PDX Main Terminal Reconstruction (PDX Next)
- Location
- Portland, OR, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of June 2026 (Port of Portland).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Port of Portland | |
| Category | Airports | |
| Amount | US$2.15 billion (US dollars), as of June 2026 | Port of Portland |
| What the amount covers | Project value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.15 bn | Project value | Whole project | Jun 2026 | Port of Portland |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Hoffman Skanska Joint Venture (Hoffman Construction Company and Skanska USA) | CMGC (construction manager/general contractor, GMP) | PDX Terminal Core Redevelopment | Hoffman Construction Company |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| August 2024 | opening | Whole project | Port of Portland |
| June 30, 2026 | completion | Whole project | ZGF Architects |
About the project
$2.15 billion reconstruction of Portland International Airport's main terminal (the terminal core expansion as approved by the airlines), with major seismic upgrades and capacity for passenger growth through 2045, about 35 million annual passengers. Phase 1 of the new main terminal opened to the public in August 2024; the second and final phase opened on June 30, 2026, completing what its architect calls the largest public infrastructure project delivered in Oregon's history.
Sources
- We Made It, PDX! Our Journey to Create the Local-est Airport Yet is Complete, Port of Portland (FlyPDX), 30 Jun 2026. Body: 'Over 11-years, this $2.15 billion-dollar effort modernized PDX'; 'Today, June 30, the Port of Portland celebrates the completion'. Consulted 12 Nov 2026.
- The local-est airport yet: The new PDX starts opening Aug. 14, Port of Portland (FlyPDX), 14 Aug 2024. Body: 'Today, arriving and departing travelers at Portland International Airport (PDX) will see the new main terminal for the first time'; 'The $2.15 billion expansion is being completed in two phases'; final phase starts Aug. 15, complete by early 2026. Consulted 12 Nov 2026.
- PDX Terminal Core Redevelopment (project page), Hoffman Construction Company. 'Owner: Port of Portland; Architect: ZGF Architects; Delivery: CMGC, GMP; Value: $1,790,000,000 [...] Hoffman has teamed up with Skanska USA to create the Hoffman Skanska Joint Venture.'. Consulted 18 Nov 2026.
- Official Statement, Portland International Airport Revenue Bonds Series Twenty-Nine (AMT) (Green Bonds), Port of Portland, 21 Mar 2023. 'In 2016, 2017, 2019, and 2022 the Signatory Airlines (defined herein) approved, in four ballots, the expansion of the terminal core area (Terminal Core Redevelopment project) totaling $2.15 billion, which included the reconfiguration and rehabilitation of Concourse B and the construction of Floors 2-4 of the Rental Car Center building.'. Consulted 19 Nov 2026.
- 2025-26 Budget, Port of Portland, 2025. 'In August 2024, Phase 1 of PDX's new main terminal - inspired by a walk in a forest - opened to the public, along with 12 new local places to eat, shop, and drink.'. Consulted 19 Nov 2026.
- Portland International Airport Main Terminal Completes, ZGF Architects, 30 Jun 2026. 'The second and final phase of the globally acclaimed Portland International Airport (PDX) main terminal expansion is now open.'. Consulted 19 Nov 2026.