ARDOT contract A10050 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO LEVEL UP AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 18.459 MILES OF HIGHWAY 49 IN CROSS, MONROE, AND WOODRUFF COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ULTRATHIN BONDED WEARING COURSE, COLD MILLING ASPHALT PAVEMENT, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL ITEMS, RUMBLE STRIPES, PORTABLE TRAFFIC SIGNAL SYSTEM, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Cross, Monroe, Woodruff. 5 bids received; low bid $3,812,007 by Atlas Asphalt, Inc..

Owner
Arkansas DOT
Letting
05 NOV 2025
Pay items
29
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlas Asphalt, Inc.$3,812,007Low
2CK Asphalt, LLC$4,188,106+10%
3Rogers Group, Inc.$4,470,491+17%
4Delta Asphalt of Arkansas, Inc.$4,600,514+21%
5Apac-Tennessee, Inc.$5,378,809+41%
ARDOT contract A10050: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlas Asphalt, Inc.2. CK Asphalt, LLC3. Rogers Group, Inc.4. Delta Asphalt of Arkansas, Inc.5. Apac-Tennessee, Inc.
0001Removal and disposal of guardrail (202132)LF550$8.50$6.50$9.00$8.50$8.63
0002Trenching and shoulder preparation (215011)STA9$631.23$155.00$250.00$589.21$303.00
0003Aggregate base course (class 7) (303117)TON2,491$45.73$38.50$49.00$44.12$58.76
0004Tack coat (401011)GAL52,780$0.01$1.00$1.00$2.52$4.31
0005Mineral aggregate in achm surface course (3/8") (407161)TON16,040$88.43$101.94$72.50$102.42$141.00
0006Asphalt binder (PG 70-22) in achm surface course (3/8") (minimum bid $120.00) (407441)TON1,078$120.00$120.00$654.00$120.00$120.00
0007Ultrathin bonded wearing course (3/4"-type C) (407904)TON12,237$119.54$119.82$135.00$139.62$148.77
0008Cold milling asphalt pavement (412002)SY5,355$2.90$6.20$4.00$8.42$15.00
0009Achm patching of existing roadway (415011)TON100$120.00$155.00$185.00$248.32$250.00
0010Approach gutters (504264)CY7.95$3,302.65$3,750.00$3,500.00$3,750.00$3,806.25
0011Maintenance of traffic (603009)LS1$117,674$120,000$95,000$90,000$10,000
0012Signs (604003)SF1,012$6.00$6.00$8.40$10.00$10.15
0013Traffic drums (604023)EACH60$23.00$23.00$42.00$45.00$45.68
0014Construction pavement markings (604041)LF477,502$0.15$0.15$0.16$0.15$0.16
0015Guardrail (type A) (617005)LF400$30.00$30.00$32.00$30.00$30.45
0016Guardrail terminal (type 2) (617312)EACH3$3,000.00$3,000.00$3,185.00$3,000.00$3,045.00
0017Silt fence (621021)LF1,200$0.48$3.25$3.40$3.25$3.30
0018Sediment removal and disposal (621111)CY44$0.36$2.00$65.00$91.86$40.00
0019Roadway construction control (635001)LS1$1,509.09$18,500$10,000$35,000$50,000
0020Rumble stripes in asphalt shoulders (642011)LF194,624$0.07$0.17$0.18$0.12$0.12
0021Centerline rumble stripes in asphalt roadways (642102)LF97,312$0.14$0.15$0.18$0.12$0.12
0022Portable traffic signal system - actuated (701603)WEEK16$1,578.00$1,800.00$1,050.00$1,000.00$1,015.00
0023Thermoplastic pavement marking white (6") (719002)LF194,924$0.60$0.59$0.61$0.60$0.61
0024Thermoplastic pavement marking yellow (6") (719102)LF43,827$0.60$0.59$0.61$0.60$0.61
0025Thermoplastic pavement marking (railroad emblems) (719203)EACH1$650.00$850.00$880.00$650.00$650.00
0026Raised pavement markers (type II) (721002)EACH1,220$4.00$4.00$4.15$4.00$4.00
0027Bridge end terminal (734011)EACH5$28,685$28,500$29,250$27,500$28,000
0028Reinforcing steel-roadway (grade 60) (804003)LB595$3.00$3.50$3.20$2.50$2.54
0029Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$56,499$115,000$110,000$190,000$130,000
ARDOT contract A10050: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy