WisDOT contract 20250408008 bid tabulation
1090-03-75. Let by Wisconsin DOT on April 8, 2025, Milwaukee. 3 bids received; low bid $22,336,461 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 08 APR 2025
- Pay items
- 307
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $22,336,461 | Low |
| 2 | Zignego Company, Inc. | $22,827,101 | +2.0% |
| 3 | Michels Road & Stone, Inc. | $22,959,022 | +3.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Zignego Company, Inc. | 3. Michels Road & Stone, Inc. |
|---|---|---|---|---|---|---|
| 1 | CPM progress schedule (108.4400) | EACH | 1 | $100.00 | $1,000.00 | $3,500.00 |
| 2 | Grubbing (201.0205) | STA | 13 | $599.00 | $1,000.00 | $599.00 |
| 3 | Abatement of asbestos containing material (structure) 001. B-40-300 (203.0211.S) | EACH | 1 | $4,560.00 | $4,560.00 | $4,560.00 |
| 4 | Abatement of asbestos containing material (structure) 002. B-40-301 (203.0211.S) | EACH | 1 | $4,710.00 | $4,710.00 | $4,710.00 |
| 5 | Abatement of asbestos containing material (structure) 003. B-40-302 (203.0211.S) | EACH | 1 | $4,710.00 | $4,710.00 | $4,710.00 |
| 6 | Removing structure (structure) 001. B-40-302 (203.0220) | EACH | 1 | $35,000 | $35,000 | $35,000 |
| 7 | Debris containment over waterway (structure) 001. B-40-188 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 8 | Debris containment over waterway (structure) 002. B-40-304 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 9 | Debris containment over waterway (structure) 003. B-40-305 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 10 | Debris containment over waterway (structure) 004. B-40-322 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 11 | Debris containment over waterway (structure) 005. B-40-323 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 12 | Debris containment over waterway (structure) 006. B-40-324 (203.0335) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 13 | Removing concrete pavement (204.0100) | SY | 36 | $29.87 | $75.00 | $15.00 |
| 14 | Removing asphaltic surface butt joints (204.0115) | SY | 225 | $18.00 | $18.00 | $18.00 |
| 15 | Removing asphaltic surface milling (204.0120) | SY | 296,323 | $4.00 | $4.00 | $4.00 |
| 16 | Removing asphaltic longitudinal notched wedge joint milling (204.0126.S) | LF | 9,630 | $9.65 | $9.65 | $9.65 |
| 17 | Removing curb & gutter (204.0150) | LF | 1,139 | $13.71 | $10.00 | $10.00 |
| 18 | Removing concrete sidewalk (204.0155) | SY | 1,384 | $17.92 | $20.00 | $10.00 |
| 19 | Removing guardrail (204.0165) | LF | 826 | $2.50 | $2.50 | $2.50 |
| 20 | Removing concrete slope paving (204.0175) | SY | 576 | $120.00 | $20.00 | $120.00 |
| 21 | Removing surface drains (204.0190) | EACH | 1 | $682.52 | $1,000.00 | $700.00 |
| 22 | Removing concrete bases (204.0195) | EACH | 36 | $350.00 | $500.00 | $350.00 |
| 23 | Removing inlets (204.0220) | EACH | 1 | $2,200.00 | $1,000.00 | $800.00 |
| 24 | Removing (item description) 001. concrete column jacketing (204.9060.S) | EACH | 25 | $6,000.00 | $6,000.00 | $6,000.00 |
| 25 | Removing (item description) 002. deck drains (204.9060.S) | EACH | 3 | $4,500.00 | $4,500.00 | $4,500.00 |
| 26 | Removing (item description) 101. lighting units (204.9060.S) | EACH | 11 | $1,200.00 | $1,200.00 | $1,200.00 |
| 27 | Removing (item description) 301. traffic signals IH 41 ramps & W oklahoma ave (204.9060.S) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 |
| 28 | Removing (item description) 302. traffic signals IH 41 SB off ramp & W. lincoln ave (204.9060.S) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 |
| 29 | Removing (item description) 303. traffic signals IH 41 NB off ramp & W. national ave (204.9060.S) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 |
| 30 | Removing (item description) 304. traffic signals IH 41 ramps & W. national ave (204.9060.S) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 |
| 31 | Removing (item description) 001. removing concrete channel (204.9180.S) | SY | 33 | $77.36 | $100.00 | $60.00 |
| 32 | Excavation common (205.0100) | CY | 122 | $117.03 | $100.00 | $55.00 |
| 33 | Excavation for structures bridges (structure) 003. B-40-302 (206.1001) | EACH | 1 | $6,000.00 | $6,000.00 | $6,000.00 |
| 34 | Borrow (208.0100) | CY | 32 | $120.13 | $100.00 | $74.00 |
| 35 | Backfill controlled low strength (209.0200.S) | CY | 4 | $1,000.00 | $500.00 | $1,000.00 |
| 36 | Backfill structure type A (210.1500) | TON | 45 | $60.00 | $100.00 | $60.00 |
| 37 | Prepare foundation for concrete pavement (project) 001. 1100-05-73 (211.0201) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 38 | Finishing roadway (project) 001. 1090-03-75 (213.0100) | EACH | 1 | $1,491.49 | $1,000.00 | $5,000.00 |
| 39 | Finishing roadway (project) 002. 1100-05-73 (213.0100) | EACH | 1 | $1,491.49 | $1,000.00 | $5,000.00 |
| 40 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 106 | $52.02 | $100.00 | $50.00 |
| 41 | Removing pavement for base patching (390.0100) | CY | 9,603 | $96.20 | $145.50 | $30.00 |
| 42 | Base patching concrete shes (390.0405) | CY | 9,603 | $91.63 | $212.00 | $200.00 |
| 43 | Drilled tie bars (416.0610) | EACH | 12,414 | $4.82 | $5.00 | $8.00 |
| 44 | Drilled dowel bars (416.0620) | EACH | 42,661 | $9.56 | $0.01 | $8.00 |
| 45 | Concrete pavement repair (416.1710) | SY | 177 | $142.70 | $110.00 | $111.00 |
| 46 | Concrete pavement repair shes (416.1715) | SY | 90 | $146.61 | $170.00 | $118.00 |
| 47 | Concrete pavement replacement (416.1720) | SY | 1,930 | $99.89 | $110.00 | $106.00 |
| 48 | Concrete pavement replacement shes (416.1725) | SY | 653 | $163.02 | $170.00 | $125.00 |
| 49 | Tack coat (455.0605) | GAL | 35,407 | $2.25 | $2.25 | $2.25 |
| 50 | HMA pavement test strip volumetrics (460.0115.S) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 51 | HMA pavement test strip density (460.0120.S) | EACH | 2 | $6,250.00 | $6,250.00 | $6,250.00 |
| 52 | Incentive density HMA pavement (460.2000) | DOL | 33,690 | $1.00 | $1.00 | $1.00 |
| 53 | HMA pavement 6 MT 58-28 H (460.6426) | TON | 247 | $128.50 | $128.50 | $128.50 |
| 54 | HMA pavement 5 HT 58-28 V (460.7625) | TON | 138 | $305.00 | $305.00 | $305.00 |
| 55 | HMA pavement 5 SMA 58-28 V (460.8625) | TON | 52,671 | $109.50 | $109.50 | $109.50 |
| 56 | Material transfer vehicle (460.9000.S) | EACH | 1 | $75,250 | $75,250 | $75,250 |
| 57 | Asphaltic surface patching (465.0110) | TON | 50 | $448.00 | $448.00 | $448.00 |
| 58 | Asphaltic flumes (465.0315) | SY | 8 | $230.00 | $230.00 | $230.00 |
| 59 | Cold patch (495.1000.S) | TON | 5 | $362.85 | $1.00 | $500.00 |
| 60 | Concrete masonry bridges (502.0100) | CY | 66 | $2,300.00 | $2,300.00 | $2,300.00 |
| 61 | Expansion device (502.3101) | LF | 80 | $400.00 | $400.00 | $400.00 |
| 62 | Protective surface treatment (502.3200) | SY | 1,520 | $4.00 | $4.00 | $4.00 |
| 63 | Pigmented surface sealer reseal (502.3205) | SY | 4,367 | $20.00 | $20.00 | $20.00 |
| 64 | Pigmented surface sealer (502.3210) | SY | 22 | $12.00 | $12.00 | $12.00 |
| 65 | Protective surface treatment reseal (502.3215) | SY | 164 | $15.00 | $15.00 | $15.00 |
| 66 | Adhesive anchors 1 1/4-inch (502.4110) | EACH | 12 | $160.00 | $160.00 | $160.00 |
| 67 | Adhesive anchors no. 5 bar (502.4205) | EACH | 96 | $30.00 | $30.00 | $30.00 |
| 68 | Bar steel reinforcement HS structures (505.0400) | LB | 3,150 | $2.40 | $2.40 | $2.40 |
| 69 | Bar steel reinforcement HS coated structures (505.0600) | LB | 6,430 | $2.63 | $2.63 | $2.63 |
| 70 | Bearing pads elastomeric laminated (506.2610) | EACH | 18 | $1,100.00 | $1,100.00 | $1,100.00 |
| 71 | Bearing assemblies fixed (structure) 001. B-40-304 (506.5000) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 |
| 72 | Bearing assemblies fixed (structure) 002. B-40-305 (506.5000) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 |
| 73 | Bearing assemblies expansion (structure) 001. B-40-305 (506.6000) | EACH | 2 | $3,000.00 | $3,000.00 | $3,000.00 |
| 74 | Removing bearings (structure) 001. B-40-304 (506.7050.S) | EACH | 4 | $1,600.00 | $1,600.00 | $1,600.00 |
| 75 | Removing bearings (structure) 002. B-40-305 (506.7050.S) | EACH | 4 | $1,600.00 | $1,600.00 | $1,600.00 |
| 76 | Removing bearings (structure) 003. B-40-322 (506.7050.S) | EACH | 8 | $1,600.00 | $1,600.00 | $1,600.00 |
| 77 | Removing bearings (structure) 004. B-40-323 (506.7050.S) | EACH | 8 | $1,600.00 | $1,600.00 | $1,600.00 |
| 78 | Preparation decks type 1 (509.0301) | SY | 749 | $185.00 | $185.00 | $185.00 |
| 79 | Preparation decks type 2 (509.0302) | SY | 305 | $200.00 | $200.00 | $200.00 |
| 80 | Sawing pavement deck preparation areas (509.0310.S) | LF | 4,050 | $2.50 | $2.50 | $2.50 |
| 81 | Cleaning decks to reapply concrete masonry overlay (509.0505.S) | SY | 1,475 | $15.00 | $15.00 | $15.00 |
| 82 | Joint repair (509.1000) | SY | 44 | $1,500.00 | $1,500.00 | $1,500.00 |
| 83 | Curb repair (509.1200) | LF | 331 | $120.00 | $120.00 | $120.00 |
| 84 | Concrete surface repair (509.1500) | SF | 4,755 | $180.00 | $180.00 | $180.00 |
| 85 | Full-depth deck repair (509.2000) | SY | 14 | $1,200.00 | $1,200.00 | $1,200.00 |
| 86 | Concrete masonry deck repair (509.2100.S) | CY | 12 | $1,600.00 | $1,600.00 | $1,600.00 |
| 87 | Concrete masonry overlay decks (509.2500) | CY | 187 | $1,000.00 | $1,000.00 | $1,000.00 |
| 88 | Removing concrete masonry deck overlay (structure) 001. B-40-322 (509.9005.S) | SY | 796 | $15.00 | $15.00 | $15.00 |
| 89 | Removing concrete masonry deck overlay (structure) 002. B-40-323 (509.9005.S) | SY | 691 | $15.00 | $15.00 | $15.00 |
| 90 | Removing asphaltic concrete deck overlay (structure) 001. B-40-301 (509.9010.S) | SY | 453 | $30.00 | $30.00 | $30.00 |
| 91 | Removing asphaltic concrete deck overlay (structure) 002. B-40-302 (509.9010.S) | SY | 453 | $30.00 | $30.00 | $30.00 |
| 92 | Removing polymer overlay (structure) 001. B-40-324 (509.9015.S) | SY | 2,092 | $14.00 | $14.00 | $14.00 |
| 93 | Temporary shoring (structure) 001. B-40-302 (511.1200) | SF | 158 | $80.00 | $80.00 | $80.00 |
| 94 | Removing and resetting tubular railing (structure) 001. B-40-302 (513.9006.S) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 |
| 95 | Floor drains type H (514.0460) | EACH | 3 | $6,500.00 | $6,500.00 | $6,500.00 |
| 96 | Downspout 6-inch (514.2625) | LF | 12 | $280.00 | $280.00 | $280.00 |
| 97 | Rubberized membrane waterproofing (516.0500) | SY | 2 | $150.00 | $150.00 | $150.00 |
| 98 | Sheet membrane waterproofing for asphalt overlays (516.0600.S) | SY | 906 | $95.00 | $95.00 | $95.00 |
| 99 | Structure repainting recycled abrasive (structure) 001. B-40-304 (517.1801.S) | EACH | 1 | $98,000 | $98,000 | $98,000 |
| 100 | Structure repainting recycled abrasive (structure) 002. B-40-305 (517.1801.S) | EACH | 1 | $98,000 | $98,000 | $98,000 |
| 101 | Negative pressure containment and collection of waste materials (structure) 001. B-40-304 (517.4501.S) | EACH | 1 | $19,500 | $19,500 | $19,500 |
| 102 | Negative pressure containment and collection of waste materials (structure) 002. B-40-305 (517.4501.S) | EACH | 1 | $19,500 | $19,500 | $19,500 |
| 103 | Portable decontamination facility (517.6001.S) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 |
| 104 | Concrete curb & gutter 31-inch (601.0331) | LF | 525 | $38.00 | $38.00 | $38.00 |
| 105 | Concrete curb pedestrian (601.0600) | LF | 30 | $40.00 | $40.00 | $40.00 |
| 106 | Concrete sidewalk 5-inch (602.0410) | SF | 8,147 | $9.00 | $9.00 | $9.00 |
| 107 | Curb ramp detectable warning field yellow (602.0505) | SF | 398 | $40.00 | $40.00 | $40.00 |
| 108 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 96 | $50.00 | $50.00 | $50.00 |
| 109 | Concrete barrier type S36 (603.1136) | LF | 34 | $110.00 | $110.00 | $110.00 |
| 110 | Slope paving concrete (604.0400) | SY | 576 | $190.00 | $190.00 | $190.00 |
| 111 | Riprap medium (606.0200) | CY | 8 | $400.00 | $1,000.00 | $400.00 |
| 112 | Riprap heavy (606.0300) | CY | 199 | $140.00 | $200.00 | $190.00 |
| 113 | Inlet covers type MS (611.0642) | EACH | 2 | $1,505.00 | $1,500.00 | $600.00 |
| 114 | Inlets median 2 grate (611.3902) | EACH | 1 | $9,062.00 | $7,500.00 | $3,200.00 |
| 115 | Adjusting manhole covers (611.8110) | EACH | 3 | $4,700.00 | $1,000.00 | $950.00 |
| 116 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 26 | $20.00 | $100.00 | $20.00 |
| 117 | Guardrail mow strip emulsified asphalt (614.0397) | SY | 324 | $22.60 | $12.95 | $12.95 |
| 118 | MGS thrie beam transition (614.2500) | LF | 355 | $98.00 | $98.00 | $90.10 |
| 119 | MGS guardrail terminal eat (614.2610) | EACH | 9 | $3,600.00 | $3,600.00 | $3,675.00 |
| 120 | Maintenance and repair of haul roads (project) 001. 1090-03-75 (618.0100) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 121 | Maintenance and repair of haul roads (project) 002. 1100-05-73 (618.0100) | EACH | 1 | $1.00 | $1.00 | $1.00 |
| 122 | Mobilization (619.1000) | EACH | 1 | $4,489,689 | $3,710,000 | $4,168,169 |
| 123 | Concrete median sloped nose (620.0300) | SF | 264 | $15.00 | $15.00 | $15.00 |
| 124 | Topsoil (625.0100) | SY | 21,918 | $6.00 | $0.01 | $4.00 |
| 125 | Silt fence (628.1504) | LF | 1,218 | $2.50 | $2.50 | $1.84 |
| 126 | Silt fence maintenance (628.1520) | LF | 1,218 | $0.10 | $0.10 | $0.05 |
| 127 | Erosion mat urban class I type B (628.2008) | SY | 21,635 | $1.85 | $1.85 | $1.68 |
| 128 | Inlet protection type A (628.7005) | EACH | 9 | $110.00 | $110.00 | $100.00 |
| 129 | Inlet protection type D (628.7020) | EACH | 574 | $115.00 | $115.00 | $71.10 |
| 130 | Culvert pipe checks (628.7555) | EACH | 48 | $17.50 | $17.50 | $32.10 |
| 131 | Fertilizer type B (629.0210) | CWT | 10.80 | $80.00 | $80.00 | $83.10 |
| 132 | Seeding mixture no. 20 (630.0120) | LB | 41 | $10.00 | $10.00 | $10.00 |
| 133 | Seeding mixture no. 60 (630.0160) | LB | 781 | $12.50 | $12.50 | $8.50 |
| 134 | Seeding mixture no. 70 (630.0170) | LB | 151 | $100.00 | $100.00 | $97.00 |
| 135 | Seeding temporary (630.0200) | LB | 30 | $10.00 | $10.00 | $3.90 |
| 136 | Seed water (630.0500) | MGAL | 485 | $25.00 | $25.00 | $10.00 |
| 137 | Sod water (631.0300) | MGAL | 7 | $25.00 | $25.00 | $50.90 |
| 138 | Sod lawn (631.1000) | SY | 285 | $12.50 | $12.50 | $10.50 |
| 139 | Posts wood 4X6-inch X 18-FT (634.0618) | EACH | 80 | $125.00 | $125.00 | $75.00 |
| 140 | Posts wood 4X6-inch X 22-FT (634.0622) | EACH | 2 | $200.00 | $200.00 | $84.10 |
| 141 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 2 | $200.00 | $200.00 | $180.90 |
| 142 | Signs type II reflective H (637.2210) | SF | 849.78 | $22.00 | $22.00 | $20.50 |
| 143 | Signs type II reflective H folding (637.2215) | SF | 246.42 | $28.75 | $28.75 | $24.10 |
| 144 | Signs type II reflective F (637.2230) | SF | 239.50 | $23.50 | $23.50 | $21.90 |
| 145 | Moving signs type II (638.2102) | EACH | 4 | $75.00 | $75.00 | $95.00 |
| 146 | Removing signs type II (638.2602) | EACH | 110 | $30.00 | $30.00 | $15.00 |
| 147 | Removing small sign supports (638.3000) | EACH | 70 | $30.00 | $30.00 | $17.00 |
| 148 | Traffic control drums (643.0300) | DAY | 164,445 | $0.12 | $0.18 | $0.12 |
| 149 | Traffic control barricades type II (643.0410) | DAY | 206 | $1.00 | $1.20 | $1.00 |
| 150 | Traffic control barricades type III (643.0420) | DAY | 21,955 | $0.35 | $0.45 | $0.35 |
| 151 | Traffic control warning lights type A (643.0705) | DAY | 42,403 | $0.10 | $0.07 | $0.10 |
| 152 | Traffic control warning lights type C (643.0715) | DAY | 59,873 | $0.10 | $0.07 | $0.10 |
| 153 | Traffic control arrow boards (643.0800) | DAY | 2,754 | $5.75 | $10.00 | $5.75 |
| 154 | Traffic control signs (643.0900) | DAY | 84,398 | $0.21 | $0.21 | $0.21 |
| 155 | Traffic control covering signs type II (643.0920) | EACH | 1,409 | $22.50 | $25.00 | $22.50 |
| 156 | Traffic control signs PCMS (643.1050) | DAY | 860 | $15.00 | $50.00 | $15.00 |
| 157 | Basic traffic queue warning system (643.1205.S) | DAY | 575 | $135.00 | $135.88 | $135.00 |
| 158 | Temporary marking line removable tape 4-inch (643.3150) | LF | 3,469 | $1.55 | $2.67 | $1.55 |
| 159 | Temporary marking line epoxy 6- inch (643.3170) | LF | 132,007 | $0.30 | $0.90 | $0.30 |
| 160 | Temporary marking line black epoxy 6-inch (643.3175) | LF | 24,592 | $0.30 | $0.52 | $0.30 |
| 161 | Temporary marking line epoxy 10- inch (643.3270) | LF | 17,218 | $1.10 | $0.98 | $1.10 |
| 162 | Temporary marking line black epoxy 10-inch (643.3275) | LF | 2,859 | $0.50 | $1.60 | $0.50 |
| 163 | Temporary marking crosswalk epoxy 6-inch (643.3320) | LF | 1,194 | $8.00 | $9.75 | $8.00 |
| 164 | Temporary marking arrow epoxy (643.3520) | EACH | 39 | $150.00 | $255.00 | $150.00 |
| 165 | Temporary marking stop line epoxy 18-inch (643.3820) | LF | 731 | $8.00 | $11.85 | $8.00 |
| 166 | Traffic control interim lane closure (643.4100) | EACH | 465 | $800.00 | $275.00 | $800.00 |
| 167 | Traffic control (643.5000) | EACH | 1 | $205,000 | $135,959 | $205,000 |
| 168 | Temporary pedestrian surface asphalt (644.1410) | SF | 323 | $11.90 | $20.00 | $11.90 |
| 169 | Temporary pedestrian surface matting (644.1440) | SF | 39 | $5.00 | $11.19 | $5.00 |
| 170 | Temporary pedestrian curb ramp (644.1601) | DAY | 135 | $20.00 | $5.83 | $20.00 |
| 171 | Temporary pedestrian detectable warning field (644.1605) | SF | 96 | $5.75 | $7.86 | $5.75 |
| 172 | Temporary pedestrian barricade (644.1810) | LF | 660 | $3.65 | $4.35 | $3.65 |
| 173 | Geotextile type HR (645.0120) | SY | 406 | $9.00 | $10.00 | $10.00 |
| 174 | Marking line epoxy 6-inch (646.2020) | LF | 3,684 | $0.35 | $0.85 | $0.35 |
| 175 | Marking line grooved black epoxy 6-inch (646.2025) | LF | 24,592 | $1.50 | $1.40 | $1.50 |
| 176 | Marking line grooved wet ref epoxy 6-inch (646.2040) | LF | 109,805 | $1.10 | $1.65 | $1.10 |
| 177 | Marking line grooved permanent tape 6-inch (646.2050) | LF | 22,598 | $7.00 | $8.80 | $7.00 |
| 178 | Marking line epoxy 10-inch (646.4020) | LF | 760 | $0.91 | $1.60 | $0.91 |
| 179 | Marking line grooved black epoxy 10-inch (646.4025) | LF | 2,859 | $2.75 | $1.80 | $2.75 |
| 180 | Marking line grooved wet ref epoxy 10-inch (646.4040) | LF | 14,690 | $2.00 | $2.50 | $2.00 |
| 181 | Marking line grooved permanent tape 10-inch (646.4050) | LF | 2,528 | $12.00 | $14.25 | $12.00 |
| 182 | Marking arrow epoxy (646.5020) | EACH | 39 | $175.00 | $300.00 | $175.00 |
| 183 | Marking word epoxy (646.5120) | EACH | 12 | $225.00 | $300.00 | $225.00 |
| 184 | Marking symbol epoxy (646.5220) | EACH | 13 | $150.00 | $350.00 | $150.00 |
| 185 | Marking stop line epoxy 18-inch (646.6120) | LF | 757 | $9.00 | $16.75 | $9.00 |
| 186 | Marking diagonal epoxy 12-inch (646.7120) | LF | 4,478 | $8.00 | $7.70 | $8.00 |
| 187 | Marking chevron epoxy 24-inch (646.7220) | LF | 2,078 | $17.00 | $16.50 | $17.00 |
| 188 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,261 | $9.00 | $12.25 | $9.00 |
| 189 | Marking curb epoxy (646.8120) | LF | 1,404 | $5.00 | $6.00 | $5.00 |
| 190 | Marking island nose epoxy (646.8220) | EACH | 17 | $200.00 | $305.00 | $200.00 |
| 191 | Marking parking stall epoxy (646.8320) | LF | 11,731 | $2.50 | $2.95 | $2.50 |
| 192 | Marking removal line water blasting 4-inch (646.9010) | LF | 2,582 | $0.50 | $1.05 | $0.50 |
| 193 | Marking removal line grooved contrast permanent tape 4-inch (646.9055) | LF | 910 | $3.25 | $0.70 | $3.25 |
| 194 | Marking removal line grooved contrast permanent tape 8-inch (646.9155) | LF | 1,125 | $3.75 | $1.40 | $3.75 |
| 195 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 2,588 | $8.50 | $8.50 | $8.50 |
| 196 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 1,788 | $15.00 | $15.00 | $15.00 |
| 197 | Conduit special 2-inch (652.0605) | LF | 309 | $25.00 | $25.00 | $25.00 |
| 198 | Conduit special 3-inch (652.0615) | LF | 3,142 | $35.00 | $35.00 | $35.00 |
| 199 | Conduit loop detector (652.0800) | LF | 3,668 | $7.50 | $7.50 | $7.50 |
| 200 | Pull boxes steel 24X36-inch (653.0135) | EACH | 15 | $1,250.00 | $1,250.00 | $1,250.00 |
| 201 | Pull boxes steel 24X42-inch (653.0140) | EACH | 39 | $1,300.00 | $1,300.00 | $1,300.00 |
| 202 | Junction boxes 18X12X6-inch (653.0222) | EACH | 1 | $2,050.00 | $2,050.00 | $2,050.00 |
| 203 | Removing pull boxes (653.0905) | EACH | 30 | $150.00 | $150.00 | $150.00 |
| 204 | Concrete bases type 1 (654.0101) | EACH | 22 | $1,200.00 | $1,200.00 | $1,200.00 |
| 205 | Concrete bases type 2 (654.0102) | EACH | 1 | $1,400.00 | $1,400.00 | $1,400.00 |
| 206 | Concrete bases type 10 (654.0110) | EACH | 5 | $8,500.00 | $8,500.00 | $8,500.00 |
| 207 | Concrete bases type 10-special (654.0120) | EACH | 2 | $11,000 | $11,000 | $11,000 |
| 208 | Concrete control cabinet bases type 9 special (654.0217) | EACH | 2 | $2,300.00 | $2,300.00 | $2,300.00 |
| 209 | Cable traffic signal 7-14 AWG (655.0240) | LF | 3,520 | $1.75 | $1.75 | $1.75 |
| 210 | Cable traffic signal 12-14 AWG (655.0260) | LF | 3,790 | $3.00 | $3.00 | $3.00 |
| 211 | Cable type UF 2-10 AWG grounded (655.0320) | LF | 1,651 | $2.50 | $2.50 | $2.50 |
| 212 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 3,312 | $1.05 | $1.05 | $1.05 |
| 213 | Electrical wire lighting 12 AWG (655.0610) | LF | 100 | $0.95 | $0.95 | $0.95 |
| 214 | Electrical wire lighting 8 AWG (655.0620) | LF | 1,420 | $1.60 | $1.60 | $1.60 |
| 215 | Loop detector lead in cable (655.0700) | LF | 8,790 | $1.50 | $1.50 | $1.50 |
| 216 | Loop detector wire (655.0800) | LF | 12,450 | $0.95 | $0.95 | $0.95 |
| 217 | Traffic signal evp detector cable (655.0900) | LF | 2,293 | $2.00 | $2.00 | $2.00 |
| 218 | Electrical service meter breaker pedestal (location) 301. IH 41 ramps & oklahoma ave (656.0201) | EACH | 1 | $1,500.00 | $1,500.00 | $1,500.00 |
| 219 | Pedestal bases (657.0100) | EACH | 24 | $300.00 | $300.00 | $300.00 |
| 220 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 1 | $600.00 | $600.00 | $600.00 |
| 221 | Poles type 3 (657.0310) | EACH | 1 | $5,885.00 | $5,885.00 | $5,885.00 |
| 222 | Traffic signal standards aluminum 13-FT (657.0420) | EACH | 14 | $700.00 | $700.00 | $700.00 |
| 223 | Traffic signal standards aluminum 15-FT (657.0425) | EACH | 3 | $770.00 | $770.00 | $770.00 |
| 224 | Traffic signal standards aluminum 10-FT (657.0430) | EACH | 7 | $610.00 | $610.00 | $610.00 |
| 225 | Luminaire arms single member 4- inch clamp 6-FT (657.0609) | EACH | 1 | $320.00 | $320.00 | $320.00 |
| 226 | Traffic signal face 3S 12-inch (658.0173) | EACH | 34 | $700.00 | $700.00 | $700.00 |
| 227 | Traffic signal face 4S 12-inch (658.0174) | EACH | 3 | $950.00 | $950.00 | $950.00 |
| 228 | Pedestrian signal face 16-inch (658.0416) | EACH | 14 | $600.00 | $600.00 | $600.00 |
| 229 | Pedestrian push buttons (658.0500) | EACH | 13 | $350.00 | $350.00 | $350.00 |
| 230 | Signal mounting hardware (location) 001. IH 41 ramps & oklahoma ave (658.5070) | EACH | 1 | $6,000.00 | $6,000.00 | $6,000.00 |
| 231 | Signal mounting hardware (location) 002. IH 41 SB off ramp & W lincoln ave (658.5070) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 |
| 232 | Signal mounting hardware (location) 003. IH 41 NB off ramp & W national ave (658.5070) | EACH | 1 | $4,200.00 | $4,200.00 | $4,200.00 |
| 233 | Underdeck lighting (structure) 001. B-40-119 & 120 (659.0601) | EACH | 1 | $18,000 | $18,000 | $18,000 |
| 234 | Luminaires utility LED C (659.1125) | EACH | 7 | $240.00 | $240.00 | $240.00 |
| 235 | Luminaires underdeck LED C (659.1215) | EACH | 4 | $280.00 | $280.00 | $280.00 |
| 236 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 68 | $75.00 | $75.00 | $75.00 |
| 237 | Temporary traffic signals for intersections (location) 301. IH 41 SB ramps & oklahoma ave (661.0201) | EACH | 1 | $40,000 | $40,000 | $40,000 |
| 238 | Temporary traffic signals for intersections (location) 302. IH 41 NB ramps & oklahoma ave (661.0201) | EACH | 1 | $40,000 | $40,000 | $40,000 |
| 239 | Temporary traffic signals for intersections (location) 303. IH 41 NB off ramp & W. national ave (661.0201) | EACH | 1 | $55,000 | $55,000 | $55,000 |
| 240 | Temporary traffic signals for intersections (location) 304. S. 124TH ST & W. layton ave (661.0201) | EACH | 1 | $40,000 | $40,000 | $40,000 |
| 241 | Generators (661.0300) | DAY | 3 | $500.00 | $500.00 | $500.00 |
| 242 | Field system integrator (670.0101) | EACH | 1 | $30,500 | $30,500 | $30,500 |
| 243 | ITS documentation (670.0201) | EACH | 1 | $6,000.00 | $6,000.00 | $6,000.00 |
| 244 | Remove cable (674.0300) | LF | 290 | $2.00 | $2.00 | $2.00 |
| 245 | Reinstall cable (674.0400) | LF | 245 | $3.50 | $3.50 | $3.50 |
| 246 | Sawing asphalt (690.0150) | LF | 42 | $1.75 | $1.75 | $10.00 |
| 247 | Sawing concrete (690.0250) | LF | 75,018 | $2.35 | $2.35 | $10.00 |
| 248 | Incentive strength concrete structures (715.0502) | DOL | 3,594 | $1.00 | $1.00 | $1.00 |
| 249 | Incentive strength concrete barrier (715.0603) | DOL | 17 | $1.00 | $1.00 | $1.00 |
| 250 | Incentive iri ride (740.0440) | DOL | 7,220 | $1.00 | $1.00 | $1.00 |
| 251 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 3,600 | $5.00 | $5.00 | $5.00 |
| 252 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 6,000 | $5.00 | $5.00 | $5.00 |
| 253 | Special 400. polyester polymer concrete deck repair (SPV.0035) | CY | 28 | $4,300.00 | $4,300.00 | $4,300.00 |
| 254 | Special 401. rapid set deck repair (SPV.0035) | CY | 3 | $2,900.00 | $2,900.00 | $2,900.00 |
| 255 | Special 001. handrail and guardrail extension (SPV.0060) | EACH | 2 | $4,000.00 | $5,000.00 | $4,000.00 |
| 256 | Special 002. adjusting water valve boxes - milwaukee water works (SPV.0060) | EACH | 2 | $2,100.00 | $1,000.00 | $750.00 |
| 257 | Special 003. adjusting water valve boxes - city of west allis (SPV.0060) | EACH | 4 | $2,100.00 | $1,000.00 | $1,200.00 |
| 258 | Special 004. reconnect storm sewer laterals (SPV.0060) | EACH | 1 | $2,000.00 | $2,000.00 | $1,700.00 |
| 259 | Special 005. field facilities office space (SPV.0060) | EACH | 1 | $20,629 | $120,000 | $46,500 |
| 260 | Special 006. traffic control close- open freeway entrance ramp (SPV.0060) | EACH | 435 | $145.00 | $100.00 | $145.00 |
| 261 | Special 007. traffic control close- open freeway to freeway system ramp (SPV.0060) | EACH | 294 | $300.00 | $500.00 | $300.00 |
| 262 | Special 008. traffic control full freeway closure (SPV.0060) | EACH | 5 | $3,325.00 | $1,400.00 | $3,325.00 |
| 263 | Special 010. survey project 1090- 03-75 (SPV.0060) | EACH | 1 | $42,500 | $42,500 | $42,500 |
| 264 | Special 011. survey project 1100- 05-73 (SPV.0060) | EACH | 1 | $42,500 | $42,500 | $42,500 |
| 265 | Special 012. mobilizations emergency pavement repair (SPV.0060) | EACH | 2 | $4,850.00 | $5,500.00 | $4,850.00 |
| 266 | Special 200. salvaging type 1 advance flasher assemblies (SPV.0060) | EACH | 2 | $1,200.00 | $1,200.00 | $1,200.00 |
| 267 | Special 201. install salvaged type 1 advance flasher assembly (SPV.0060) | EACH | 2 | $2,000.00 | $2,000.00 | $2,000.00 |
| 268 | Special 202. store cable (SPV.0060) | EACH | 1 | $500.00 | $500.00 | $500.00 |
| 269 | Special 300. install poles type 9 (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 |
| 270 | Special 301. install poles type 10 (SPV.0060) | EACH | 3 | $1,500.00 | $1,500.00 | $1,500.00 |
| 271 | Special 302. install poles type 9 special (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 |
| 272 | Special 303. install monotube arms 25-FT (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 |
| 273 | Special 304. install monotube arms 30-FT (SPV.0060) | EACH | 3 | $1,500.00 | $1,500.00 | $1,500.00 |
| 274 | Special 305. install monotube arms 35-FT type 9/10 spec pole (SPV.0060) | EACH | 1 | $1,500.00 | $1,500.00 | $1,500.00 |
| 275 | Special 306. install monotube arms 40-FT type 9/10 spec pole (SPV.0060) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 |
| 276 | Special 307. install luminaire arms steel 15-FT (SPV.0060) | EACH | 6 | $250.00 | $250.00 | $250.00 |
| 277 | Special 308.transport & install state-furnished traf sig cabinet IH41 ramps&oklahoma ave (SPV.0060) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 |
| 278 | Special 309. transport traf sig & intersection light matl IH41 ramps & oklahoma ave (SPV.0060) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 |
| 279 | Special 310.transport traf sig&intersection light matl IH 41 NB off ramp&W. national ave (SPV.0060) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 |
| 280 | Special 311. temporary infrared evp system IH41 NB off ramp & W. national ave (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 |
| 281 | Special 312.transport & install SF evp detector heads IH 41 ramps & oklahoma ave (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 |
| 282 | Special 313.transport & install SF evp detector heads IH 41 NB off ramp& W. national ave (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 |
| 283 | Special 314. remove, salvage & reinstall FO interconnect IH 41 & ramps & oklahoma ave (SPV.0060) | EACH | 1 | $7,500.00 | $7,500.00 | $7,500.00 |
| 284 | Special 315. install state-furnished video detection system S. 124TH ST & W. layton ave (SPV.0060) | EACH | 1 | $4,500.00 | $4,500.00 | $4,500.00 |
| 285 | Special 400. embedded galvanic anodes (SPV.0060) | EACH | 351 | $33.00 | $33.00 | $33.00 |
| 286 | Special 401. cleaning and painting bearings (SPV.0060) | EACH | 28 | $1,500.00 | $1,500.00 | $1,500.00 |
| 287 | Special 402. deck drain cleaning (SPV.0060) | EACH | 14 | $270.00 | $270.00 | $270.00 |
| 288 | Special 403. fence repair (SPV.0060) | EACH | 2 | $5,050.00 | $5,000.00 | $5,000.00 |
| 289 | Special 404. cleaning and painting pin and hanger assemblies (SPV.0060) | EACH | 43 | $7,600.00 | $7,600.00 | $7,600.00 |
| 290 | Special 405. bearing maintenance special B-40-188 (SPV.0060) | EACH | 6 | $3,200.00 | $3,200.00 | $3,200.00 |
| 291 | Special 406. cleaning and sealing concrete girder ends (SPV.0060) | EACH | 55 | $450.00 | $450.00 | $450.00 |
| 292 | Special 407. strapping B-40-303 (SPV.0060) | EACH | 1 | $3,500.00 | $3,500.00 | $3,500.00 |
| 293 | Special 001. pavement cleanup project 1100-05-73 (SPV.0075) | HRS | 200 | $370.79 | $300.00 | $185.00 |
| 294 | Special 001. concrete curb & gutter 31-inch, modified (SPV.0090) | LF | 444 | $40.00 | $40.00 | $40.00 |
| 295 | Special 002. special concrete joint repair (SPV.0090) | LF | 5,000 | $9.38 | $25.00 | $33.00 |
| 296 | Special 101. city furnished electrical cable type 1#8/7#16 XLP, 5KV (SPV.0090) | LF | 740 | $2.50 | $2.50 | $2.50 |
| 297 | Special 400. strip seal expansion joint gland replacement (SPV.0090) | LF | 672 | $80.00 | $80.00 | $80.00 |
| 298 | Special 401. modular expansion joint gland replacement (SPV.0090) | LF | 123 | $95.00 | $95.00 | $95.00 |
| 299 | Special 400. removing loose concrete overhead (SPV.0165) | SF | 520 | $30.00 | $30.00 | $30.00 |
| 300 | Special 401. concrete girder repair (SPV.0165) | SF | 94 | $350.00 | $350.00 | $350.00 |
| 301 | Special 402. fiber wrap reinforcing non-structural (SPV.0165) | SF | 646 | $55.00 | $92.00 | $92.00 |
| 302 | Special 001. resin binder high friction surface treatment modified (SPV.0180) | SY | 29,593 | $20.65 | $20.65 | $20.65 |
| 303 | Special 400. high friction surface treatment polymer overlay (SPV.0180) | SY | 2,547 | $49.75 | $54.75 | $54.75 |
| 304 | Special 401. abutment seat cleaning and sealing (SPV.0180) | SY | 149 | $70.00 | $70.00 | $70.00 |
| 305 | Special 402. methacrylate flood seal (SPV.0180) | SY | 7,842 | $14.00 | $14.00 | $14.00 |
| 306 | Special 001. HMA longitudinal joint repair (SPV.0195) | TON | 100 | $333.00 | $333.00 | $333.00 |
| 307 | Special 002. HMA transverse joint repair (SPV.0195) | TON | 50 | $333.00 | $333.00 | $333.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.