| 0005 | Mobilization (0101-1) | LS | 1 | $100,000 | $125,000 | $135,000 | $100,000 | $150,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $24,000 | $145,000 | $45,000 | $15,000 | $50,000 |
| 0015 | Traffic control officer (0102-14) | HR | 240 | $70.00 | $100.00 | $100.00 | $85.00 | $100.00 |
| 0020 | Work zone sign (0102-60) | ED | 20,040 | $0.25 | $0.35 | $2.85 | $0.29 | $0.50 |
| 0025 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 1,716 | $50.00 | $15.00 | $65.00 | $45.00 | $78.00 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 27,120 | $0.12 | $0.13 | $2.82 | $0.14 | $0.36 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 240 | $8.00 | $8.00 | $45.00 | $6.00 | $11.00 |
| 0040 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 233 | $3.00 | $5.00 | $5.00 | $6.60 | $4.11 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 268 | $11.00 | $5.00 | $40.00 | $12.00 | $19.01 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 30 | $30.00 | $65.00 | $350.00 | $15.00 | $100.00 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 30 | $30.00 | $65.00 | $350.00 | $15.00 | $200.00 |
| 0060 | Type III barricade (0102-115) | ED | 420 | $0.15 | $0.35 | $2.85 | $0.66 | $1.00 |
| 0065 | Portable regulatory, sign (0102-150-1) | ED | 480 | $8.00 | $8.50 | $65.00 | $5.50 | $11.00 |
| 0070 | Radar speed display unit (0102-150-2) | ED | 480 | $8.00 | $8.50 | $65.00 | $5.50 | $11.00 |
| 0075 | Sediment barrier (0104-10-3) | LF | 1,974 | $3.50 | $3.75 | $5.00 | $3.00 | $4.11 |
| 0080 | Inlet protection system (0104-18) | EACH | 3 | $100.00 | $300.00 | $65.00 | $30.00 | $10.00 |
| 0085 | Litter removal (0107-1) | ACRE | 34.27 | $1.00 | $75.00 | $100.00 | $25.00 | $1.00 |
| 0090 | Mowing (0107-2) | ACRE | 32.34 | $1.00 | $75.00 | $100.00 | $25.00 | $1.00 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $20,000 | $26,840 | $20,000 | $300,000 | $35,000 |
| 0100 | Removal of existing concrete (0110-4-10) | SY | 98 | $20.00 | $30.00 | $45.00 | $30.00 | $100.00 |
| 0105 | Regular excavation (0120-1) | CY | 1,233 | $35.00 | $15.00 | $20.00 | $30.00 | $77.00 |
| 0110 | Embankment (0120-6) | CY | 638.40 | $34.00 | $25.00 | $15.00 | $20.00 | $77.00 |
| 0115 | Type B stabilization (0160-4) | SY | 3,343 | $30.00 | $25.00 | $15.00 | $30.00 | $22.61 |
| 0120 | Optional base, base group 11 (0285-711) | SY | 2,557 | $34.00 | $38.00 | $30.00 | $45.00 | $29.61 |
| 0125 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 2,020 | $10.00 | $8.00 | $9.00 | $25.00 | $18.00 |
| 0130 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 663 | $240.00 | $270.00 | $250.00 | $360.00 | $395.00 |
| 0135 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 228.80 | $240.00 | $255.00 | $250.00 | $480.00 | $395.00 |
| 0140 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $9,000.00 | $10,980 | $25,000 | $5,000.00 | $15,000 |
| 0145 | Inlets, ditch bottom, type C, partial (0425-1525) | EACH | 1 | $5,000.00 | $6,100.00 | $25,000 | $4,000.00 | $15,000 |
| 0150 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 4 | $200.00 | $250.00 | $200.00 | $250.00 | $1,000.00 |
| 0155 | Concrete curb & gutter, type E (0520-1-7) | LF | 521 | $100.00 | $36.00 | $45.00 | $30.00 | $77.00 |
| 0160 | Concrete traffic separator, special- variable width (0520-70) | SY | 128 | $100.00 | $150.00 | $175.00 | $90.00 | $377.00 |
| 0165 | Performance turf, sod (0570-1-2) | SY | 1,428 | $3.50 | $4.00 | $10.00 | $4.00 | $6.77 |
| 0170 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.14 | $2,000.00 | $5,000.00 | $4,500.00 | $2,200.00 | $100.00 |
| 0175 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.32 | $2,667.00 | $5,000.00 | $4,500.00 | $2,750.00 | $100.00 |
| 0180 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 713 | $1.70 | $2.00 | $4.00 | $2.20 | $1.00 |
| 0185 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 13 | $1.80 | $10.00 | $4.21 | $3.30 | $1.00 |
| 0190 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 24 | $35.00 | $50.00 | $150.00 | $38.50 | $1.00 |
| 0195 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.43 | $2,000.00 | $5,000.00 | $4,500.00 | $2,200.00 | $100.00 |
| 0200 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 115 | $1.70 | $10.00 | $4.21 | $2.20 | $1.00 |
| 0205 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.04 | $650.00 | $5,000.00 | $4,500.00 | $1,100.00 | $100.00 |
| 0210 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0215 | Fiber optic cable locator (0633-6) | DA | 120 | $35.00 | $150.00 | $150.00 | $25.00 | $50.00 |
| 0220 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 13 | $750.00 | $780.00 | $950.00 | $825.00 | $700.00 |
| 0225 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 1 | $1,500.00 | $1,250.00 | $1,500.00 | $2,750.00 | $2,000.00 |
| 0230 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 4 | $3,500.00 | $1,980.00 | $2,500.00 | $3,300.00 | $2,450.00 |
| 0235 | Single column ground sign assembly, remove (0700-1600) | EACH | 14 | $50.00 | $75.00 | $500.00 | $55.00 | $30.00 |
| 0240 | Multi-column ground sign assembly, F&I ground mount, 50.0 SF (0700-2114) | EACH | 1 | $10,000 | $5,850.00 | $8,500.00 | $12,100 | $7,900.00 |
| 0245 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $300.00 | $500.00 | $1,500.00 | $1,650.00 | $1,200.00 |
| 0250 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 18 | $100.00 | $125.00 | $20.00 | $137.50 | $10.00 |
| 0255 | Tubular marker, 36" yellow (0704-1-4) | EACH | 4 | $150.00 | $175.00 | $200.00 | $275.00 | $200.00 |
| 0260 | Object marker, type 2 (0705-10-2) | EACH | 2 | $120.00 | $250.00 | $200.00 | $165.00 | $100.00 |
| 0265 | Raised pavement marker, type B (0706-1-3) | EACH | 121 | $4.00 | $4.00 | $5.00 | $6.60 | $4.11 |
| 0270 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,351 | $8,500.00 | $5,000.00 | $4,840.00 | $7,000.00 |
| 0275 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 713 | $6.13 | $5.00 | $8.00 | $8.80 | $4.00 |
| 0280 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 13 | $8.18 | $10.00 | $10.00 | $13.20 | $20.00 |
| 0285 | Thermoplastic, standard, arrow (0711-11170) | EACH | 24 | $77.00 | $150.00 | $150.00 | $132.00 | $100.00 |
| 0290 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 115 | $5.45 | $5.00 | $8.00 | $8.80 | $4.00 |
| 0295 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.04 | $2,832.00 | $10,000 | $8,500.00 | $6,600.00 | $5,000.00 |
| 0300 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 0.14 | $8,490.00 | $7,000.00 | $8,500.00 | $8,800.00 | $5,000.00 |
| 0305 | Thermoplastic, standard-open graded asphalt surfaces, solid, 8" (0711-15102) | GM | 0.32 | $11,320 | $9,000.00 | $8,500.00 | $10,450 | $5,000.00 |
| 0310 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 0.43 | $7,496.00 | $7,000.00 | $8,500.00 | $8,800.00 | $5,000.00 |