FDOT contract T3994 bid tabulation
SR 69 FROM S OF NE VAN LEROP RD TO JACKSON CO LINE. Let by Florida DOT on December 3, 2025, Calhoun, District 3. 5 bids received; low bid $2,851,686 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 03 DEC 2025
- Pay items
- 45
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $2,851,686 | Low |
| 2 | Roberts and Roberts, Inc. | $3,178,875 | +11% |
| 3 | C.W. Roberts Contracting, Inc. | $3,535,808 | +24% |
| 4 | American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving | $3,800,274 | +33% |
| 5 | Pigott Asphalt and Sitework LLC | $4,562,173 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Roberts and Roberts, Inc. | 3. C.W. Roberts Contracting, Inc. | 4. American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving | 5. Pigott Asphalt and Sitework LLC |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $202,318 | $135,000 | $150,000 | $250,000 | $349,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $50,000 | $80,000 | $217,500 | $150,000 | $250,000 |
| 0015 | Traffic control officer (0102-14) | HR | 40 | $90.00 | $65.00 | $100.61 | $90.00 | $250.00 |
| 0020 | Work zone sign (0102-60) | ED | 8,400 | $0.05 | $0.40 | $0.34 | $0.28 | $0.25 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 48,736 | $0.01 | $0.20 | $0.11 | $0.17 | $0.01 |
| 0030 | Portable changeable message sign, temporary (0102-99) | ED | 574 | $7.50 | $17.30 | $16.77 | $33.00 | $1.00 |
| 0035 | Type III barricade (0102-115) | ED | 540 | $0.10 | $0.30 | $0.28 | $0.55 | $1.00 |
| 0040 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 280 | $1.17 | $30.00 | $33.54 | $50.00 | $10.00 |
| 0045 | Sediment barrier (0104-10-3) | LF | 234 | $3.50 | $4.70 | $10.79 | $10.00 | $10.00 |
| 0050 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 70 | $23.32 | $20.60 | $12.17 | $20.00 | $30.00 |
| 0055 | Inlet protection system (0104-18) | EACH | 14 | $408.02 | $220.00 | $216.14 | $500.00 | $150.00 |
| 0060 | Litter removal (0107-1) | ACRE | 850.85 | $5.00 | $51.80 | $15.00 | $85.00 | $10.00 |
| 0065 | Mowing (0107-2) | ACRE | 771.21 | $5.00 | $51.80 | $10.00 | $85.00 | $10.00 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $50,000 | $7,000.00 | $70,283 | $60,000 | $25,000 |
| 0075 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 108,001 | $0.74 | $2.70 | $2.65 | $1.50 | $3.00 |
| 0080 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 39,100 | $1.61 | $2.70 | $1.11 | $2.00 | $3.00 |
| 0085 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 2,483 | $3.54 | $2.70 | $4.18 | $3.50 | $3.00 |
| 0090 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 409.40 | $132.72 | $135.00 | $148.73 | $170.00 | $250.00 |
| 0095 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 15,379.30 | $117.26 | $120.00 | $137.78 | $145.00 | $180.00 |
| 0100 | Pipe culvert, optional material, round, 24"SD (0430-174124) | LF | 176 | $98.06 | $118.00 | $115.40 | $300.00 | $150.00 |
| 0105 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 24 | $442.52 | $437.30 | $709.33 | $450.00 | $750.00 |
| 0110 | Straight concrete endwalls, double, 0 degrees, round (0430-548200) | EACH | 1 | $25,729 | $15,987 | $29,904 | $25,000 | $8,500.00 |
| 0115 | Mitered end section, optional round, 24" SD (0430-984129) | EACH | 2 | $2,558.58 | $2,841.50 | $3,143.92 | $3,000.00 | $2,500.00 |
| 0120 | Performance turf, sod (0570-1-2) | SY | 23,018 | $1.15 | $4.30 | $3.07 | $4.75 | $3.50 |
| 0125 | Conduit, furnish & install, open trench (0630-2-11) | LF | 79 | $58.29 | $16.10 | $15.65 | $38.50 | $38.00 |
| 0130 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $1,923.57 | $920.00 | $894.35 | $1,980.00 | $1,900.00 |
| 0135 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 2 | $5,828.98 | $3,588.20 | $3,488.12 | $3,080.00 | $3,000.00 |
| 0140 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 4 | $3,497.39 | $1,035.00 | $1,006.15 | $3,300.00 | $3,200.00 |
| 0145 | Traffic monitoring site cabinet, furnish & install, type 4, base mount (0695-7141) | EACH | 1 | $11,658 | $4,393.90 | $4,271.32 | $8,800.00 | $9,000.00 |
| 0150 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 1 | $932.64 | $345.00 | $335.38 | $770.00 | $1,000.00 |
| 0155 | Raised pavement marker, type B (0706-1-3) | EACH | 1,753 | $6.41 | $6.40 | $6.15 | $5.50 | $4.00 |
| 0160 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 15.55 | $116.58 | $115.00 | $111.79 | $2,200.00 | $1,800.00 |
| 0165 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 7.06 | $1,632.12 | $1,610.00 | $1,563.13 | $2,200.00 | $1,800.00 |
| 0170 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 6.09 | $932.64 | $920.00 | $893.91 | $1,110.00 | $1,000.00 |
| 0175 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0180 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 23.34 | $2,666.50 | $1,600.80 | $2,106.58 | $2,062.25 | $1,500.00 |
| 0185 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 2 | $582.90 | $575.00 | $558.97 | $721.50 | $500.00 |
| 0190 | Raised pavement marker, type B (0706-1-3) | EACH | 1,753 | $6.41 | $6.40 | $6.15 | $5.50 | $5.00 |
| 0195 | Painted pavement markings, surface (0710-90) | LS | 1 | $68,782 | $67,850 | $65,959 | $33,000 | $69,000 |
| 0200 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 15.55 | $5,828.98 | $5,922.50 | $5,589.72 | $5,280.00 | $6,200.00 |
| 0205 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 7.06 | $5,828.98 | $5,922.50 | $5,582.59 | $5,272.50 | $6,200.00 |
| 0210 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 6.09 | $2,797.91 | $2,760.00 | $2,681.74 | $2,667.50 | $5,000.00 |
| 0215 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.17 | $34,974 | $34,500 | $32,767 | $38,500 | $50,000 |
| 0220 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.05 | $34,974 | $34,500 | $29,164 | $38,500 | $50,000 |
| 0225 | Permanent tape, yellow, 10-30 skip, 6" wide, for concrete surfaces (0713-103281) | GM | 0.09 | $5,828.98 | $5,750.00 | $5,140.00 | $16,500 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way