ARDOT contract A80045 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 10.267 MILES OF HIGHWAYS 109 AND 393 IN LOGAN COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, EARTHWORK, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE AND SURFACE COURSES, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPS AND STRIPES, MODIFICATION OF EXISTING BRIDGE STRUCTURE, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Logan. 3 bids received; low bid $5,260,281 by Blackstone Construction, LLC.
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 48
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blackstone Construction, LLC | $5,260,281 | Low |
| 2 | Emery Sapp & Sons, Inc. | $5,903,961 | +12% |
| 3 | Forsgren, Inc. | $5,949,104 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blackstone Construction, LLC | 2. Emery Sapp & Sons, Inc. | 3. Forsgren, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of approach gutters (202052) | EACH | 4 | $3,300.00 | $3,761.28 | $3,425.00 |
| 0002 | Removal and disposal of guardrail (202132) | LF | 1,080 | $10.00 | $11.53 | $10.50 |
| 0003 | Unclassified excavation (210213) | CY | 104 | $75.00 | $48.42 | $40.00 |
| 0004 | Compacted embankment (210611) | CY | 509 | $70.00 | $99.15 | $27.00 |
| 0005 | Trenching and shoulder preparation (215011) | STA | 286 | $250.00 | $210.72 | $275.00 |
| 0006 | Aggregate base course (class 7) (303117) | TON | 1,148 | $45.00 | $48.33 | $40.00 |
| 0007 | Aggregate surface course (class D-8) (303308) | TON | 3,231 | $33.50 | $27.84 | $29.50 |
| 0008 | Tack coat (401011) | GAL | 37,655 | $3.50 | $0.01 | $3.00 |
| 0009 | Mineral aggregate in achm binder course (1") (406161) | TON | 2,834 | $23.02 | $118.62 | $116.50 |
| 0010 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 134 | $2,000.00 | $120.00 | $120.00 |
| 0011 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 32,117 | $102.63 | $121.03 | $119.70 |
| 0012 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 46 | $120.00 | $120.00 | $120.00 |
| 0013 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 2,150 | $120.00 | $120.00 | $120.00 |
| 0014 | Cold milling asphalt pavement (412002) | SY | 5,016 | $6.00 | $4.21 | $5.05 |
| 0015 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 50 | $10.00 | $159.75 | $210.00 |
| 0016 | Achm patching of existing roadway (415011) | TON | 500 | $225.73 | $173.21 | $190.00 |
| 0017 | Approach gutters (504264) | CY | 73.36 | $2,150.00 | $3,038.37 | $2,767.00 |
| 0018 | Maintenance of traffic (603009) | LS | 1 | $15,000 | $45,142 | $110,000 |
| 0019 | Signs (604003) | SF | 1,470 | $5.00 | $5.76 | $5.25 |
| 0020 | Traffic drums (604023) | EACH | 18 | $25.00 | $28.82 | $26.25 |
| 0021 | Construction pavement markings (604041) | LF | 202,476 | $0.20 | $0.23 | $0.21 |
| 0022 | Removal of permanent pavement markings (604061) | LF | 1,736 | $0.50 | $0.58 | $0.53 |
| 0023 | Vertical panels (604083) | EACH | 132 | $30.00 | $34.59 | $31.50 |
| 0024 | Pavement repair over culverts (concrete) (615020) | CY | 36.60 | $887.00 | $922.44 | $840.00 |
| 0025 | Guardrail (type A) (617005) | LF | 2,250 | $38.75 | $44.67 | $40.70 |
| 0026 | Guardrail terminal (type 2) (617312) | EACH | 12 | $3,500.00 | $4,035.02 | $3,675.00 |
| 0027 | Thrie beam guardrail terminal (617332) | EACH | 12 | $2,400.00 | $2,766.86 | $2,520.00 |
| 0028 | Lime (620001) | TON | 2 | $85.00 | $97.99 | $89.00 |
| 0029 | Seeding (620011) | ACRE | 1.02 | $1,329.64 | $1,532.89 | $1,396.00 |
| 0030 | Mulch cover (620022) | ACRE | 2.04 | $1,164.23 | $1,342.20 | $1,222.00 |
| 0031 | Water (620030) | MGAL | 124.80 | $10.00 | $11.53 | $10.50 |
| 0032 | Temporary seeding (621001) | ACRE | 1.02 | $987.47 | $1,138.43 | $1,036.00 |
| 0033 | Sand bag ditch checks (621031) | BAG | 1,250 | $10.86 | $12.52 | $11.40 |
| 0034 | Filter sock (18") (621169) | LF | 2,400 | $11.29 | $13.02 | $11.85 |
| 0035 | Roadway construction control (635011) | LS | 1 | $12,500 | $12,820 | $42,900 |
| 0036 | Mailboxes (637001) | EACH | 28 | $30.00 | $34.59 | $31.50 |
| 0037 | Mailbox supports (single) (637017) | EACH | 28 | $150.00 | $172.93 | $157.50 |
| 0038 | Rumble strips in asphalt shoulders (642001) | LF | 16,231 | $0.25 | $0.13 | $0.12 |
| 0039 | Rumble stripes in asphalt shoulders (642011) | LF | 56,644 | $0.25 | $0.13 | $0.14 |
| 0040 | Centerline rumble stripes in asphalt roadways (642102) | LF | 21,558 | $0.25 | $0.13 | $0.18 |
| 0041 | Portable traffic signal system - actuated (701603) | WEEK | 8 | $2,000.00 | $979.93 | $2,285.00 |
| 0042 | Thermoplastic pavement marking white (6") (719002) | LF | 111,366 | $0.56 | $0.65 | $0.59 |
| 0043 | Thermoplastic pavement marking white (12") (719005) | LF | 55 | $10.00 | $11.53 | $10.50 |
| 0044 | Thermoplastic pavement marking yellow (6") (719102) | LF | 101,238 | $0.55 | $0.63 | $0.58 |
| 0045 | Raised pavement markers (type II) (721002) | EACH | 682 | $7.00 | $8.07 | $7.35 |
| 0046 | Reinforcing steel-roadway (grade 60) (804003) | LB | 7,376 | $2.75 | $3.46 | $3.15 |
| 0047 | Modification of existing bridge structure (bridge no.______) (821001) | LS | 1 | $5,000.00 | $5,764.31 | $5,250.00 |
| 0048 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $124,344 | $184,895 | $135,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.