FDOT contract T3966 bid tabulation

SR 368 (23RD ST) AND SR 75 (US 231) FROM E OF SR 390 TO... Let by Florida DOT on February 25, 2026, Bay, District 3. 4 bids received; low bid $11,361,185 by Roberts and Roberts, Inc..

Owner
Florida DOT
Letting
25 FEB 2026
Pay items
135
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Roberts and Roberts, Inc.$11,361,185Low
2Anderson Columbia Co., Inc.$11,391,9940.0%
3American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving$12,277,762+8.0%
4C.W. Roberts Contracting, Inc.$12,653,932+11%
FDOT contract T3966: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Roberts and Roberts, Inc.2. Anderson Columbia Co., Inc.3. American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving4. C.W. Roberts Contracting, Inc.
0005Mobilization (0101-1)LS1$480,000$863,059$500,000$340,000
0010Mobilization (0101-1)LS1$320,000$14,299$500,000$550,000
0015Maintenance of traffic (0102-1)DA1$145,000$285,968$425,000$234,500
0020Maintenance of traffic (0102-1)DA1$260,000$50,000$425,000$366,876
0025Pedestrian or bicycle special detour (0102-4-1)SY1$6,300.00$30,639$19,500$6,707.49
0030Pedestrian or bicycle special detour (0102-4-1)SY1$36,000$72,766$19,500$33,572
0035Pedestrian escort/flagger (0102-5)HR300$67.10$50.00$45.00$63.66
0040Traffic control officer (0102-14)HR1,116$71.50$105.00$120.00$73.52
0045Work zone sign (0102-60)ED170,547$0.40$0.10$0.33$0.31
0050Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED379,905$0.20$0.05$0.11$0.10
0055Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD33,201$0.20$0.25$0.11$0.10
0060Arrow board / advance warning arrow panel (0102-76)ED941$5.50$6.00$5.37$5.13
0065Portable changeable message sign, temporary (0102-99)ED4,869$19.30$10.00$18.81$17.95
0070Temporary signalization and maintenance, intersection (0102-104)ED11,543$11.00$5.00$16.13$10.26
0075Temporary traffic detection and maintenance, intersection (0102-107-1)ED11,543$11.00$5.00$17.20$10.26
0080Sediment barrier (0104-10-3)LF5,459$4.10$3.46$5.00$3.97
0085Inlet protection system (0104-18)EACH204$200.00$297.89$450.00$252.14
0090Litter removal (0107-1)ACRE768.14$82.50$25.00$80.00$76.92
0095Mowing (0107-2)ACRE677.22$82.50$25.00$80.00$10.00
0100Clearing & grubbing (0110-1-1)ACRE1$15,000$32,177$25,000$59,115
0105Clearing & grubbing (0110-1-1)ACRE1$30,000$21,601$25,000$345,117
0110Removal of existing concrete (0110-4-10)SY4,102$25.00$47.07$45.00$56.33
0115Regular excavation (0120-1)CY88.80$40.20$57.90$50.00$63.95
0120Embankment (0120-6)CY2.80$163.90$129.16$50.00$99.26
0125Type B stabilization (0160-4)SY150$35.00$35.61$38.00$34.26
0130Optional base, base group 04 (0285-704)SY137$50.00$38.26$150.00$53.61
0135Optional base, base group 11 (0285-711)SY45$160.00$133.72$165.00$131.62
0140Turnout base- optional materials (0286-1)SY176$45.20$31.49$180.00$35.01
0145Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY140,195$2.30$1.00$1.20$1.55
0150Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY25,343$2.30$1.00$2.50$8.33
0155Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY113,026$2.30$1.00$1.25$2.45
0160Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY8,246$2.30$1.00$2.65$5.82
0165Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN7,815.90$137.50$132.05$124.00$149.51
0170Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN2,422.30$137.50$151.53$133.00$177.88
0175Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82)TN8,346.50$137.50$135.35$145.00$153.63
0180Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN1,590.10$137.50$145.04$133.00$239.17
0185Asphalt concrete friction course,traffic C, FC-12.5, high polymer (0337-7-93)TN13,499.80$160.00$196.57$155.00$166.67
0190Manhole, adjust (0425-5)EACH18$1,500.00$1,578.93$2,000.00$1,901.51
0195Manhole, adjust, utilities (0425-5-1)EACH8$1,500.00$1,494.12$2,500.00$1,857.02
0200Valve boxes, adjust (0425-6)EACH27$850.00$1,578.93$1,100.00$1,274.05
0205Concrete curb & gutter, type E (0520-1-7)LF116$85.30$45.97$55.00$115.80
0210Concrete curb & gutter, type F (0520-1-10)LF3,348$64.40$48.21$42.00$63.91
0215Concrete sidewalk and driveways, 4" thick (0522-1)SY1,442$112.80$99.31$95.00$116.66
0220Concrete sidewalk and driveways, 6" thick (0522-2)SY2,591$131.60$115.00$122.00$151.99
0225Detectable warnings (0527-2)SF2,564$26.40$28.60$25.80$24.62
0230Performance turf, sod (0570-1-2)SY9,286$6.00$3.58$6.00$8.41
0235Raised pavement marker, type B (0706-1-3)EACH2,354$7.20$7.75$4.84$6.67
0240Painted pavement markings, standard, white, solid, 6" (0710-11101)GM17.93$1,100.00$1,191.56$1,505.00$1,281.77
0245Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.36$1,100.00$1,191.56$1,720.00$1,025.64
0250Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF10,436$0.90$0.89$2.42$0.77
0255Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF639$1.10$1.19$2.80$1.03
0260Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF3,114$1.70$1.79$3.49$1.54
0265Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM11.05$1,100.00$1,191.56$913.75$1,025.46
0270Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.29$825.00$893.65$1,612.50$758.78
0275Painted pavement markings, standard, white, message or symbol (0710-11160)EACH29$55.00$59.58$53.75$51.28
0280Painted pavement markings, standard, white, arrows (0710-11170)EACH422$22.00$23.83$43.00$20.51
0285Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM14.86$2,145.00$2,323.55$1,612.50$1,998.79
0290Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF1,856$1.10$1.19$2.80$1.03
0295Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM5.91$1,100.00$1,191.56$913.75$1,024.25
0300Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.58$825.00$893.68$1,612.50$766.58
0305Initial contingency amount, DO not bid (0999-25)LS1$48,101$48,101$48,101$48,101
0310Initial contingency amount, DO not bid (0999-25)LS1$84,061$84,061$84,061$84,061
0315Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH10$440.00$476.63$430.00$410.26
0320Single column ground sign assembly, relocate (0700-1500)EACH3$165.00$178.74$161.25$153.85
0325Single column ground sign assembly, remove (0700-1600)EACH3$33.00$35.75$32.25$30.77
0330Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH8$330.00$357.47$322.50$307.69
0335Sign panel, install, UP to 12 SF (0700-3401)EACH2$110.00$119.16$107.50$102.57
0340Sign panel, relocate, UP to 12 SF (0700-3501)EACH1$55.00$59.58$53.75$51.28
0345Sign panel, remove, UP to 12 SF (0700-3601)EACH8$27.50$29.79$26.88$25.64
0350Retroreflective sign strip- of rail road crossbuck sign blades (0700-13-10)EACH2$170.50$184.68$166.63$158.98
0355Enhanced highway sign solar powered, relocate - ground mount (0700-142802)EACH2$1,105.50$1,201.57$1,084.30$1,116.31
0360Tubular marker, 36" white post (0704-1-3)EACH6$187.00$202.56$182.75$174.36
0365Tubular marker, 36" yellow (0704-1-4)EACH2$187.00$202.56$182.75$174.36
0370Raised pavement marker, type B (0706-1-3)EACH6,079$5.00$5.36$4.84$6.67
0375Painted pavement markings, standard, white, island nose (0710-11190)SF35$2.80$2.98$10.75$2.56
0380Painted pavement markings, standard, yellow, island nose (0710-11290)SF16$2.80$2.98$10.75$2.56
0385Painted pavement markings, surface (0710-90)LS1$41,800$45,279$53,750$39,231
0390Painted pavement markings, surface (0710-90)LS1$66,000$71,494$86,000$63,590
0395Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF10,436$3.90$4.17$5.38$4.10
0400Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF643$5.50$5.96$6.45$5.13
0405Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF3,113$6.60$7.15$8.06$6.15
0410Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.29$2,640.00$2,859.75$6,987.50$2,428.06
0415Thermoplastic, standard, message or symbol (0711-11160)EACH29$192.50$208.52$241.88$205.13
0420Thermoplastic, standard, arrow (0711-11170)EACH422$110.00$119.16$96.75$102.56
0425Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF1,856$5.50$5.96$5.38$5.13
0430Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.58$2,640.00$2,859.75$6,987.50$2,453.08
0435Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF6,155$18.70$20.26$12.90$20.51
0440Thermoplastic, preformed, white, message (0711-14160)EACH15$275.00$297.89$161.25$256.41
0445Thermoplastic, preformed, 6" white, railroad dynamic envelope (0711-14191)LF107$3.30$3.58$6.72$4.10
0450Thermoplastic, preformed, 12" white on asphalt pavement, railroad dynamic envelope (0711-14193)LF858$6.60$7.15$9.14$8.21
0455Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM17.93$6,215.00$6,553.59$5,590.00$6,103.24
0460Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.37$6,380.00$6,911.06$8,062.50$6,153.84
0465Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM11.05$2,640.00$2,859.75$2,526.25$2,461.09
0470Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.02$2,640.00$2,859.65$26,875$2,461.50
0475Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM14.86$6,215.00$6,553.59$5,482.50$6,102.97
0480Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM5.91$2,640.00$2,859.75$2,418.75$2,458.21
0485Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF94$3.30$3.58$10.75$3.08
0490Itsfm subsurface documentation- project length (0611-1-1)MI3.47$6,050.00$6,553.59$5,375.00$5,641.03
0495Itsfm location documentation- intersection (0611-2-1)EACH4$4,400.00$4,766.25$4,300.00$4,102.57
0500Conduit, furnish & install, open trench (0630-2-11)LF5,589$11.00$11.92$19.35$10.26
0505Conduit, furnish & install, directional bore (0630-2-12)LF6,827$33.00$35.75$40.85$30.77
0510Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI15$9,900.00$10,724$11,288$9,230.77
0515Signal cable, remove- intersection (0632-7-6)PI15$660.00$714.93$1,075.00$615.38
0520Fiber optic cable locator (0633-6)DA679$88.00$95.33$268.75$82.05
0525Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH147$1,100.00$1,191.56$1,720.00$1,025.64
0530Aluminum signals pole, (0646-1-11)EACH13$3,300.00$3,574.68$3,225.00$3,076.92
0535Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH9$1,100.00$1,191.56$2,042.50$102.56
0540Aluminum signals pole, remove (0646-1-60)EACH8$550.00$595.78$430.00$51.28
0545Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH1$95,600$102,474$103,044$88,205
0550Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3)EACH1$12,100$11,916$6,450.00$10,256
0555Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34)AS20$1,815.00$1,966.08$2,150.00$1,692.31
0560Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36)AS20$2,200.00$2,383.13$2,795.00$2,051.28
0565Vehicular traffic signal, furnish & install 5 section straight, 1 way (0650-1-38)AS2$2,420.00$2,621.44$3,010.00$2,256.41
0570Vehicular traffic signal, remove- poles to remain (0650-1-60)AS20$220.00$238.31$322.50$205.13
0575Vehicular traffic signal, relocate- includes removal reinstallation (0650-1-70)AS20$951.50$1,030.70$1,290.00$887.18
0580Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH45$495.00$536.21$698.75$461.54
0585Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS11$1,210.00$1,310.71$1,720.00$1,128.21
0590Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS2$2,750.00$2,978.91$2,580.00$2,564.11
0595Loop detector inductive, F&I, type 10 (0660-1110)EACH26$550.00$595.78$483.75$512.82
0600Loop assembly- F&I, type A (0660-2101)AS39$1,650.00$1,787.35$1,935.00$1,538.46
0605Loop assembly, F&I, type B (0660-2102)AS125$1,650.00$1,787.35$2,257.50$1,538.46
0610Loop assembly, F&I, type F (0660-2106)AS67$2,200.00$2,383.13$2,365.00$2,051.28
0615Vehicle detection system- furnish & install above ground equipment (0660-4-12)EACH1$9,130.00$9,889.96$8,600.00$8,512.82
0620Vehicle detection system- remove cabinet equipment (0660-4-61)EACH2$1,100.00$1,191.56$483.75$1,025.64
0625Vehicle detection system- remove above ground (0660-4-62)EACH8$660.00$714.93$967.50$615.39
0630Pedestrian detector, furnish & install, standard (0665-1-11)EACH48$550.00$595.78$860.00$512.82
0635Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH33$55.00$119.16$107.50$102.56
0640Traffic controller, modify (0671-2-40)EACH7$3,300.00$3,574.68$2,687.50$3,076.92
0645Traffic controller, relocate- without cabinet (0671-2-50)EACH4$5,500.00$5,957.81$2,150.00$5,128.21
0650Traffic signal controller cabinet, furnish & install without controller, NEMA 44" W X 52" H X 24" D (0676-1116)EACH4$44,000$47,663$36,013$41,026
0655Traffic signal controller cabinet, remove (0676-1600)EACH4$1,100.00$1,191.56$1,720.00$1,025.64
0660Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$660.00$714.93$1,075.00$615.38
0665Sign panel, furnish & install overhead mount, 12-20 SF (0700-3202)EACH1$1,320.00$1,429.87$2,150.00$1,230.77
0670Sign panel, relocate, UP to 12 SF (0700-3501)EACH19$550.00$595.78$215.00$512.82
0675Sign panel, relocate, 12-20 SF (0700-3502)EACH1$660.00$714.93$430.00$615.38
FDOT contract T3966: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy