ARDOT contract A60039 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 5.436 MILES OF HIGHWAY 33 IN PRAIRIE COUNTY. THIS PROJECT CONSISTS OF TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, EROSION CONTROL, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Prairie. 5 bids received; low bid $2,041,301 by Rogers Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 15 JAN 2025
- Pay items
- 25
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $2,041,301 | Low |
| 2 | Atlas Asphalt, Inc. | $2,227,486 | +9.0% |
| 3 | Redstone Construction Group, Inc. | $2,562,481 | +26% |
| 4 | Delta Asphalt of Arkansas, Inc. | $2,749,578 | +35% |
| 5 | Cranford Construction Co. | $2,811,773 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. Atlas Asphalt, Inc. | 3. Redstone Construction Group, Inc. | 4. Delta Asphalt of Arkansas, Inc. | 5. Cranford Construction Co. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Trenching and shoulder preparation (215011) | STA | 286 | $74.00 | $53.78 | $210.50 | $69.13 | $116.42 |
| 0002 | Aggregate base course (class 7) (303117) | TON | 861 | $60.00 | $47.43 | $50.01 | $47.39 | $63.50 |
| 0003 | Tack coat (401011) | GAL | 16,839 | $0.01 | $0.01 | $0.10 | $0.01 | $0.01 |
| 0004 | Mineral aggregate in achm binder course (1") (406161) | TON | 2,664 | $70.00 | $98.09 | $120.00 | $88.75 | $120.82 |
| 0005 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 126 | $590.00 | $120.00 | $120.00 | $600.00 | $120.00 |
| 0006 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 13,154 | $32.00 | $101.80 | $115.00 | $91.27 | $123.22 |
| 0007 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 766 | $1,000.00 | $120.00 | $120.00 | $600.00 | $120.00 |
| 0008 | Cold milling asphalt pavement (412002) | SY | 959 | $6.00 | $11.21 | $13.93 | $19.21 | $30.23 |
| 0009 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 136 | $200.00 | $175.00 | $200.00 | $464.89 | $336.38 |
| 0010 | Achm patching of existing roadway (415011) | TON | 500 | $175.00 | $175.00 | $396.07 | $351.27 | $261.87 |
| 0011 | Maintenance of traffic (603009) | LS | 1 | $90,000 | $182,160 | $59,437 | $65,000 | $146,228 |
| 0012 | Signs (604003) | SF | 482 | $6.00 | $4.50 | $6.00 | $6.00 | $5.00 |
| 0013 | Vertical panels (604083) | EACH | 105 | $105.00 | $20.00 | $28.00 | $28.00 | $33.00 |
| 0014 | Lime (620001) | TON | 26 | $26.00 | $1.00 | $100.00 | $100.00 | $100.00 |
| 0015 | Seeding (620011) | ACRE | 13.18 | $1,000.00 | $5.00 | $500.00 | $1,350.00 | $1,350.00 |
| 0016 | Mulch cover (620022) | ACRE | 13.18 | $1,000.00 | $5.00 | $700.00 | $1,050.00 | $1,050.00 |
| 0017 | Water (620030) | MGAL | 1,344.40 | $10.00 | $5.00 | $10.00 | $5.00 | $5.00 |
| 0018 | Silt fence (621021) | LF | 57,404 | $1.75 | $0.05 | $1.00 | $2.90 | $2.90 |
| 0019 | Mailboxes (637001) | EACH | 17 | $85.00 | $50.00 | $85.00 | $85.00 | $50.00 |
| 0020 | Mailbox supports (single) (637017) | EACH | 9 | $165.00 | $125.00 | $165.00 | $165.00 | $130.00 |
| 0021 | Mailbox supports (double) (637018) | EACH | 4 | $195.00 | $125.00 | $195.00 | $195.00 | $150.00 |
| 0022 | Thermoplastic pavement marking white (6") (719002) | LF | 57,202 | $0.66 | $0.64 | $0.67 | $0.67 | $0.68 |
| 0023 | Thermoplastic pavement marking yellow (6") (719102) | LF | 27,547 | $0.62 | $0.64 | $0.63 | $0.63 | $0.68 |
| 0024 | Raised pavement markers (type II) (721002) | EACH | 360 | $4.75 | $5.00 | $4.75 | $4.75 | $4.50 |
| 0025 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $95,000 | $86,926 | $63,879 | $120,000 | $46,824 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.