WisDOT contract 20250114019 bid tabulation
Oak Creek - Milwaukee; College Ave to Layton Ave (STH 241, Milwaukee County Oak Creek - Milwaukee). Let by Wisconsin DOT on January 14, 2025, Milwaukee. 4 bids received; low bid $6,164,846 by Payne and Dolan, Inc.
- Owner
- Wisconsin DOT
- Letting
- 14 JAN 2025
- Pay items
- 218
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Payne and Dolan, Inc | $6,164,846 | Low |
| 2 | Zignego Company, Inc. | $6,204,599 | +1.0% |
| 3 | Lalonde Contractors Incorporated | $6,328,624 | +3.0% |
| 4 | Stark Pavement Corporation | $6,567,166 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Payne and Dolan, Inc | 2. Zignego Company, Inc. | 3. Lalonde Contractors Incorporated | 4. Stark Pavement Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0120) | ID | 51 | $35.42 | $34.73 | $58.00 | $34.73 |
| 2 | Grubbing (201.0220) | ID | 51 | $36.91 | $36.19 | $8.00 | $36.19 |
| 3 | Removing concrete pavement (204.0100) | SY | 511 | $16.24 | $20.00 | $12.66 | $15.00 |
| 4 | Removing asphaltic surface (204.0110) | SY | 233 | $15.30 | $20.00 | $13.19 | $15.00 |
| 5 | Removing asphaltic surface butt joints (204.0115) | SY | 200 | $25.00 | $25.00 | $25.00 | $3.00 |
| 6 | Removing asphaltic surface milling (204.0120) | SY | 103,631 | $2.55 | $2.55 | $2.55 | $3.00 |
| 7 | Removing curb (204.0130) | LF | 132 | $10.20 | $10.00 | $11.07 | $10.00 |
| 8 | Removing curb & gutter (204.0150) | LF | 4,701 | $7.07 | $10.00 | $8.01 | $10.00 |
| 9 | Removing concrete sidewalk (204.0155) | SY | 3,366 | $7.87 | $10.00 | $8.52 | $10.00 |
| 10 | Removing concrete bases (204.0195) | EACH | 21 | $357.00 | $500.00 | $350.00 | $350.00 |
| 11 | Removing manholes (204.0210) | EACH | 4 | $612.00 | $500.00 | $600.00 | $600.00 |
| 12 | Removing inlets (204.0220) | EACH | 14 | $510.00 | $400.00 | $500.00 | $500.00 |
| 13 | Removing storm sewer (size) 001. (12-inch) (204.0245) | LF | 134 | $20.40 | $20.00 | $20.00 | $20.00 |
| 14 | Removing storm sewer (size) 002. (18-inch) (204.0245) | LF | 5 | $20.40 | $100.00 | $20.00 | $20.00 |
| 15 | Removing storm sewer (size) 003. (24-inch) (204.0245) | LF | 5 | $20.40 | $100.00 | $20.00 | $20.00 |
| 16 | Removing storm sewer (size) 004. (30-inch) (204.0245) | LF | 5 | $25.50 | $100.00 | $25.00 | $25.00 |
| 17 | Removing storm sewer (size) 005. (36-inch) (204.0245) | LF | 5 | $25.50 | $100.00 | $25.00 | $25.00 |
| 18 | Removing storm sewer (size) 006. (48-inch) (204.0245) | LF | 17 | $35.70 | $100.00 | $35.00 | $35.00 |
| 19 | Removing (item description) 001. removing traffic signals (STH 241 & ramsey ave) (204.9060.S) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 20 | Removing (item description) 002. removing traffic signals (STH 241 & parnell ave) (204.9060.S) | EACH | 1 | $3,570.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 21 | Removing (item description) 003. removing traffic signals (STH 241 & grange ave) (204.9060.S) | EACH | 1 | $6,630.00 | $6,500.00 | $6,500.00 | $6,500.00 |
| 22 | Removing (item description) 004. removing traffic signals (STH 241 & edgerton ave) (204.9060.S) | EACH | 1 | $2,040.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 23 | Removing (item description) 005. removing traffic signals (STH 241 & layton ave) (204.9060.S) | EACH | 1 | $2,040.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 24 | Removing (item description) 006. removing wood planter (204.9060.S) | EACH | 1 | $966.57 | $520.00 | $953.00 | $520.00 |
| 25 | Removing (item description) 001. removing landscape retaining wall (204.9090.S) | LF | 295 | $20.40 | $20.00 | $14.55 | $20.00 |
| 26 | Excavation common (205.0100) | CY | 413 | $39.83 | $50.00 | $59.12 | $50.00 |
| 27 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 88.50 | $117.30 | $75.00 | $82.30 | $210.00 |
| 28 | Backfill granular grade 1 (209.1500) | TON | 91 | $20.40 | $50.00 | $45.00 | $35.00 |
| 29 | Finishing roadway (project) 001. 2265-18-70 (213.0100) | EACH | 1 | $3,000.00 | $1,000.00 | $3,000.00 | $5,000.00 |
| 30 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 36 | $55.00 | $100.00 | $50.57 | $50.00 |
| 31 | Concrete base 9-inch (320.0155) | SY | 500 | $55.77 | $90.00 | $70.86 | $90.00 |
| 32 | Removing pavement for base patching (390.0100) | CY | 2,915 | $70.53 | $60.00 | $82.55 | $90.00 |
| 33 | Base patching concrete hes (390.0305) | CY | 2,872 | $268.33 | $274.00 | $268.81 | $230.00 |
| 34 | Base patching concrete shes (390.0405) | CY | 41 | $612.00 | $500.00 | $488.31 | $500.00 |
| 35 | Coloring concrete wisdot red (405.0100) | CY | 16 | $112.20 | $200.00 | $147.56 | $535.90 |
| 36 | Drilled tie bars (416.0610) | EACH | 3,922 | $9.30 | $15.00 | $11.08 | $10.00 |
| 37 | Drilled dowel bars (416.0620) | EACH | 2,976 | $20.00 | $30.00 | $13.90 | $15.00 |
| 38 | Concrete pavement repair (416.1710) | SY | 11 | $224.82 | $300.00 | $118.91 | $180.00 |
| 39 | Concrete pavement repair shes (416.1715) | SY | 28 | $639.54 | $300.00 | $182.43 | $260.00 |
| 40 | Concrete pavement replacement (416.1720) | SY | 255 | $83.82 | $100.00 | $112.79 | $180.00 |
| 41 | Concrete pavement replacement shes (416.1725) | SY | 1,274 | $154.43 | $125.00 | $173.40 | $212.00 |
| 42 | Tack coat (455.0605) | GAL | 11,521 | $2.25 | $2.25 | $2.25 | $3.00 |
| 43 | Incentive density HMA pavement (460.2000) | DOL | 13,660 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | HMA pavement 3 MT 58-28 S (460.6223) | TON | 11,999 | $74.05 | $74.05 | $74.05 | $75.55 |
| 45 | HMA pavement 4 MT 58-28 H (460.6424) | TON | 9,332 | $86.45 | $86.45 | $86.45 | $85.15 |
| 46 | Asphaltic surface patching (465.0110) | TON | 16 | $290.00 | $290.00 | $290.00 | $225.00 |
| 47 | Asphaltic surface driveways and field entrances (465.0120) | TON | 9 | $290.00 | $290.00 | $290.00 | $225.00 |
| 48 | Asphaltic surface temporary (465.0125) | TON | 1,150 | $65.00 | $65.00 | $65.00 | $60.00 |
| 49 | Concrete collars for pipe (520.8000) | EACH | 12 | $612.00 | $685.00 | $600.00 | $600.00 |
| 50 | Concrete curb & gutter 31-inch (601.0331) | LF | 4,651 | $52.55 | $45.00 | $45.99 | $48.40 |
| 51 | Concrete curb & gutter 18-inch type D (601.0407) | LF | 211 | $60.18 | $45.00 | $46.36 | $48.40 |
| 52 | Concrete curb pedestrian (601.0600) | LF | 1,045 | $28.82 | $45.00 | $50.42 | $44.00 |
| 53 | Concrete sidewalk 5-inch (602.0410) | SF | 31,151 | $8.48 | $9.00 | $8.09 | $10.50 |
| 54 | Curb ramp detectable warning field yellow (602.0505) | SF | 1,200 | $45.14 | $45.00 | $44.10 | $50.00 |
| 55 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 404 | $61.20 | $60.00 | $58.36 | $60.00 |
| 56 | Concrete driveway hes 6-inch (602.0860) | SY | 68 | $81.60 | $75.00 | $66.02 | $90.00 |
| 57 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 138 | $122.40 | $76.00 | $120.00 | $120.00 |
| 58 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 14 | $132.60 | $80.00 | $130.00 | $130.00 |
| 59 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 18 | $142.80 | $105.00 | $140.00 | $140.00 |
| 60 | Reconstructing manholes (611.0420) | EACH | 1 | $2,550.00 | $1,350.00 | $2,500.00 | $2,500.00 |
| 61 | Reconstructing inlets (611.0430) | EACH | 8 | $1,683.00 | $1,400.00 | $1,650.00 | $1,650.00 |
| 62 | Manhole covers type J (611.0530) | EACH | 8 | $765.00 | $650.00 | $750.00 | $750.00 |
| 63 | Inlet covers type A (611.0600) | EACH | 3 | $867.00 | $850.00 | $800.00 | $950.00 |
| 64 | Inlet covers type R (611.0648) | EACH | 9 | $1,632.00 | $1,350.00 | $1,600.00 | $1,600.00 |
| 65 | Inlet covers type S (611.0651) | EACH | 2 | $918.00 | $1,050.00 | $900.00 | $900.00 |
| 66 | Manholes 4-FT diameter (611.2004) | EACH | 3 | $5,100.00 | $3,600.00 | $5,000.00 | $5,000.00 |
| 67 | Manholes 7-FT diameter (611.2007) | EACH | 1 | $10,200 | $7,900.00 | $10,000 | $10,000 |
| 68 | Inlets 2X2-FT (611.3220) | EACH | 9 | $3,162.00 | $2,250.00 | $3,100.00 | $3,100.00 |
| 69 | Inlets 2X2.5-FT (611.3225) | EACH | 1 | $3,570.00 | $2,100.00 | $3,500.00 | $3,500.00 |
| 70 | Adjusting manhole covers (611.8110) | EACH | 35 | $1,020.00 | $725.00 | $1,000.00 | $1,000.00 |
| 71 | Adjusting inlet covers (611.8115) | EACH | 25 | $1,071.00 | $700.00 | $1,050.00 | $1,050.00 |
| 72 | Cover plates temporary (611.8120.S) | EACH | 25 | $255.00 | $225.00 | $250.00 | $250.00 |
| 73 | Pipe underdrain 6-inch (612.0106) | LF | 230 | $25.50 | $12.50 | $25.00 | $25.00 |
| 74 | Pipe underdrain unperforated 8- inch (612.0208) | LF | 21 | $35.70 | $40.00 | $35.00 | $35.00 |
| 75 | MGS guardrail 3 (614.2300) | LF | 200 | $26.52 | $26.00 | $26.00 | $26.00 |
| 76 | MGS guardrail terminal type 2 (614.2620) | EACH | 4 | $3,876.00 | $3,800.00 | $3,800.00 | $3,800.00 |
| 77 | Mobilization (619.1000) | EACH | 1 | $199,000 | $249,000 | $448,528 | $390,000 |
| 78 | Concrete median sloped nose (620.0300) | SF | 380 | $24.48 | $18.00 | $17.49 | $18.00 |
| 79 | Topsoil (625.0100) | SY | 4,252 | $4.56 | $4.47 | $4.47 | $4.47 |
| 80 | Mobilizations erosion control (628.1905) | EACH | 2 | $102.00 | $100.00 | $100.00 | $100.00 |
| 81 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $1.02 | $1.00 | $1.00 | $1.00 |
| 82 | Inlet protection type A (628.7005) | EACH | 49 | $51.00 | $50.00 | $50.00 | $50.00 |
| 83 | Inlet protection type B (628.7010) | EACH | 2 | $51.00 | $50.00 | $50.00 | $50.00 |
| 84 | Inlet protection type C (628.7015) | EACH | 167 | $71.40 | $70.00 | $70.00 | $70.00 |
| 85 | Inlet protection type D (628.7020) | EACH | 7 | $127.50 | $125.00 | $125.00 | $125.00 |
| 86 | Fertilizer type B (629.0210) | CWT | 2.10 | $81.60 | $80.00 | $80.00 | $80.00 |
| 87 | Sod water (631.0300) | MGAL | 43 | $35.70 | $35.00 | $35.00 | $35.00 |
| 88 | Sod lawn (631.1000) | SY | 4,252 | $6.63 | $6.50 | $6.50 | $6.50 |
| 89 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 88 | $132.60 | $130.00 | $130.00 | $130.00 |
| 90 | Posts tubular steel 2X2-inch X 8-FT (634.0808) | EACH | 2 | $153.00 | $150.00 | $150.00 | $150.00 |
| 91 | Signs type II reflective H (637.2210) | SF | 458 | $21.52 | $21.10 | $21.10 | $21.10 |
| 92 | Signs type II reflective F (637.2230) | SF | 898 | $23.36 | $22.90 | $22.90 | $22.90 |
| 93 | Moving signs type II (638.2102) | EACH | 22 | $56.10 | $55.00 | $55.00 | $55.00 |
| 94 | Removing signs type II (638.2602) | EACH | 3 | $10.20 | $10.00 | $10.00 | $10.00 |
| 95 | Removing small sign supports (638.3000) | EACH | 17 | $15.30 | $15.00 | $15.00 | $15.00 |
| 96 | Traffic control drums (643.0300) | DAY | 163,199 | $0.10 | $0.12 | $0.10 | $0.10 |
| 97 | Traffic control barricades type III (643.0420) | DAY | 12,379 | $0.56 | $0.48 | $0.55 | $0.55 |
| 98 | Traffic control warning lights type A (643.0705) | DAY | 24,758 | $0.08 | $0.12 | $0.08 | $0.08 |
| 99 | Traffic control warning lights type C (643.0715) | DAY | 15,907 | $0.08 | $0.12 | $0.08 | $0.08 |
| 100 | Traffic control arrow boards (643.0800) | DAY | 614 | $8.16 | $14.25 | $8.00 | $8.00 |
| 101 | Traffic control signs (643.0900) | DAY | 22,745 | $0.46 | $0.25 | $0.45 | $0.45 |
| 102 | Traffic control covering signs type I (643.0910) | EACH | 10 | $178.50 | $225.00 | $175.00 | $175.00 |
| 103 | Traffic control covering signs type II (643.0920) | EACH | 10 | $51.00 | $75.00 | $50.00 | $50.00 |
| 104 | Traffic control signs fixed message (643.1000) | SF | 93 | $14.79 | $15.50 | $14.50 | $14.50 |
| 105 | Traffic control signs PCMS (643.1050) | DAY | 55 | $27.00 | $18.55 | $27.00 | $27.00 |
| 106 | Traffic control cones 42-inch (643.1070) | DAY | 53,204 | $0.10 | $0.12 | $0.10 | $0.10 |
| 107 | Temporary marking line paint 6- inch (643.3165) | LF | 48,453 | $0.43 | $0.24 | $0.42 | $0.42 |
| 108 | Temporary marking line removable tape 6-inch (643.3180) | LF | 26,103 | $1.00 | $2.00 | $0.98 | $0.98 |
| 109 | Temporary marking line paint 10- inch (643.3265) | LF | 3,468 | $1.63 | $0.60 | $1.60 | $1.60 |
| 110 | Temporary marking removable mask out tape 6-inch (643.3960) | LF | 640 | $2.04 | $3.25 | $2.00 | $2.00 |
| 111 | Traffic control interim lane closure (643.4100) | EACH | 60 | $535.50 | $525.00 | $525.00 | $525.00 |
| 112 | Traffic control (643.5000) | EACH | 1 | $107,290 | $64,250 | $105,187 | $105,187 |
| 113 | Temporary pedestrian surface asphalt (644.1410) | SF | 1,760 | $11.00 | $0.01 | $0.01 | $14.20 |
| 114 | Temporary pedestrian surface plate (644.1430) | SF | 1,090 | $6.63 | $5.00 | $0.01 | $6.50 |
| 115 | Temporary pedestrian detectable warning field (644.1605) | SF | 20 | $6.12 | $100.00 | $6.00 | $6.00 |
| 116 | Temporary pedestrian barricade (644.1810) | LF | 5,650 | $2.04 | $2.00 | $2.00 | $2.00 |
| 117 | Geotextile type DF schedule B (645.0112) | SY | 67 | $5.10 | $10.00 | $4.68 | $5.00 |
| 118 | Marking line epoxy 4-inch (646.1020) | LF | 2,284 | $0.67 | $0.40 | $0.66 | $0.66 |
| 119 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 11,800 | $1.07 | $2.10 | $1.05 | $1.05 |
| 120 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 52,372 | $1.39 | $1.20 | $1.36 | $1.36 |
| 121 | Marking line epoxy 8-inch (646.3020) | LF | 402 | $1.35 | $0.95 | $1.32 | $1.32 |
| 122 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 14,119 | $2.81 | $2.50 | $2.75 | $2.75 |
| 123 | Marking arrow epoxy (646.5020) | EACH | 78 | $224.40 | $250.00 | $220.00 | $220.00 |
| 124 | Marking word epoxy (646.5120) | EACH | 26 | $244.80 | $260.00 | $240.00 | $240.00 |
| 125 | Marking stop line epoxy 12-inch (646.6020) | LF | 280 | $13.01 | $12.75 | $12.75 | $12.75 |
| 126 | Marking stop line epoxy 18-inch (646.6120) | LF | 1,221 | $13.26 | $13.30 | $13.00 | $13.00 |
| 127 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 4,090 | $10.20 | $10.00 | $10.00 | $10.00 |
| 128 | Marking curb epoxy (646.8120) | LF | 2,409 | $8.16 | $5.50 | $8.00 | $8.00 |
| 129 | Marking island nose epoxy (646.8220) | EACH | 38 | $275.40 | $246.30 | $270.00 | $270.00 |
| 130 | Marking removal line 4-inch (646.9000) | LF | 2,453 | $0.56 | $0.75 | $0.55 | $0.55 |
| 131 | Marking removal line water blasting 4-inch (646.9010) | LF | 1,560 | $1.02 | $1.00 | $1.00 | $1.00 |
| 132 | Marking removal special marking water blasting (646.9310) | EACH | 4 | $255.00 | $250.00 | $250.00 | $250.00 |
| 133 | Construction staking storm sewer (650.4000) | EACH | 14 | $204.00 | $200.00 | $200.00 | $115.00 |
| 134 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 4,651 | $0.61 | $0.60 | $0.60 | $1.25 |
| 135 | Construction staking resurfacing reference (650.8000) | LF | 9,928 | $0.20 | $0.20 | $0.20 | $0.25 |
| 136 | Construction staking curb ramps (650.9000) | EACH | 128 | $142.80 | $140.00 | $140.00 | $125.00 |
| 137 | Construction staking sidewalk (project) 001. 2265-18-70 (650.9500) | EACH | 1 | $2,040.00 | $2,000.00 | $2,000.00 | $4,000.00 |
| 138 | Construction staking supplemental control (project) 001. 2265-18-70 (650.9911) | EACH | 1 | $1,428.00 | $1,400.00 | $1,400.00 | $2,500.00 |
| 139 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 791 | $8.67 | $8.50 | $8.50 | $8.50 |
| 140 | Conduit special 2-inch (652.0605) | LF | 103 | $25.50 | $25.00 | $25.00 | $25.00 |
| 141 | Conduit loop detector (652.0800) | LF | 4,882 | $7.65 | $7.50 | $7.50 | $7.50 |
| 142 | Pull boxes steel 24X36-inch (653.0135) | EACH | 20 | $1,275.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 143 | Adjusting pull boxes (653.0900) | EACH | 20 | $459.00 | $450.00 | $450.00 | $450.00 |
| 144 | Removing pull boxes (653.0905) | EACH | 10 | $153.00 | $150.00 | $150.00 | $150.00 |
| 145 | Concrete bases type 1 (654.0101) | EACH | 29 | $1,173.00 | $1,150.00 | $1,150.00 | $1,150.00 |
| 146 | Concrete bases type 2 (654.0102) | EACH | 1 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 147 | Cable traffic signal 7-14 AWG (655.0240) | LF | 3,203 | $1.73 | $1.70 | $1.70 | $1.70 |
| 148 | Cable traffic signal 12-14 AWG (655.0260) | LF | 3,501 | $2.60 | $2.55 | $2.55 | $2.55 |
| 149 | Cable traffic signal 15-14 AWG (655.0270) | LF | 1,063 | $3.32 | $3.25 | $3.25 | $3.25 |
| 150 | Cable type UF 2-10 AWG grounded (655.0320) | LF | 88 | $2.81 | $2.75 | $2.75 | $2.75 |
| 151 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 3,364 | $1.02 | $1.00 | $1.00 | $1.00 |
| 152 | Electrical wire lighting 12 AWG (655.0610) | LF | 144 | $0.92 | $0.90 | $0.90 | $0.90 |
| 153 | Loop detector lead in cable (655.0700) | LF | 26,816 | $1.28 | $1.25 | $1.25 | $1.25 |
| 154 | Loop detector wire (655.0800) | LF | 23,536 | $1.12 | $1.10 | $1.10 | $1.10 |
| 155 | Pedestal bases (657.0100) | EACH | 9 | $275.40 | $270.00 | $270.00 | $270.00 |
| 156 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 9 | $408.00 | $400.00 | $400.00 | $400.00 |
| 157 | Pedestrian push buttons (658.0500) | EACH | 3 | $357.00 | $350.00 | $350.00 | $350.00 |
| 158 | Signal mounting hardware (location) 001. signal mounting hardware (STH 241 & ramsey ave) (658.5070) | EACH | 1 | $714.00 | $700.00 | $700.00 | $700.00 |
| 159 | Signal mounting hardware (location) 002. signal mounting hardware (STH 241 & parnell ave) (658.5070) | EACH | 1 | $780.30 | $765.00 | $765.00 | $765.00 |
| 160 | Signal mounting hardware (location) 003. signal mounting hardware (STH 241 & grange ave) (658.5070) | EACH | 1 | $780.30 | $765.00 | $765.00 | $765.00 |
| 161 | Signal mounting hardware (location) 004. signal mounting hardware (STH 241 & edgerton ave) (658.5070) | EACH | 1 | $153.00 | $150.00 | $150.00 | $150.00 |
| 162 | Signal mounting hardware (location) 005. signal mounting hardware (STH 241 & layton ave) (658.5070) | EACH | 1 | $1,428.00 | $1,400.00 | $1,400.00 | $1,400.00 |
| 163 | Sawing asphalt (690.0150) | LF | 1,442 | $1.79 | $1.39 | $1.75 | $5.00 |
| 164 | Sawing concrete (690.0250) | LF | 13,492 | $2.40 | $7.20 | $2.35 | $5.00 |
| 165 | Incentive iri ride (740.0440) | DOL | 22,273 | $1.00 | $1.00 | $1.00 | $1.00 |
| 166 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,800 | $5.00 | $5.00 | $5.00 | $5.00 |
| 167 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 7,200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 168 | Special 600. engineered soil (SPV.0035) | CY | 141 | $61.20 | $60.00 | $60.00 | $60.00 |
| 169 | Special 603. 6" granite cobbles (SPV.0035) | CY | 12 | $76.50 | $75.00 | $75.00 | $75.00 |
| 170 | Special 617. bedding layer (SPV.0035) | CY | 22 | $61.20 | $60.00 | $60.00 | $60.00 |
| 171 | Special 619. storage layer (SPV.0035) | CY | 160 | $61.20 | $60.00 | $60.00 | $60.00 |
| 172 | Special 620. shredded hardwood bark mulch (SPV.0035) | CY | 207 | $44.88 | $44.00 | $44.00 | $44.00 |
| 173 | Special 001. grading and shaping curb ramps (SPV.0060) | EACH | 106 | $51.00 | $600.00 | $1.00 | $200.00 |
| 174 | Special 002. utility line opening (ulo) (SPV.0060) | EACH | 14 | $816.00 | $0.01 | $1,166.00 | $950.00 |
| 175 | Special 003. temporary bus stop (SPV.0060) | EACH | 16 | $4,500.00 | $1,050.00 | $1.00 | $2,950.00 |
| 176 | Special 004. field facilities office space (SPV.0060) | EACH | 1 | $16,000 | $40,000 | $21,460 | $17,000 |
| 177 | Special 005. salvage wheel stops (SPV.0060) | EACH | 2 | $750.00 | $75.00 | $126.00 | $75.00 |
| 178 | Special 010. modify existing traffic signal during construction, STH 241 & ramsey ave (SPV.0060) | EACH | 1 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 179 | Special 011. modify existing traffic signal during construction, STH 241 & parnell ave (SPV.0060) | EACH | 1 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 180 | Special 012. modify existing traffic signal during construction, STH 241 & grange ave (SPV.0060) | EACH | 1 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 181 | Special 013. modifying existing traffic signal during construction, STH 241 & edgerton A (SPV.0060) | EACH | 1 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 182 | Special 014. modify existing traffic signal during construction, STH 241 & layton ave (SPV.0060) | EACH | 1 | $1,530.00 | $2,500.00 | $1,500.00 | $1,500.00 |
| 183 | Special 015. removing, salvaging, & installing traffic signal equipment, STH 241 & ramse (SPV.0060) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 184 | Special 016. removing, salvaging, & installing traffic signal equipment, STH 241 & parne (SPV.0060) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 185 | Special 017. removing, salvaging, & installing traffic signal equipment, STH 241 & grang (SPV.0060) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 186 | Special 018. removing, salvaging, & installing traffic signal equipment, STH 241 & edger (SPV.0060) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 187 | Special 019. removing, salvaging, & installing traffic signal equipment, STH 241 & layto (SPV.0060) | EACH | 1 | $2,550.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 188 | Special 020. remove & salvage video detection equipment (SPV.0060) | EACH | 1 | $10,200 | $10,000 | $10,000 | $10,000 |
| 189 | Special 038. adjust sanitary sewer manhole (SPV.0060) | EACH | 17 | $1,530.00 | $1,050.00 | $1,500.00 | $1,500.00 |
| 190 | Special 039. adjusting water valve boxes (SPV.0060) | EACH | 70 | $200.00 | $525.00 | $346.00 | $750.00 |
| 191 | Special 050. remove and reinstall mailboxes (SPV.0060) | EACH | 3 | $322.19 | $100.00 | $100.00 | $100.00 |
| 192 | Special 100. adjust sanitary sewer manhole, milwaukee (SPV.0060) | EACH | 18 | $1,224.00 | $750.00 | $1,200.00 | $1,200.00 |
| 193 | Special 400. adjust cuc manhole cover (SPV.0060) | EACH | 6 | $1,530.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 194 | Special 600. 6-inch cleanout (SPV.0060) | EACH | 9 | $1,122.00 | $340.00 | $1,100.00 | $1,100.00 |
| 195 | Special 601. 8-inch diameter overflow standpipe with dome grate (SPV.0060) | EACH | 3 | $1,428.00 | $2,100.00 | $1,400.00 | $1,400.00 |
| 196 | Special 602. storm curb inlet with grate type "A" (SPV.0060) | EACH | 6 | $3,672.00 | $3,200.00 | $3,921.88 | $1,460.00 |
| 197 | Special 610. informational sign post (SPV.0060) | EACH | 6 | $204.00 | $200.00 | $200.00 | $200.00 |
| 198 | Special 612. storm inlet type 45A (SPV.0060) | EACH | 1 | $2,958.00 | $5,500.00 | $2,900.00 | $2,900.00 |
| 199 | Special 613. inlet repair (SPV.0060) | EACH | 3 | $2,142.00 | $850.00 | $2,100.00 | $2,100.00 |
| 200 | Special 640. perennial black eyed susan (rudbeckia fulgida ’goldsturm’) (SPV.0060) | EACH | 30 | $20.40 | $20.00 | $20.00 | $20.00 |
| 201 | Special 641. perennial blue wonder catmint (nepeta racemosa "blue wonder") (SPV.0060) | EACH | 50 | $20.40 | $20.00 | $20.00 | $20.00 |
| 202 | Special 642. perennial daylilies (hemerocallis) (SPV.0060) | EACH | 70 | $20.40 | $20.00 | $20.00 | $20.00 |
| 203 | Special 643. perennial rugosa roses (rosa species rugosa) (SPV.0060) | EACH | 7 | $51.00 | $50.00 | $50.00 | $50.00 |
| 204 | Special 644. perennial russian sage (perovskia atriplicifolia) (SPV.0060) | EACH | 15 | $20.40 | $20.00 | $20.00 | $20.00 |
| 205 | Special 645. panicum grass (panicum hillmanii) (SPV.0060) | EACH | 26 | $20.40 | $20.00 | $20.00 | $20.00 |
| 206 | Special 646. blue false indigo (baptisia austalis) (SPV.0060) | EACH | 9 | $20.40 | $20.00 | $20.00 | $20.00 |
| 207 | Special 647. purple coneflower (echinacea purpurea) (SPV.0060) | EACH | 60 | $20.40 | $20.00 | $20.00 | $20.00 |
| 208 | Special 648. diablo ninebark (physocarpus opufolius "summer wine") (SPV.0060) | EACH | 11 | $51.00 | $50.00 | $50.00 | $50.00 |
| 209 | Special 649. sea green juniper (juniperus pfitzeriana ‘sea green’) (SPV.0060) | EACH | 30 | $71.40 | $70.00 | $70.00 | $70.00 |
| 210 | Special 650. joe phy weed (eutrochium purpureum) (SPV.0060) | EACH | 40 | $20.40 | $20.00 | $20.00 | $20.00 |
| 211 | Special 651. red twig dogwood (cornus sericea "cardinal") (SPV.0060) | EACH | 30 | $61.20 | $60.00 | $60.00 | $60.00 |
| 212 | Special 652. karl forester grass (calamogrostis acutiflora "karl foerster") (SPV.0060) | EACH | 20 | $20.40 | $20.00 | $20.00 | $20.00 |
| 213 | Special 001. tuck point landscape retaining wall (SPV.0090) | LF | 238 | $86.70 | $85.00 | $85.00 | $85.00 |
| 214 | Special 001. wall modular block gravity landscape, sta. 1157+82 (SPV.0165) | SF | 885 | $71.40 | $70.00 | $70.00 | $70.00 |
| 215 | Special 002. remove and replace decorative stone mulch (SPV.0165) | SF | 100 | $2.04 | $2.00 | $2.00 | $2.00 |
| 216 | Special 001. excavation, hauling, and disposal of pah and lead contaminated soil (SPV.0195) | TON | 20.10 | $153.00 | $200.00 | $110.87 | $210.00 |
| 217 | Special 002. asphaltic repair (SPV.0195) | TON | 732 | $140.00 | $140.00 | $140.00 | $96.30 |
| 218 | Special 003. joint and crack repair (SPV.0195) | TON | 65 | $215.00 | $215.00 | $215.00 | $475.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.