FieldValueSource
Owners or sponsorsTualatin Valley Water District, City of Hillsboro, City of Beaverton
CategoryWater
AmountUS$1.3 billion (US dollars), as of August 16, 2019U.S. Environmental Protection Agency
What the amount coversCost of the WIFIA-financed scope: Cost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost.
Threshold evidenceOnly a financed-scope figure meets the threshold; to reconcile
Sourced facts in the research record

Water projects are counted apart and left out of totals while their place in the atlas is decided.

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.3 bnCost of the WIFIA-financed scopeScope financed by WIFIA16 Aug 2019U.S. Environmental Protection AgencyCost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost.
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
Sundt Construction, Inc.construction manager/general contractorWTP_1.0: Willamette Water Supply Water Treatment PlantWillamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Kiewit Infrastructure West Co.construction manager/general contractorRWF_1.0: raw water facilitiesWillamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Hoffman-Fowler LLCconstruction manager/general contractorRes_1.0-PLM_5.3: reservoirs and pipeline section PLM_5.3Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Emery & Sons Construction Group, LLCcontractorPipeline packages PLM_2.0, PLM_5.2, MPE_1.2-COB_1.2, MPE_1.3Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Tapani, Inc.contractorPipeline packages PLM_4.2, PLM_4.3, PLM_4.4, PLW_1.2, PLW_1.3 (and PLM_5.1 with Moore Excavation Inc.)Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Moore Excavation, Inc.contractorPipeline packages PLM_1.2, PLM_1.3, PLM_4.1, PLW_2.1, MPE_1.1-COB_1.1Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Kerr Contractors Inc.contractorPipeline packages PLM_3.0, PLW_1.1Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
James W. Fowler Co.contractorPipeline package PLM_1.1Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro)
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
August 16, 2019Financing closedScope financed by WIFIAU.S. Environmental Protection Agency
Dated milestones, at the precision of their source

About the project

The EPA describes the shared water supply system and identifies intake, pipeline, plant and reservoirs. Two loan rows describe the same programme.

Scope notes

  • The EPA describes the shared water supply system and identifies intake, pipeline, plant and reservoirs. Two loan rows describe the same programme. U.S. Environmental Protection Agency

Sources

  • Willamette Water Supply Program – WIFIA profile, U.S. Environmental Protection Agency. Total WIFIA Project Costs; Project Description. The EPA closed-loan register gives the separate closing date.. Consulted 9 Nov 2026.
  • WIFIA Closed Loans, U.S. Environmental Protection Agency. Borrower, Project Name, Close Date and Loan Amount columns.. Consulted 9 Nov 2026.
  • Contracting Opportunities - Awarded Contracts, Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro). 'WTP_1.0 CM/GC | Sundt Construction, Inc. | RFP'. Consulted 18 Nov 2026.
  • Beaverton, Willamette Water Supply Program (Tualatin Valley Water District / City of Hillsboro). 'As of July 1, 2019, the City of Beaverton will officially become a part owner of the WWSS, receiving up to five million gallons per day when it is operational.'. Consulted 19 Nov 2026.

See it on the map. How the atlas qualifies a record.