Closeout documents, checked system by system
Send us the specification's closeout and commissioning sections with what the trades have turned over so far. Mirage lists what is missing for each system, assembles O&M manuals, warranties, spare parts and record drawings by system, and keeps the register current until handover.
MasterFormat files ten closeout submittal sections under 01 78 00 alone. Commissioning then adds construction checklists and functional tests for each commissioned system, plus an issues log. Every document turned over has to be matched to the requirement it answers.
What the specification asks for at closeout
To check a turnover, you first need to know what the specification asks for. In a project manual organized by MasterFormat, closeout and commissioning requirements sit in Division 01 and in the 08 00 section of each facility services division. The numbers and titles below come from the 2018 edition of CSI's master list. Check them against the edition and the table of contents of your own project manual.
| Section | Title |
|---|---|
| 01 75 00 | Starting and Adjusting (01 75 13 Checkout Procedures, 01 75 16 Startup Procedures) |
| 01 77 00 | Closeout Procedures (01 77 13 Preliminary Closeout Reviews, 01 77 16 Final Closeout Reviews, 01 77 19 Closeout Requirements) |
| 01 78 13 | Completion and Correction List |
| 01 78 19 | Maintenance Contracts |
| 01 78 23 | Operation and Maintenance Data (.13 Operation Data, .16 Maintenance Data, .19 Preventative Maintenance Instructions) |
| 01 78 29 | Final Site Survey |
| 01 78 33 | Bonds |
| 01 78 36 | Warranties |
| 01 78 39 | Project Record Documents |
| 01 78 43 | Spare Parts |
| 01 78 46 | Extra Stock Materials |
| 01 78 53 | Sustainable Design Closeout Documentation |
| 01 79 00 | Demonstration and Training |
| 01 91 00 | Commissioning (01 91 13 General Commissioning Requirements) |
| 21 08 00 | Commissioning of Fire Suppression |
| 22 08 00 | Commissioning of Plumbing |
| 23 08 00 | Commissioning of HVAC |
| 25 08 00 | Commissioning of Integrated Automation |
| 26 08 00 | Commissioning of Electrical Systems |
| 27 08 00 | Commissioning of Communications |
| 28 08 00 | Commissioning of Electronic Safety and Security |
The contract side of closeout, meaning final completion and final payment, is set by the contract form, not by Division 01. See the closeout section of the AIA contract documents guide. Punch lists are drawn up at the walk-through before substantial completion, and they have their own page: see the free punch list template.
Commissioning records
Commissioning adds records of its own to the turnover. ASHRAE publishes the two reference documents on the process, and sells both. Guideline 0-2019, The Commissioning Process for New Buildings and New Systems, presents best practices for applying whole-building commissioning to all phases of new construction and renovation. Standard 202-2024, The Commissioning Process Requirements for New Buildings and New Systems, describes the process, the roles of the principal agents and stakeholders, and a framework for design documents, specifications, procedures, documentation and reports (ASHRAE's own summary).
The US General Services Administration's Commissioning Guide (September 2020) shows the records this produces on a federal building. Construction checklists come first. The commissioning provider develops them, the construction manager as advisor maintains them, and the contractor and subcontractors use them from equipment delivery until the system is started up and operational, testing, adjusting and balancing and controls included. Functional performance testing then takes over where the construction checklists end, to check that the components of a system work together to meet the Owner's Project Requirements. Every comment and issue goes into a formal issues log whose minimum fields include a description, the cause and a recommendation. The guide's list of commissioning activities and documents also names operation and maintenance (O&M) manual review, training, warranty review and test data reports. Its responsibilities matrix has the commissioning provider verify that design changes are reflected in the as-built documents.
In England, a higher-risk building also carries the golden thread. This is a digital record of building information, kept from design through the building's life and handed to the accountable person when the work is complete (Building Safety Regulator). See the golden thread record for what Mirage builds there.
What Mirage does with a turnover package
Turns the closeout sections into a list per system
Mirage reads Division 01 and the commissioning sections of the systems divisions, and extracts every closeout submittal and commissioning record they require. It then lists them per system, with what is required, from which trade and in what form.
Checks what was turned over against that list
Mirage matches construction checklists, functional performance test records, inspection and test plans, O&M data, warranties, spare parts lists and record drawings to the requirement each one answers. Anything missing, unsigned, for the wrong equipment or on a superseded revision is listed per system.
Assembles the package by system, a person signs off
Mirage files O&M manuals, warranties, spare parts and as-builts by system, and keeps the register current until handover. The commissioning provider or the project's handover lead accepts each system. The agent never marks one accepted.
A turnover register by system
An illustrative register: systems, tags and documents are invented.
| System | Requirement | Section | Received | Status |
|---|---|---|---|---|
| AHU-3, air handling unit↳ Results are filled in but the witness line is empty: listed against the mechanical contractor and the commissioning provider before the system is marked complete. | Functional performance test, witnessed and signed | 23 08 00 | Test sheet, no witness signature | Incomplete |
| Fire pump FP-1↳ The manual covers another model than the approved submittal; flagged before it goes into the O&M binder. | Operation and maintenance data | 01 78 23 | Manual for another pump model | Wrong equipment |
| Switchgear SWG-1 | Manufacturer warranty | 01 78 36 | Warranty letter | Received |
| Domestic water heaters | Spare parts list | 01 78 43 | Not received | Missing |
| Level 3 ductwork | Record drawings | 01 78 39 | M-301 rev. C | Superseded by rev. D |
What goes in, what comes out
- Who uses it
- Commissioning leads, project managers and document controllers assembling the turnover; the commissioning provider and the owner's facilities team receiving it.
- What goes in
- The project manual's closeout and commissioning sections, the commissioning plan if there is one, approved submittals, construction checklists, functional performance test records, inspection and test plans, O&M data, warranties, spare parts lists and record drawings. Documents in English or French.
- What comes out
- A requirement list per system, what is missing or wrong against each line, O&M manuals, warranties, spares and as-builts filed by system, and a register kept current until handover.
- Where a person decides
- The commissioning provider, or the project's handover lead, accepts each system and signs off the turnover.
- What it does not do
- It does not plan, perform or witness tests, and it is not commissioning software: it reads and files the documents commissioning and closeout produce.
- Where it runs
- In your cloud, on your premises or hosted by Mirage, with a named approver set for the workflow.
- How long it takes
- A reply within two business hours, a proof of concept one week after the first meeting, the first workflow in production in 4 to 6 weeks.
- How it is priced
- A fixed-price pilot first, then an annual subscription priced by volume, not per user.
What is published, and what is not
No Mirage deployment on commissioning or closeout documents is published yet. The two construction deployments below are takeoff work, which is a different workflow. What they share with this one is that every output is tied back to the document it came from.
OCBM
3 agents in production
100% of quantities traceable to a source drawing
Workflow: quantity takeoff and bid pricing
John Cockerill
80 to 90% less time on piping takeoff
Fabrication bill of materials produced ten times faster
Workflow: piping takeoff and bill of materials
Send us the closeout sections and what has been turned over
We send back the requirement list per system and what is missing against each line.
How a deployment runs: Observe, Map, Build, Run, Expand. See the method
Frequently asked questions
Closeout documents are the documents a contractor turns over at the end of a project, as the specification lists them. In a project manual organized by MasterFormat, they sit under 01 78 00 Closeout Submittals. There you find operation and maintenance data, warranties, project record documents, spare parts, extra stock materials, bonds, maintenance contracts, the final site survey, the completion and correction list and sustainable design closeout documentation.
A turnover package holds whatever your project manual's closeout and commissioning sections require. Those are the 01 78 00 closeout submittals, the demonstration and training of 01 79 00, and the commissioning records, such as construction checklists, functional performance tests and the issues log. The list that binds you is your own specification's.
The specification lists closeout requirements in Division 01, under 01 77 00 Closeout Procedures, 01 78 00 Closeout Submittals, 01 79 00 Demonstration and Training and 01 91 00 Commissioning. Each facility services division also has a commissioning section at 08 00, such as 23 08 00 Commissioning of HVAC (MasterFormat 2018 numbers and titles).
In GSA's Commissioning Guide, construction checklists and functional performance tests cover two successive stages. Construction checklists run from the delivery of equipment until the system is started up and operational. Functional performance testing then takes over where they end, to check that the components of a system work together to meet the Owner's Project Requirements.
ASHRAE Guideline 0-2019 presents best practices for whole-building commissioning across new construction and renovation. Standard 202-2024 describes the commissioning process for new buildings and new systems, the roles of the principal agents and stakeholders, and a framework for the documents and reports it produces. ASHRAE sells both, so these summaries are ASHRAE's own.
No, Mirage is not commissioning software: it does not plan, perform or witness tests. It reads the documents that commissioning and closeout produce, checks them against the specification and files them by system. The commissioning provider and the project's handover lead decide what is accepted.
No Mirage deployment on commissioning or closeout documents is published yet. The nearest published construction work is OCBM, with 3 agents in production and 100% of quantities traceable to a source drawing, and John Cockerill, with 80 to 90% less time on piping takeoff. Both are takeoff workflows.
It is priced as a fixed-price pilot first, then an annual subscription priced by volume, not per user.
Sources
Checked . Because ASHRAE sells Guideline 0 and Standard 202, they are described here from ASHRAE's own summary, not quoted.
- CSI and CSC, MasterFormat 2018 Edition, Groups, Subgroups and Divisions and Master List (PDF hosted by AGC Austin): the Division 01 numbers and titles from 01 75 00 to 01 91 13, and the 08 00 commissioning sections of Divisions 21 to 28.
- ASHRAE, ASHRAE Standards Summary (PDF): titles and scope of Guideline 0-2019 and Standard 202-2024.
- US General Services Administration, GSA Commissioning Guide (September 2020, hosted by the Whole Building Design Guide): construction checklists, functional performance testing, the issues log and its minimum fields, the list of commissioning activities and documents, verification of design changes in the as-built documents.
- Building Safety Regulator, Understanding the golden thread (GOV.UK campaign site): the golden thread as a digital record kept from design through the building's life, handed to the accountable person when the work is complete.