ARDOT contract A60055 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 14.749 MILES OF HIGHWAY 13 IN LONOKE AND PRAIRIE COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL ITEMS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Lonoke, Prairie. 5 bids received; low bid $4,878,489 by Redstone Construction Group, Inc..

Owner
Arkansas DOT
Letting
05 NOV 2025
Pay items
29
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Redstone Construction Group, Inc.$4,878,489Low
2CK Asphalt, LLC$5,256,294+8.0%
3Rogers Group, Inc.$5,298,736+9.0%
4Cranford Construction Co.$5,826,491+19%
5Delta Asphalt of Arkansas, Inc.$5,916,559+21%
ARDOT contract A60055: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Redstone Construction Group, Inc.2. CK Asphalt, LLC3. Rogers Group, Inc.4. Cranford Construction Co.5. Delta Asphalt of Arkansas, Inc.
0001Removal and disposal of approach gutters (202052)EACH4$2,089.08$900.00$3,052.00$2,000.00$2,000.00
0002Removal and disposal of guardrail (202132)LF550$8.00$6.50$7.65$8.00$8.00
0003Trenching and shoulder preparation (215011)STA779$71.80$105.00$55.00$32.45$61.01
0004Aggregate base course (class 7) (303117)TON3,890$36.33$39.50$45.00$40.31$36.69
0005Tack coat (401011)GAL76,418$0.01$1.00$1.00$0.01$2.71
0006Mineral aggregate in achm binder course (1") (406161)TON7,295$82.87$21.00$68.00$75.56$63.25
0007Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412)TON312$120.00$1,400.00$560.00$750.00$900.00
0008Mineral aggregate in achm surface course (3/8") (407161)TON35,619$88.00$22.00$59.00$106.82$100.14
0009Asphalt binder (PG 70-22) in achm surface course (3/8") (minimum bid $120.00) (407441)TON2,314$120.00$1,200.00$640.00$120.00$120.00
0010Cold milling asphalt pavement (412002)SY1,222$8.03$9.56$5.45$9.75$12.25
0011Achm patching of existing roadway (415011)TON750$175.04$155.00$185.00$256.51$180.36
0012Approach gutters (504264)CY45.56$1,664.20$1,700.00$1,221.00$1,700.00$1,700.00
0013Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$35,025$182,500$100,000$43,762$250,000
0014Maintenance of traffic (603009)LS1$53,245$44,000$100,000$123,155$88,000
0015Signs (604003)SF788$5.25$5.25$7.35$7.00$5.25
0016Construction pavement markings (604041)LF312,088$0.15$0.12$0.16$0.15$0.12
0017Removal of construction pavement markings (604055)LF350$1.00$2.95$1.07$1.00$2.95
0018Guardrail (type A) (617005)LF450$30.00$30.00$31.00$30.00$30.00
0019Terminal anchor posts (type 1) (617105)EACH2$1,700.00$1,700.00$1,790.00$1,700.00$1,700.00
0020Guardrail terminal (type 2) (617312)EACH2$3,000.00$3,000.00$3,170.00$3,000.00$3,000.00
0021Thrie beam guardrail terminal (617332)EACH4$2,000.00$2,000.00$2,035.00$2,000.00$2,000.00
0022Silt fence (621021)LF800$3.50$3.50$3.60$3.50$3.50
0023Filter sock (12") (621168)LF800$7.79$7.76$7.90$7.76$7.76
0024Wattle (20") (621173)LF800$12.92$12.92$13.15$12.92$12.92
0025Roadway construction control (635001)LS1$9,686.69$24,000$11,000$12,850$27,819
0026Thermoplastic pavement marking white (6") (719002)LF156,044$0.64$1.04$0.70$0.64$1.04
0027Thermoplastic pavement marking yellow (6") (719102)LF156,044$0.54$0.36$0.59$0.54$0.36
0028Raised pavement markers (type II) (721002)EACH975$4.00$4.25$4.40$4.00$4.25
0029Reinforcing steel-roadway (grade 60) (804003)LB4,424$2.06$3.50$2.10$2.50$2.50
ARDOT contract A60055: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy