FDOT contract T2A62 bid tabulation
SR A1A (ATLANTIC AVE) FROM CENTRE ST TO S FLETCHER AVE. Let by Florida DOT on March 25, 2026, Nassau, District 2. 5 bids received; low bid $5,031,116 by Maer Homes, LLC.
- Owner
- Florida DOT
- Letting
- 25 MAR 2026
- Pay items
- 78
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Maer Homes, LLC | $5,031,116 | Low |
| 2 | Anderson Columbia Co., Inc. | $5,687,997 | +13% |
| 3 | Watson Civil Construction, Inc. | $7,442,156 | +48% |
| 4 | Coxwell, J.B. Contracting, Inc. | $8,098,835 | +61% |
| 5 | Hubbard Construction Company | $8,145,275 | +62% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Maer Homes, LLC | 2. Anderson Columbia Co., Inc. | 3. Watson Civil Construction, Inc. | 4. Coxwell, J.B. Contracting, Inc. | 5. Hubbard Construction Company |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization & (0101-1) | LS | 1 | $483,340 | $723,432 | $740,000 | $873,520 | $814,000 |
| 0010 | Maintenance of traffic & (0102-1) | DA | 1 | $75,000 | $410,830 | $986,500 | $1,105,650 | $1,598,000 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $13,000 | $22,761 | $7,400.00 | $8,200.00 | $12,982 |
| 0020 | Pedestrian escort/flagger (0102-5) | HR | 790 | $39.00 | $33.13 | $29.00 | $42.00 | $30.00 |
| 0025 | Work zone sign (0102-60) | ED | 17,300 | $0.50 | $0.22 | $0.30 | $0.26 | $0.19 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 144 | $57.00 | $99.40 | $86.00 | $50.00 | $41.00 |
| 0035 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 84 | $21.00 | $55.22 | $34.00 | $17.00 | $16.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 20,000 | $0.25 | $0.11 | $0.15 | $0.11 | $0.10 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 2,998 | $1.00 | $0.04 | $0.07 | $0.10 | $0.06 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 628 | $16.00 | $13.39 | $14.00 | $12.75 | $12.50 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 600 | $67.00 | $13.84 | $25.00 | $56.00 | $52.64 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 600 | $45.00 | $13.84 | $25.00 | $37.00 | $35.10 |
| 0065 | Type III barricade (0102-115) | ED | 400 | $1.00 | $0.28 | $0.40 | $0.45 | $0.35 |
| 0070 | Inlet protection system (0104-18) | EACH | 40 | $255.00 | $61.37 | $100.00 | $170.00 | $236.48 |
| 0075 | Litter removal (0107-1) | ACRE | 64 | $350.00 | $167.39 | $140.00 | $350.00 | $350.00 |
| 0080 | Mowing (0107-2) | ACRE | 45.21 | $300.00 | $334.78 | $210.00 | $470.00 | $500.00 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $19,100 | $44,178 | $5,000.00 | $3,000.00 | $15,000 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $165,110 | $44,178 | $105,000 | $997,100 | $992,000 |
| 0095 | Removal of existing concrete (0110-4-10) | SY | 1,298 | $20.00 | $97.19 | $35.00 | $51.00 | $45.00 |
| 0100 | Borrow excavation, truck measure (0120-2-2) | CY | 84 | $34.00 | $220.89 | $49.00 | $20.00 | $61.65 |
| 0105 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $21,000 | $77,312 | $16,500 | $8,000.00 | $10,000 |
| 0110 | Optional base, base group 04 (0285-704) | SY | 487 | $47.00 | $83.99 | $50.00 | $41.00 | $105.00 |
| 0115 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 1,192 | $12.00 | $7.20 | $11.20 | $11.20 | $9.95 |
| 0120 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 18,895 | $7.00 | $3.07 | $6.30 | $6.36 | $4.35 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 20,239 | $4.50 | $2.81 | $4.00 | $4.05 | $6.80 |
| 0130 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 1,210 | $8.50 | $7.10 | $8.00 | $8.00 | $9.40 |
| 0135 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 1,947.10 | $210.00 | $193.79 | $177.00 | $181.84 | $222.91 |
| 0140 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 3,426.20 | $255.00 | $194.77 | $224.00 | $231.39 | $239.00 |
| 0145 | Inlets, curb, type P-2, <10' (0425-1321) | EACH | 1 | $19,000 | $20,197 | $8,400.00 | $12,700 | $8,933.19 |
| 0150 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 2 | $14,000 | $12,536 | $7,000.00 | $10,100 | $7,924.79 |
| 0155 | Inlets, curb type J-1, <10' (0425-1411) | EACH | 3 | $18,075 | $17,174 | $11,000 | $14,450 | $11,019 |
| 0160 | Inlets, curb, type J-1, >10' (0425-1412) | EACH | 1 | $28,900 | $33,559 | $23,000 | $20,600 | $39,245 |
| 0165 | Inlets, curb, type J-2, <10' (0425-1421) | EACH | 1 | $19,050 | $22,089 | $12,000 | $15,875 | $10,488 |
| 0170 | Inlets, curb, type J-3, <10' (0425-1431) | EACH | 3 | $19,600 | $18,223 | $12,200 | $15,000 | $18,601 |
| 0175 | Inlets, curb, type J-4, <10' (0425-1441) | EACH | 2 | $19,900 | $24,762 | $13,000 | $15,250 | $15,613 |
| 0180 | Inlets, curb, type J-4, >10' (0425-1442) | EACH | 2 | $20,000 | $35,961 | $19,000 | $23,000 | $37,931 |
| 0185 | Manholes, P-7, <10' (0425-2-41) | EACH | 1 | $13,000 | $13,281 | $5,800.00 | $6,175.00 | $6,077.17 |
| 0190 | Manholes, J-7, <10' (0425-2-71) | EACH | 2 | $15,100 | $19,394 | $11,000 | $10,315 | $10,997 |
| 0195 | Manholes, J-7, >10' (0425-2-72) | EACH | 3 | $23,700 | $31,508 | $21,000 | $16,500 | $34,764 |
| 0200 | Manhole, adjust, utilities (0425-5-1) | EACH | 16 | $2,200.00 | $3,865.58 | $1,700.00 | $1,550.00 | $1,359.61 |
| 0205 | Valve boxes, adjust (0425-6) | EACH | 16 | $1,500.00 | $1,656.67 | $735.00 | $475.00 | $1,307.11 |
| 0210 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 89 | $535.00 | $237.84 | $660.00 | $508.00 | $762.16 |
| 0215 | Pipe culvert,optional material,round, 24"S/CD (0430-175124) | LF | 692 | $320.00 | $281.80 | $745.00 | $302.00 | $400.36 |
| 0220 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 803 | $325.00 | $282.85 | $753.00 | $325.00 | $390.19 |
| 0225 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 2,232 | $352.00 | $583.16 | $854.00 | $860.00 | $521.49 |
| 0230 | Pipe culvert, opt material, shape - elip/arch, 30"S/CD (0430-175230) | LF | 309 | $345.00 | $292.02 | $511.00 | $590.00 | $523.86 |
| 0235 | Concrete curb & gutter, type F (0520-1-10) | LF | 2,910 | $54.00 | $50.80 | $54.00 | $50.00 | $43.14 |
| 0240 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 18 | $77.00 | $77.31 | $77.00 | $70.00 | $101.26 |
| 0245 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 681 | $87.00 | $106.02 | $77.00 | $108.00 | $77.49 |
| 0250 | Detectable warnings (0527-2) | SF | 440 | $41.00 | $55.22 | $42.00 | $41.00 | $38.50 |
| 0255 | Performance turf, sod (0570-1-2) | SY | 5,950 | $7.00 | $2.89 | $5.80 | $7.77 | $7.04 |
| 0260 | Raised pavement marker, type B (0706-1-3) | EACH | 497 | $8.00 | $5.02 | $4.70 | $5.25 | $6.00 |
| 0265 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 4.35 | $2,800.00 | $2,678.22 | $2,475.00 | $2,515.00 | $2,199.49 |
| 0270 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 2,611 | $3.00 | $1.67 | $1.55 | $1.58 | $2.00 |
| 0275 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 363 | $4.00 | $2.23 | $2.10 | $2.10 | $3.00 |
| 0280 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,014 | $6.00 | $3.35 | $3.10 | $3.15 | $4.00 |
| 0285 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.12 | $1,300.00 | $892.74 | $763.00 | $850.00 | $1,008.40 |
| 0290 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 31 | $110.00 | $94.85 | $88.00 | $90.00 | $85.00 |
| 0295 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 28 | $58.00 | $52.45 | $49.00 | $49.50 | $45.00 |
| 0300 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 2.93 | $2,800.00 | $2,678.22 | $2,475.00 | $2,515.00 | $2,203.76 |
| 0305 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $27,925 | $27,925 | $27,925 | $27,925 | $27,925 |
| 0310 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $47,926 | $47,926 | $47,926 | $47,926 | $47,926 |
| 0315 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 14 | $605.00 | $446.37 | $811.00 | $585.00 | $475.00 |
| 0320 | Single column ground sign assembly, relocate (0700-1500) | EACH | 16 | $477.00 | $167.39 | $465.00 | $185.00 | $375.00 |
| 0325 | Single column ground sign assembly, remove (0700-1600) | EACH | 1 | $65.00 | $50.21 | $116.00 | $55.00 | $50.00 |
| 0330 | Raised pavement marker, type B (0706-1-3) | EACH | 497 | $8.00 | $5.58 | $5.20 | $5.25 | $6.00 |
| 0335 | Painted pavement markings, surface (0710-90) | LS | 1 | $32,000 | $13,391 | $11,000 | $12,600 | $25,000 |
| 0340 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,611 | $6.50 | $3.35 | $3.10 | $3.15 | $5.00 |
| 0345 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 176 | $11.50 | $9.48 | $8.80 | $8.93 | $9.00 |
| 0350 | Thermoplastic, standard, arrow (0711-11170) | EACH | 28 | $140.00 | $113.83 | $106.00 | $108.00 | $110.00 |
| 0355 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 363 | $9.00 | $6.42 | $5.95 | $6.04 | $7.00 |
| 0360 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.12 | $5,800.00 | $13,391 | $11,500 | $12,710 | $4,537.82 |
| 0365 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 838 | $26.00 | $15.34 | $14.20 | $14.44 | $20.00 |
| 0370 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 31 | $255.00 | $234.34 | $217.00 | $225.00 | $200.00 |
| 0375 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 31 | $159.00 | $161.81 | $150.00 | $155.00 | $125.00 |
| 0380 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 4.35 | $8,300.00 | $4,463.70 | $4,150.00 | $4,200.00 | $6,498.51 |
| 0385 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 2.93 | $8,300.00 | $4,463.70 | $4,150.00 | $4,200.00 | $6,511.11 |
| 0390 | Loop assembly, F&I, type F (0660-2106) | AS | 13 | $2,715.00 | $1,965.26 | $2,050.00 | $2,250.00 | $2,134.69 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 25, 2026. Compiled by Mirage Metrics.