Research record, not reviewed
Bloor-Yonge Station Capacity Improvements
- Location
- Toronto, ON, Canada. Location shown at city level. See it on the map
- Stage
- Stage not confirmed: Not collected yet.
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Toronto Transit Commission | |
| Category | Urban transit | |
| Amount | C$1.514 billion (Canadian dollars), as of April 30, 2026 | Toronto Transit Commission |
| What the amount covers | Budget: Estimated Final Cost (EFC) $1,514.0M and Total Approved Budget $1,514.0M (period ended 30 April 2026). 'The Estimated Final Cost (EFC), as reported to the Board in February 2025, is based on a 2021 estimate and has not been fully adjusted for escalation'; Platform Edge Doors and Net Zero scope are not reflected in it. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| C$1.51 bn | Budget | Whole project | 30 Apr 2026 | Toronto Transit CommissionEstimated Final Cost (EFC) $1,514.0M and Total Approved Budget $1,514.0M (period ended 30 April 2026). 'The Estimated Final Cost (EFC), as reported to the Board in February 2025, is based on a 2021 estimate and has not been fully adjusted for escalation'; Platform Edge Doors and Net Zero scope are not reflected in it. |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Kenaidan Murphy Joint Venture (KMJV) | progressive design-builder | Progressive Design-Build (PDB) contract, Development Phase | Toronto Transit Commission |
About the project
TTC major projects report identifies a C$1.514bn estimated final cost for the retrofit and capacity expansion of the Bloor-Yonge interchange station, based on a 2021 estimate not fully adjusted for escalation.
Scope notes
- TTC major projects report identifies C$1.514bn estimated total for retrofit and capacity expansion at the Bloor–Yonge interchange. Toronto Transit Commission
Sources
- Bloor-Yonge Station Capacity Improvements – official project evidence, Toronto Transit Commission, 2026. TTC major projects report identifies C$1.514bn estimated total for retrofit and capacity expansion at the Bloor–Yonge interchange.. Consulted 9 Nov 2026.
Research leads not yet reviewed: www.renewcanada.net.