 2020 | C0000109440C01 | Bristol | 2,225 | $3.30 | $3.27 | 2 | Jones Road & Bridge, Inc. | VDOT |
| 25 MAR 2020 | C0000018003C01 | Staunton | 2,945 | $1.10 | $5.05 | 2 | General Excavation, Inc. | VDOT |
| 25 MAR 2020 | C0000018003C01 | Staunton | 195 | $3.15 | $6.58 | 2 | General Excavation, Inc. | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 145 | $6.50 | $4.80 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 22 JAN 2020 | C000111370C01B | Salem | 10 | $28.00 | $1,614.00 | 2 | Allegheny Construction Company, Inc. | VDOT |
| 20 MAR 2019 | C0000111711C01 | Hampton Roads | 11,115 | $2.00 | $1.84 | 2 | Allan Myers Va, Inc. | VDOT |
| 25 APR 2018 | C0000109326N01 | Staunton | 422 | $6.72 | $4.86 | 2 | M & F Concrete, Inc. | VDOT |
| 26 APR 2017 | C0000107044C01 | Hampton Roads | 3,820 | $4.00 | $4.00 | 3 | Branch Civil, Inc. | VDOT |
| 26 APR 2017 | C0000107044C01 | Hampton Roads | 3,235 | $1.00 | $1.61 | 3 | Branch Civil, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.