| 0005 | Mobilization (0101-1) | LS | 1 | $159,000 | $313,500 | $229,970 | $420,760 |
| 0010 | Mobilization (0101-1) | LS | 1 | $15,000 | $17,128 | $62,392 | $80,190 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $152,738 | $247,347 | $156,023 | $344,458 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $12,000 | $17,668 | $64,164 | $61,290 |
| 0025 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $5,400.00 | $5,726.32 | $5,937.52 | $2,500.00 |
| 0030 | Traffic control officer (0102-14) | HR | 32 | $84.00 | $110.35 | $100.00 | $125.00 |
| 0035 | Work zone sign (0102-60) | ED | 19,820 | $0.15 | $0.22 | $0.25 | $0.22 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 54,512 | $0.10 | $0.15 | $0.11 | $0.15 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 719 | $0.10 | $0.06 | $0.08 | $0.06 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 200 | $3.75 | $6.07 | $4.50 | $5.91 |
| 0055 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 2,320 | $4.75 | $5.52 | $5.00 | $5.65 |
| 0060 | Portable changeable message sign, temporary (0102-99) | ED | 428 | $8.50 | $17.11 | $10.50 | $16.70 |
| 0065 | Type III barricade (0102-115) | ED | 600 | $0.40 | $0.55 | $0.32 | $0.55 |
| 0070 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 200 | $20.00 | $51.01 | $20.45 | $65.00 |
| 0075 | Artificial coverings /rolled erosion control products (0104-1) | SY | 13 | $58.00 | $5.52 | $100.96 | $20.00 |
| 0080 | Sediment barrier (0104-10-3) | LF | 9,959 | $1.25 | $1.16 | $2.17 | $1.75 |
| 0085 | Inlet protection system (0104-18) | EACH | 5 | $195.00 | $165.52 | $272.51 | $125.00 |
| 0090 | Litter removal (0107-1) | ACRE | 446.72 | $40.00 | $132.42 | $120.00 | $107.50 |
| 0095 | Mowing (0107-2) | ACRE | 367.76 | $41.00 | $121.39 | $110.00 | $161.25 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $12,000 | $23,980 | $22,748 | $7,500.00 |
| 0105 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $1,200.00 | $15,987 | $5,000.00 | $17,805 |
| 0110 | Removal of existing concrete (0110-4-10) | SY | 154 | $35.00 | $49.66 | $37.50 | $50.80 |
| 0115 | Regular excavation (0120-1) | CY | 390.20 | $20.00 | $30.73 | $53.07 | $15.00 |
| 0120 | Borrow excavation, truck measure (0120-2-2) | CY | 263.30 | $20.00 | $34.01 | $79.30 | $25.00 |
| 0125 | Embankment (0120-6) | CY | 3 | $78.00 | $22.07 | $894.02 | $50.00 |
| 0130 | Optional base, base group 01 (0285-701) | SY | 1,914 | $6.75 | $8.57 | $13.07 | $15.00 |
| 0135 | Optional base, base group 09 (0285-709) | SY | 130 | $35.00 | $114.87 | $67.03 | $90.00 |
| 0140 | Turnout construction- asphalt/driveway base- asphalt material (0286-2) | TN | 291.40 | $125.00 | $244.57 | $205.18 | $195.00 |
| 0145 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 50,031 | $1.00 | $1.86 | $1.57 | $1.70 |
| 0150 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 93 | $2.00 | $20.06 | $24.76 | $2.08 |
| 0155 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 131,453 | $1.00 | $2.60 | $1.50 | $2.67 |
| 0160 | Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12) | SY | 2,576 | $1.50 | $7.20 | $7.73 | $1.89 |
| 0165 | Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15) | SY | 392 | $3.25 | $12.21 | $12.47 | $2.86 |
| 0170 | Milling existing asphalt pavement, 8 1/2" avg depth (0327-70-32) | SY | 130 | $9.50 | $57.38 | $21.50 | $7.08 |
| 0175 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 105.70 | $165.00 | $399.49 | $372.13 | $195.00 |
| 0180 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 10,887.80 | $160.00 | $136.53 | $160.94 | $150.50 |
| 0185 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 15,235.70 | $160.00 | $138.93 | $150.63 | $150.50 |
| 0190 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 32.30 | $940.00 | $1,542.48 | $1,150.00 | $1,532.00 |
| 0195 | Reinforcing steel- roadway (0415-1-1) | LB | 921 | $4.75 | $5.52 | $11.25 | $6.45 |
| 0200 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 230 | $59.00 | $66.21 | $175.00 | $64.50 |
| 0205 | Concrete curb & gutter, type F (0520-1-10) | LF | 43 | $46.00 | $71.73 | $52.50 | $86.00 |
| 0210 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 25 | $94.00 | $69.52 | $47.50 | $66.70 |
| 0215 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,395 | $70.00 | $81.47 | $68.50 | $73.65 |
| 0220 | Detectable warnings (0527-2) | SF | 411 | $35.00 | $49.66 | $35.50 | $40.35 |
| 0225 | Performance turf, sod (0570-1-2) | SY | 38,803 | $2.25 | $2.43 | $2.69 | $2.70 |
| 0230 | Shoulder drop off soil (0570-13-1) | CY | 4,641.40 | $15.00 | $20.07 | $20.55 | $12.50 |
| 0235 | Conduit, furnish & install, open trench (0630-2-11) | LF | 72 | $11.00 | $23.62 | $31.62 | $12.90 |
| 0240 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 2 | $2,500.00 | $3,330.66 | $2,189.31 | $3,140.00 |
| 0245 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 2 | $1,900.00 | $2,872.22 | $2,395.78 | $2,365.00 |
| 0250 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 18.84 | $1,550.00 | $2,482.82 | $2,250.00 | $1,775.00 |
| 0255 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,054 | $1.50 | $3.31 | $3.00 | $2.15 |
| 0260 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 274 | $2.00 | $3.03 | $2.75 | $3.00 |
| 0265 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,120 | $2.25 | $5.52 | $5.00 | $4.05 |
| 0270 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.17 | $1,300.00 | $838.65 | $760.00 | $914.00 |
| 0275 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 9 | $135.00 | $110.35 | $100.00 | $91.40 |
| 0280 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 30 | $43.00 | $60.69 | $55.00 | $49.45 |
| 0285 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 7.81 | $1,500.00 | $2,482.82 | $2,250.00 | $1,775.00 |
| 0290 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 563 | $2.00 | $3.03 | $2.75 | $2.96 |
| 0295 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 7.13 | $1,300.00 | $485.53 | $440.00 | $1,075.00 |
| 0300 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $59,289 | $59,289 | $59,289 | $59,289 |
| 0305 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $2,207.62 | $2,207.62 | $2,207.62 | $2,207.62 |
| 0310 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 24.19 | $1,450.00 | $2,041.43 | $2,205.82 | $3,000.00 |
| 0315 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,500.00 | $2,008.36 | $1,853.18 | $1,925.00 |
| 0320 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 11 | $315.00 | $502.09 | $455.00 | $490.00 |
| 0325 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $660.00 | $2,206.95 | $2,000.00 | $2,150.00 |
| 0330 | Single column ground sign assembly, relocate (0700-1500) | EACH | 3 | $115.00 | $193.10 | $175.00 | $190.00 |
| 0335 | Single column ground sign assembly, remove (0700-1600) | EACH | 5 | $23.00 | $55.18 | $50.00 | $53.75 |
| 0340 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 2 | $98.00 | $165.52 | $150.00 | $161.25 |
| 0345 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $23.00 | $38.63 | $35.00 | $37.65 |
| 0350 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 2 | $58.00 | $49.66 | $45.00 | $50.00 |
| 0355 | Object marker, type 1 (0705-10-1) | EACH | 21 | $70.00 | $275.87 | $250.00 | $269.00 |
| 0360 | Raised pavement marker, type B (0706-1-3) | EACH | 2,320 | $4.75 | $5.52 | $5.00 | $5.65 |
| 0365 | Painted pavement markings, surface (0710-90) | LS | 1 | $58,000 | $76,140 | $69,000 | $69,875 |
| 0370 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 972 | $3.25 | $4.97 | $4.50 | $4.60 |
| 0375 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 274 | $3.75 | $6.62 | $6.00 | $5.40 |
| 0380 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 464 | $5.25 | $10.48 | $9.50 | $6.95 |
| 0385 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.17 | $3,900.00 | $2,979.39 | $2,700.00 | $2,890.00 |
| 0390 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 7 | $135.00 | $148.97 | $135.00 | $139.00 |
| 0395 | Thermoplastic, standard, arrow (0711-11170) | EACH | 28 | $78.00 | $110.35 | $100.00 | $104.00 |
| 0400 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 563 | $3.75 | $6.62 | $6.00 | $5.40 |
| 0405 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 656 | $12.00 | $15.45 | $14.00 | $17.35 |
| 0410 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 2 | $195.00 | $242.77 | $220.00 | $231.15 |
| 0415 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 2 | $98.00 | $220.69 | $200.00 | $116.00 |
| 0420 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 18.84 | $4,850.00 | $4,193.22 | $3,800.00 | $6,125.00 |
| 0425 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 7.81 | $4,600.00 | $4,193.22 | $3,800.00 | $6,125.00 |
| 0430 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 7.13 | $1,950.00 | $1,324.18 | $1,200.00 | $1,735.00 |