CDOT contract C26678 bid tabulation

SH 141 MP 85.5 K-01-B BRIDGE REPAIR. Let by Colorado DOT on February 28, 2025, Region 5. 4 bids received; low bid $2,088,197 by Myers & Sons Construction, LLC, -12% against the engineer's estimate of $2,375,002.

Owner
Colorado DOT
Letting
28 FEB 2025
Pay items
78
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Myers & Sons Construction, LLC$2,088,197Low-12%
2Meridian Engineering Co. dba Meridian Contracting, Inc.$2,674,268+28%+13%
3HANK WILLIAMS, INC. dba WILLIAMS CONSTRUCTION CONTRACTORS$2,756,520+32%+16%
4Structures, Inc.$2,790,262+34%+17%
CDOT contract C26678: bids by rank

Engineer's estimate: $2,375,002.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Myers & Sons Construction, LLC2. Meridian Engineering Co. dba Meridian Contracting, Inc.3. HANK WILLIAMS, INC. dba WILLIAMS CONSTRUCTION CONTRACTORS4. Structures, Inc.
1Clearing and grubbing (201-00000)LS1$20,000$17,500$20,000$81,753$24,902
2Removal of asphalt mat (planing) (202-00240)SY430$50.00$20.00$24.00$21.84$25.50
3Removal of asphalt mat (planing) (special) (202-00246)SY275$46.00$10.00$29.00$28.63$53.95
4Removal of portions of present structure (class 2) (202-00453)SY14$380.00$200.00$700.00$673.24$981.31
5Removal of portions of present structure (class 3) (202-00460)SY3$2,500.00$350.00$1,800.00$2,162.09$3,123.60
6Removal of portions of present structure (202-00502)CY1$7,000.00$5,000.00$3,800.00$3,712.85$3,536.49
7Hydraulic excavator (203-01565)HR15$230.00$200.00$120.00$186.74$296.60
8Combination loader (203-01594)HR15$230.00$120.00$90.00$138.26$259.23
9Potholing (203-01597)HR16$350.00$375.00$325.00$374.32$456.00
10Laborer (203-02330)HR15$65.00$45.00$45.00$70.86$77.60
11Structure excavation (206-00000)CY2,658$35.00$50.00$20.00$75.75$63.29
12Structure backfill (flow-fill) (206-00065)CY22$680.00$750.00$1,100.00$2,459.56$1,147.87
13Structure backfill (class 2) (206-00200)CY597$100.00$35.00$19.00$108.43$19.47
14Stockpile topsoil (207-00210)CY161$30.00$15.00$12.00$21.78$14.43
15Stockpile wetland topsoil (207-00310)CY8$30.00$50.00$50.00$219.17$28.87
16Topsoil (onsite) (207-00700)CY161$50.00$15.00$25.00$21.78$21.65
17Topsoil (wetland) (207-00703)CY8$500.00$50.00$50.00$219.17$43.30
18Erosion log type 1 (12 inch) (208-00002)LF570$10.00$6.50$16.00$9.45$12.71
19Silt fence (reinforced) (208-00021)LF205$5.00$6.50$12.00$8.39$13.45
20Pre-fabricated vehicle tracking pad (208-00075)EACH1$5,000.00$25,000$4,000.00$4,263.41$10,109
21Removal and disposal of sediment (labor) (208-00103)HR20$150.00$45.00$130.00$124.15$54.04
22Removal and disposal of sediment (equipment) (208-00105)HR20$150.00$100.00$100.00$230.56$110.09
23Pre-fabricated concrete washout structure (type 2) (208-00146)EACH2$100.00$5,000.00$2,300.00$2,116.44$2,684.93
24Water control (208-00400)LS1$75,000$98,000$350,000$67,163$94,722
25Reset fence (210-01000)LF100$50.00$35.00$15.00$50.81$27.16
26Relay riprap (210-02900)CY385$100.00$200.00$61.00$65.69$131.21
27Biotic soil amendments (hydraulically applied) (212-00702)LB1,050$10.00$2.00$3.00$2.37$2.35
28Mycorrhizae (212-00704)LB18$10.00$45.00$80.00$53.03$60.12
29Seeding (native) hydraulic (212-00707)ACRE0.30$2,500.00$5,000.00$7,000.00$4,900.90$5,556.00
30Seeding (wetland) hydraulic (212-00710)ACRE0.02$2,500.00$9,000.00$30,000$21,109$17,948
31Mulching (weed free) (213-00003)ACRE0.32$500.00$4,150.00$7,500.00$5,489.08$5,649.83
32Mulch tackifier (213-00061)LB63$3.00$15.00$25.00$19.72$19.97
33Live willow stakes (214-01013)EACH73$25.00$22.00$39.00$31.47$28.82
34Wildlife biologist (240-00000)HR20$250.00$273.00$300.00$344.87$290.75
35Removal of nests (240-00010)HR10$250.00$273.00$300.00$411.13$197.18
36Aggregate base course (special) (304-09000)CY4$250.00$50.00$900.00$1,161.73$191.58
37Hot mix asphalt (patching) (asphalt) (403-00720)TON88$400.00$537.50$800.00$520.17$609.71
38Joint sealant (408-01100)LF96$50.00$100.00$90.00$84.87$26.63
39Geotextile (erosion control) (class 1) (420-00102)SY1,125$5.00$15.00$4.00$24.53$6.57
40Micropile (10 inch) (503-01100)LF305$800.00$550.00$760.00$658.34$1,123.57
41Verification test pile (503-02000)EACH1$15,000$15,000$15,000$13,590$13,404
42Soil nail (504-06406)LF3,785$65.00$65.00$90.00$69.54$144.09
43Verification testing (504-06410)EACH2$4,500.00$10,000$11,000$11,700$10,053
44Riprap (24 inch) (506-00226)TON1,628$166.16$140.00$75.00$104.61$125.73
45Waterproofing (membrane) (515-00120)SY275$35.00$45.00$53.00$143.02$35.72
46Concrete sealer (515-00400)SY175$23.00$25.00$10.00$145.53$28.78
47Sawing and sealing bridge joint (518-03000)LF48$50.00$30.00$50.00$164.83$129.02
48Concrete class D (601-03000)CY53.20$2,000.00$2,100.00$1,150.00$2,463.81$1,875.11
49Concrete class DR (601-03057)CY1.90$3,500.00$3,500.00$8,000.00$4,681.23$4,403.80
50Concrete (patching) (601-06150)SF2$500.00$2,400.00$1,000.00$1,410.47$1,622.08
51Galvanic anodes (601-51005)EACH83$35.00$35.00$80.00$193.64$46.08
52Reinforcing steel (602-00000)LB96$5.00$7.00$2.50$19.80$2.64
53Reinforcing steel (epoxy coated) (602-00020)LB10,739$10.00$5.00$4.00$6.80$2.89
54Subsurface drain outlet (605-84000)LF165$80.00$90.00$30.00$49.17$31.20
55Fence (plastic) (607-11525)LF100$10.00$2.00$7.00$5.26$4.98
56Field office (class 1) (620-00001)EACH1$50,000$22,000$80,000$125,317$34,174
57Sanitary facility (620-00020)EACH1$6,000.00$4,000.00$10,000$1,950.90$5,130.00
58Construction surveying (625-00000)LS1$35,000$25,000$60,000$38,120$39,362
59Mobilization (626-00000)LS1$330,000$207,000$232,061$306,248$252,979
60Public information services (tier IV) (626-01104)LS1$10,000$10,000$10,000$79,752$8,444.59
61Flagging (630-00000)HR600$60.00$33.00$70.00$45.65$56.45
62Traffic control inspection (630-00007)DAY37$500.00$600.00$630.00$731.50$383.98
63Traffic control management (630-00012)DAY80$1,800.00$1,200.00$2,300.00$1,463.01$1,395.15
64Barricade (type 3 M-B) (temporary) (630-80336)EACH2$500.00$397.00$1,000.00$528.15$321.70
65Construction traffic sign (panel size A) (630-80341)EACH28$60.00$82.00$120.00$96.95$61.66
66Construction traffic sign (panel size B) (630-80342)EACH10$70.00$88.00$130.00$104.05$65.68
67Construction traffic sign (special) (630-80344)SF40$30.00$30.00$45.00$35.47$16.08
68Vertical panel (630-80350)EACH15$60.00$44.00$37.00$934.82$64.34
69Portable message sign panel (630-80355)EACH2$10,000$4,000.00$11,000$5,612.85$11,449
70Drum channelizing device (630-80360)EACH10$35.00$50.00$50.00$59.12$73.72
71Drum channelizing device (with light) (flashing) (630-80363)EACH4$100.00$115.00$60.00$136.27$83.11
72Barrier (temporary) (concrete) (630-80370)LF150$200.00$70.00$210.00$211.94$111.60
73Traffic cone (630-80380)EACH30$15.00$13.00$22.00$15.08$44.73
74Portable rumble strips (temporary) (630-80440)EACH6$1,700.00$800.00$1,800.00$1,019.51$2,982.00
75Impact attenuator (temporary) (630-85010)EACH2$10,000$4,000.00$12,000$4,729.46$7,857.06
76Traffic signal (temporary) (630-86810)EACH1$30,000$25,000$55,000$29,559$40,175
77Initial shotcrete facing (641-10010)SF2,059$30.00$46.00$88.00$57.18$79.66
78Shotcrete (class D) (641-11003)CY50.80$1,000.00$1,900.00$2,800.00$2,564.83$2,783.79
CDOT contract C26678: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of February 28, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy