FDOT contract T4747 bid tabulation
SR 5 (S FEDERAL HWY) FROM SR 5 (US1 / N DIXIE HWY) TO 10TH AVE S. Let by Florida DOT on July 29, 2026, Palm Beach, District 4. 6 bids received; low bid $829,378 by R & D Paving LLC.
- Owner
- Florida DOT
- Letting
- 29 JUL 2026
- Pay items
- 67
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R & D Paving LLC | $829,378 | Low |
| 2 | Leon America Construction | $867,011 | +5.0% |
| 3 | Heavy Civil Inc | $900,814 | +9.0% |
| 4 | Aum Construction Inc. | $998,000 | +20% |
| 5 | Traffico LLC | $1,044,444 | +26% |
| 6 | Signal Technology and Installation Corp. | $1,206,381 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R & D Paving LLC | 2. Leon America Construction | 3. Heavy Civil Inc | 4. Aum Construction Inc. | 5. Traffico LLC | 6. Signal Technology and Installation Corp. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $68,000 | $90,000 | $80,000 | $50,000 | $145,879 | $107,975 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $21,000 | $50,000 | $73,000 | $50,000 | $75,000 | $27,497 |
| 0015 | Work zone sign (0102-60) | ED | 3,632 | $0.70 | $0.23 | $0.22 | $0.30 | $1.00 | $0.33 |
| 0020 | Business sign (0102-61) | EACH | 18 | $44.00 | $50.00 | $50.00 | $55.00 | $100.00 | $53.92 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 6,180 | $0.15 | $0.19 | $0.10 | $0.20 | $0.50 | $0.19 |
| 0030 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 12,339 | $0.10 | $0.05 | $0.10 | $0.15 | $0.08 | $0.10 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 110 | $7.45 | $5.57 | $6.50 | $10.00 | $5.00 | $9.10 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 420 | $13.20 | $10.00 | $11.00 | $15.00 | $15.00 | $16.18 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 44 | $10.10 | $15.00 | $9.25 | $25.00 | $20.00 | $13.80 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 44 | $10.10 | $13.70 | $9.25 | $25.00 | $20.00 | $13.80 |
| 0055 | Type III barricade (0102-115) | ED | 432 | $0.80 | $0.38 | $0.30 | $1.00 | $50.00 | $1.02 |
| 0060 | Sediment barrier (0104-10-3) | LF | 1,737 | $6.85 | $3.20 | $2.85 | $2.50 | $5.00 | $3.89 |
| 0065 | Inlet protection system (0104-18) | EACH | 60 | $135.00 | $150.00 | $160.00 | $150.00 | $150.00 | $192.51 |
| 0070 | Litter removal (0107-1) | ACRE | 7.44 | $245.00 | $24.00 | $50.00 | $50.00 | $200.00 | $27.60 |
| 0075 | Removal of existing concrete (0110-4-10) | SY | 451 | $41.90 | $42.00 | $30.00 | $40.00 | $30.00 | $47.18 |
| 0080 | Tree root and branch pruning (0110-22) | EACH | 2 | $2,500.00 | $340.00 | $1,000.00 | $500.00 | $1,000.00 | $827.89 |
| 0085 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 14,027 | $4.15 | $5.00 | $3.80 | $6.75 | $2.85 | $5.40 |
| 0090 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 1,157.20 | $180.35 | $230.00 | $251.00 | $280.00 | $245.00 | $283.04 |
| 0095 | Inlets, adjust (0425-4) | EACH | 1 | $3,300.00 | $5,000.00 | $1,000.00 | $3,423.00 | $1,020.00 | $3,975.99 |
| 0100 | Manhole, adjust (0425-5) | EACH | 32 | $1,045.00 | $750.00 | $900.00 | $1,500.00 | $720.00 | $3,887.63 |
| 0105 | Concrete curb & gutter, type F (0520-1-10) | LF | 444 | $53.35 | $35.00 | $50.00 | $45.00 | $34.80 | $105.13 |
| 0110 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 246 | $97.85 | $72.00 | $80.00 | $100.00 | $90.00 | $132.09 |
| 0115 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 106 | $110.55 | $89.00 | $120.00 | $120.00 | $110.00 | $175.22 |
| 0120 | Detectable warnings (0527-2) | SF | 448 | $46.20 | $30.00 | $39.00 | $40.00 | $40.00 | $51.22 |
| 0125 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0130 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.20 | $2,440.00 | $1,480.00 | $2,250.00 | $3,500.00 | $3,240.00 | $1,361.38 |
| 0135 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 46 | $3.30 | $2.30 | $3.00 | $5.00 | $2.88 | $5.53 |
| 0140 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.48 | $2,440.00 | $1,430.00 | $2,250.00 | $3,000.00 | $3,240.00 | $1,361.28 |
| 0145 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0150 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 21 | $522.50 | $600.00 | $850.00 | $850.00 | $575.00 | $741.29 |
| 0155 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 17 | $1,870.00 | $1,400.00 | $1,600.00 | $2,500.00 | $1,700.00 | $2,965.14 |
| 0160 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $13,200 | $1,860.00 | $3,555.00 | $3,500.00 | $1,900.00 | $4,717.27 |
| 0165 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $275.00 | $500.00 | $351.00 | $500.00 | $750.00 | $741.29 |
| 0170 | Single column ground sign assembly, remove (0700-1600) | EACH | 25 | $192.50 | $80.00 | $25.00 | $25.00 | $250.00 | $26.96 |
| 0175 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 1 | $275.00 | $100.00 | $70.00 | $150.00 | $100.00 | $134.79 |
| 0180 | Raised pavement marker, type B (0706-1-3) | EACH | 288 | $5.70 | $4.50 | $5.00 | $10.00 | $5.76 | $6.74 |
| 0185 | Painted pavement markings, surface (0710-90) | LS | 1 | $12,100 | $9,000.00 | $10,300 | $13,000 | $14,715 | $13,679 |
| 0190 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,298 | $3.60 | $3.30 | $2.80 | $3.50 | $3.90 | $2.84 |
| 0195 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 224 | $6.15 | $6.00 | $5.50 | $7.00 | $7.78 | $5.53 |
| 0200 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 12 | $4.70 | $5.00 | $3.60 | $10.00 | $5.10 | $4.49 |
| 0205 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 80 | $22.00 | $17.00 | $14.50 | $20.00 | $20.70 | $24.27 |
| 0210 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 37 | $275.00 | $300.00 | $280.00 | $375.00 | $402.00 | $1,213.02 |
| 0215 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.58 | $8,250.00 | $560.00 | $5,000.00 | $6,500.00 | $7,130.00 | $6,757.84 |
| 0220 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.01 | $9,350.00 | $8,000.00 | $6,600.00 | $20,000 | $9,500.00 | $9,166.67 |
| 0225 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.68 | $8,250.00 | $5,490.00 | $4,500.00 | $5,700.00 | $6,329.00 | $6,757.84 |
| 0230 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $1,685.00 | $1,400.00 | $1,550.00 | $1,600.00 | $2,000.00 | $1,761.00 |
| 0235 | Conduit, furnish & install, open trench (0630-2-11) | LF | 85 | $15.65 | $25.00 | $14.50 | $30.00 | $28.00 | $34.81 |
| 0240 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 220 | $37.30 | $42.00 | $34.00 | $30.00 | $60.00 | $53.92 |
| 0245 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $9,998.00 | $1,600.00 | $9,100.00 | $10,000 | $12,500 | $9,492.30 |
| 0250 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $1,123.00 | $1,700.00 | $1,100.00 | $500.00 | $2,500.00 | $2,069.72 |
| 0255 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 13 | $1,921.00 | $1,600.00 | $1,750.00 | $1,800.00 | $2,200.00 | $1,760.99 |
| 0260 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $5,988.00 | $9,000.00 | $5,450.00 | $7,500.00 | $5,400.00 | $2,669.37 |
| 0265 | Electrical service wire, & install (0639-2-1) | LF | 100 | $11.15 | $17.00 | $10.50 | $10.00 | $13.00 | $5.71 |
| 0270 | Electrical service wire, (0639-2-6) | LF | 30 | $0.45 | $1.35 | $0.50 | $1.00 | $10.00 | $1.39 |
| 0275 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $2,786.00 | $2,800.00 | $2,550.00 | $2,500.00 | $3,000.00 | $5,703.53 |
| 0280 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $562.00 | $600.00 | $550.00 | $750.00 | $1,500.00 | $827.90 |
| 0285 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,931.94 | $2,800.00 | $3,000.00 | $2,000.00 | $3,000.00 | $3,237.38 |
| 0290 | Prestressed concrete pole, type P-IV (0641-2-14) | EACH | 1 | $13,500 | $27,000 | $12,400 | $20,000 | $15,000 | $12,792 |
| 0295 | Aluminum signals pole, (0646-1-11) | EACH | 4 | $2,743.00 | $2,500.00 | $2,550.00 | $1,800.00 | $3,000.00 | $4,085.96 |
| 0300 | Aluminum signals pole, remove (0646-1-60) | EACH | 4 | $450.00 | $500.00 | $500.00 | $500.00 | $750.00 | $827.89 |
| 0305 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 6 | $685.00 | $690.00 | $630.00 | $750.00 | $1,000.00 | $349.98 |
| 0310 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 4 | $1,163.35 | $1,200.00 | $1,100.00 | $1,800.00 | $2,200.00 | $1,068.68 |
| 0315 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 3 | $702.25 | $500.00 | $650.00 | $650.00 | $1,500.00 | $1,027.83 |
| 0320 | Loop assembly, F&I, type F (0660-2106) | AS | 5 | $2,175.25 | $2,200.00 | $2,000.00 | $2,000.00 | $3,000.00 | $4,717.27 |
| 0325 | Vehicle detection system- remove (0660-4-60) | EACH | 3 | $674.00 | $700.00 | $620.00 | $750.00 | $3,500.00 | $827.89 |
| 0330 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 4 | $460.55 | $500.00 | $450.00 | $350.00 | $700.00 | $502.38 |
| 0335 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $3,088.15 | $3,700.00 | $2,850.00 | $4,000.00 | $5,800.00 | $6,899.02 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.