ARDOT contract A90038 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 15.538 MILES OF HIGHWAY 14 IN SEARCY COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, EARTHWORK, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE STRUCTURES, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on March 4, 2026, Searcy. 2 bids received; low bid $4,398,367 by Apac-Central, Inc..

Owner
Arkansas DOT
Letting
04 MAR 2026
Pay items
61
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Apac-Central, Inc.$4,398,367Low
2Atlas Asphalt, Inc.$4,620,481+5.0%
ARDOT contract A90038: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Apac-Central, Inc.2. Atlas Asphalt, Inc.
0001Removal and disposal of pipe culverts (202049)LF295$62.85$23.76
0002Removal and disposal of box culverts (202097)EACH1$1,835.00$6,021.04
0003Removal and disposal of headwalls (202099)EACH10$413.62$1,193.44
0004Removal and disposal of guardrail (202132)LF1,552$2.93$10.66
0005Unclassified excavation (210213)CY15$48.39$413.78
0006Compacted embankment (210611)CY270$34.59$76.71
0007Trenching and shoulder preparation (215011)STA417$46.42$46.43
0008Aggregate base course (class 7) (303117)TON2,505$24.92$33.64
0009Tack coat (401011)GAL50,130$0.01$0.01
0010Mineral aggregate in achm binder course (1") (406161)TON5,846$79.00$70.76
0011Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402)TON269$120.00$120.00
0012Mineral aggregate in achm surface course (1/2") (407162)TON32,124$83.50$83.90
0013Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON2,051$120.00$120.00
0014Cold milling asphalt pavement (412002)SY4,601$5.28$3.25
0015Achm patching of existing roadway (415011)TON300$107.44$100.00
0016Approach gutters (504264)CY10.60$699.47$3,739.44
0017Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$86,000$214,000
0018Maintenance of traffic (603009)LS1$35,000$208,255
0019Signs (604003)SF1,224$5.04$5.00
0020Traffic drums (604023)EACH55$25.20$25.00
0021Construction pavement markings (604041)LF413,435$0.14$0.14
0022Removal of permanent pavement markings (604061)LF3,570$1.01$1.00
002324" reinforced concrete pipe culverts (class IV) (605608)LF55$108.92$216.36
002424" reinforced concrete pipe culverts (class V) (605609)LF200$127.07$177.14
002536" reinforced concrete pipe culverts (class V) (605619)LF40$318.96$351.42
002648" reinforced concrete pipe culverts (class V) (605629)LF40$443.33$418.67
002718" flared end sections for reinforced concrete pipe culverts (605856)EACH3$2,230.06$2,286.89
002824" flared end sections for reinforced concrete pipe culverts (605858)EACH18$2,057.29$2,844.44
002930" flared end sections for reinforced concrete pipe culverts (605860)EACH1$5,553.50$3,466.47
003036" flared end sections for reinforced concrete pipe culverts (605862)EACH2$3,786.50$4,766.19
003148" flared end sections for reinforced concrete pipe culverts (605866)EACH2$3,695.77$7,076.32
0032Selected pipe bedding (606994)CY30$34.10$13.85
0033Selected pipe backfill (606996)CY60$34.10$13.85
0034Pavement repair over culverts (asphalt) (615022)TON108$113.83$357.32
0035Guardrail (type A) (617005)LF1,350$35.59$35.59
0036Guardrail terminal (type 2) (617312)EACH8$3,379.98$3,379.98
0037Lime (620001)TON10$95.00$10.00
0038Seeding (620011)ACRE4.90$1,126.67$130.00
0039Mulch cover (620022)ACRE9.80$898.64$80.00
0040Water (620030)MGAL603.10$10.00$10.00
0041Temporary seeding (621001)ACRE4.90$836.49$10.00
0042Silt fence (621021)LF9,714$3.28$0.10
0043Sand bag ditch checks (621031)BAG1,386$9.96$9.96
0044Rock ditch checks (621151)CY189$73.48$76.88
0045Filter sock (18") (621169)LF15,943$10.38$0.20
0046Wattle (20") (621173)LF1,000$13.21$0.40
0047Triangular silt dike (621181)LF210$15.89$1.50
0048Solid sodding (624001)SY264$6.39$6.39
0049Roadway construction control (635011)LS1$15,000$57,266
0050Mailboxes (637001)EACH35$40.33$40.00
0051Mailbox supports (single) (637017)EACH31$201.63$200.00
0052Mailbox supports (double) (637018)EACH2$252.04$250.00
0053Rumble stripes in asphalt shoulders (642011)LF65,629$0.17$0.19
0054Centerline rumble stripes in asphalt roadways (642102)LF82,036$0.17$0.19
0055Portable traffic signal system - actuated (701603)WEEK4$882.12$1,536.86
0056Reflectorized paint pavement marking white (6") (718002)LF164,704$0.16$0.16
0057Reflectorized paint pavement marking white (12") (718005)LF392$5.04$5.00
0058Reflectorized paint pavement marking yellow (6") (718102)LF164,704$0.16$0.16
0059Reflectorized paint pavement marking (yield line) (718206)LF22$15.12$15.00
0060Raised pavement markers (type II) (721002)EACH1,050$6.55$6.50
0061Reinforcing steel-roadway (grade 60) (804003)LB792$1.81$3.42
ARDOT contract A90038: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of March 4, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy