Northwest Langley Wastewater Treatment Plant
- Location
- Langley, BC, Canada. Location shown at city level. See it on the map
- Stage
- Stage not confirmed: Not collected yet.
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Metro Vancouver | |
| Category | Water | |
| Amount | C$2.281 billion (Canadian dollars), as of May 31, 2026 | Metro Vancouver |
| What the amount covers | Capital estimate: 'Project Estimate' 2,280,650,000 for the 'Northwest Langley Wastewater Treatment Program' in 'Capital Expenditures as of May 31, 2026' (Liquid Waste Committee agenda, July 15, 2026, p. 44); 'Budget On budget (endorsed at Stage Gate 2) - reviewing impact due to schedule delay and market feedback'. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Water projects are counted apart and left out of totals while their place in the atlas is decided.
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| C$2.28 bn | Capital estimate | Whole project | 31 May 2026 | Metro Vancouver'Project Estimate' 2,280,650,000 for the 'Northwest Langley Wastewater Treatment Program' in 'Capital Expenditures as of May 31, 2026' (Liquid Waste Committee agenda, July 15, 2026, p. 44); 'Budget On budget (endorsed at Stage Gate 2) - reviewing impact due to schedule delay and market feedback'. |
Contracts and teams
Contracts and teams: No construction contract awarded yet Metro Vancouver.
About the project
Metro Vancouver's capital program update of July 2026 gives a project estimate of C$2.28bn for the Northwest Langley Wastewater Treatment Program as of May 31, 2026; its budget is being reviewed for the impact of the schedule delay and market feedback.
Scope notes
- Historical C$2.28bn estimate in the Liquid Waste Committee agenda. Metro Vancouver
Sources
- Northwest Langley Wastewater Treatment Plant – official project evidence, Metro Vancouver, 17 May 2023. Historical C$2.28bn estimate in the Liquid Waste Committee agenda.. Consulted 9 Nov 2026.
- Liquid Waste Committee Regular Meeting agenda, July 15, 2026 (Liquid Waste Services capital program status), Metro Vancouver, 8 Jul 2026. 'Pre-construction recommenced in May 2026 to prepare for construction of the wastewater treatment plant that is set to commence in 2028. ... the GVS&DD Board will receive an update at the next Stage Gate 3 to seek approval to proceed to construction. ... Northwest Langley Wastewater Treatment Plant Expansion Program ... Detailed Design approximately 90% complete ... Next Milestone Stage Gate 3 –...'. Consulted 18 Nov 2026.
Research leads not yet reviewed: www.renewcanada.net.