Heavy Civil Inc: FDOT bid record

Heavy Civil Inc submitted 16 bids on Florida DOT contracts in the data, from 30 JAN 2019 to 29 JUL 2026, and was the low bidder on 6 of them (38%). When it was not low, its total sat a median +8.0% above the low bid.

Owner
Florida DOT
Low bid volume
$4,068,991
Latest bid
29 JUL 2026
Data through
28 OCT 2026
16Bids
6Low bids
38Win rate, percent
+8.0%Median gap to the low bid when not low, 10 bids

By year

YearBidsLow bidsWin rate
20196467%
20205120%
2021200%
202211100%
2026200%
Heavy Civil Inc, FDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 410220%
District 533100%
District 12150%
District 7100%
Heavy Civil Inc, FDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Channelizing device- types I, II, VP, drum, or LCD0102-74-1ED135 (38%)$0.15$0.13
Inlet protection system0104-18EACH125 (42%)$88.00$150.00
Work zone sign0102-60ED134 (31%)$0.25$0.25
Removal of existing concrete0110-4-10SY114 (36%)$13.70$33.96
Thermoplastic, standard, solid, 12" for crosswalk and roundabout0711-11123LF104 (40%)$2.25$3.25
Concrete sidewalk and driveways, 4" thick0522-1SY94 (44%)$39.00$65.00
Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6"0711-11141GM64 (67%)$1,460.00$2,500.00
Traffic control officer0102-14HR54 (80%)$55.00$80.00
Thermoplastic, standard, solid, 24" for stop line and crosswalk0711-11125LF113 (27%)$4.50$6.09
Concrete sidewalk and driveways, 6" thick0522-2SY113 (27%)$51.00$86.00
Single post sign, remove0700-1-60AS93 (33%)$55.00$31.94
Thermoplastic, standard-other surfaces, yellow, solid, 6"0711-16201GM83 (38%)$6,150.00$5,200.00
Heavy Civil Inc, FDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Hardrives of Delray, Inc.43 of 4
Weekley Asphalt Paving, Inc.40 of 4
Blacktip Services Incorporated40 of 4
The Stout Group LLC41 of 4
Roadway Construction, LLC30 of 3
Ohl USA Inc30 of 3
R & D Paving LLC32 of 3
Wrangler Construction Inc.30 of 3
Leon America Construction32 of 3
Ranger Construction Industries, Inc.30 of 3
Heavy Civil Inc, FDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
29 JUL 2026T4747District 4SR 5 (S FEDERAL HWY) FROM SR 5 (US1 / N DIXIE HWY) TO 10TH AVE S3 of 6$900,814+9.0%
10 JUN 2026T4766District 4SR 84 (SE 24TH ST) FROM SW 4TH AVE TO SR 5 (US 1)3 of 8$1,348,260+7.0%
25 MAY 2022T4623District 4TRAFFIC CALMING ENHANCEMENTS1 of 1$928,651Low
26 MAY 2021T4567District 4HOMEWOOD BLVD2 of 6$2,637,000+5.0%
27 JAN 2021T4571District 4GEORGE BUSH BLVD (NE 8TH ST)2 of 10$2,150,000+6.0%
26 AUG 2020T4528District 4SR 5 (US 1)2 of 4$593,560+8.0%
29 JUL 2020T4553District 4NE 5TH AVE5 of 6$580,435+34%
29 APR 2020T7452District 7PLEASANT GROVE ELEMENTARY SIDEWALK4 of 7$620,000+16%
29 JAN 2020T4514District 4POMPANO BEACH MOBILITY SIDEWALKS4 of 6$320,991+15%
29 JAN 2020T5618District 5CLARCONA-OCOEE CONNECTOR TRAIL1 of 4$249,700Low, 2.0% under the second
04 DEC 2019T4532District 4CLINT MOORE RD1 of 5$291,936Low, 8.0% under the second
04 DEC 2019T4533District 4HAMLIN BLVD5 of 7$329,808+10%
04 DEC 2019T5674District 5SR 3261 of 2$1,194,208Low, 1.0% under the second
25 SEP 2019T1766District 1WEST HICKORY ST1 of 6$305,000Low, 10% under the second
31 JUL 2019T5673District 5SR A1A1 of 4$1,099,497Low, 7.0% under the second
30 JAN 2019T1749District 1SR 70 AND POTTER RD2 of 4$351,339+5.0%
Heavy Civil Inc: latest FDOT bids in the data

How this record was read

FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

  • Every bid counted here matched its published total to within one dollar; FDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy