Research record, not reviewed
METRO Green Line Extension
- Location
- Minneapolis, MN, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of November 19, 2026 (Metropolitan Council).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Metropolitan Council (Metro Transit) | |
| Category | Urban transit | |
| Route length | 14.5 mi | Metropolitan Council |
| New stations | 16 | Metropolitan Council |
| Amount | US$2.86 billion (US dollars), as of June 2025 | Metropolitan Council |
| What the amount covers | Budget. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.86 bn | Budget | Whole project | Jun 2025 | Metropolitan Council |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| C. S. McCrossan (partnered with Lunda Construction) | construction contractor, with Lunda Construction | METRO Green Line Extension (Southwest LRT) civil construction, Eden Prairie to Downtown Minneapolis | C. S. McCrossan |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| December 11, 2024 | budget authorized | Whole project | Metropolitan Council |
| June 12, 2027 | planned opening | Whole project | Metropolitan Council |
About the project
A 14.5-mile double-track light rail extension of the METRO Green Line from downtown Minneapolis through St. Louis Park, Hopkins and Minnetonka to Eden Prairie, with 16 new stations. The Metropolitan Council authorized an overall project budget of $2.86 billion on December 11, 2024. Systems testing began in July 2025; opening is set for June 12, 2027.
Sources
- Business Item 2025-145, Transportation Committee, June 23, 2025: Purchase of Non-Revenue Vehicles and Equipment for the Green Line Extension, Metropolitan Council, 23 Jun 2025. Background paragraph: 'authorized the overall METRO Green Line Extension project budget of $2.86 billion'. Consulted 12 Nov 2026.
- METRO Green Line Extension project page, Metropolitan Council. Page states 14.5 miles of double track, 16 new stations, opening June 12, 2027. Consulted 12 Nov 2026.
- Metro Green Line Extension (SW Light Rail Transit) (project page), C. S. McCrossan. 'Owner: Metropolitan Council; Contract Value: $799,500,000 [...] For this large project, C. S. McCrossan partnered with Lunda Construction and this project marks the third time C. S. McCrossan has been involved in the construction of a Met Council light rail project in the metro area, and this one is also the longest.'. Consulted 18 Nov 2026.
- METRO Green Line Extension: Systems Testing, Metropolitan Council. 'Testing of the Green Line Extension began in July 2025 and will continue until the line opens in 2027.'. Consulted 19 Nov 2026.