| 0005 | Mobilization (0101-1) | LS | 1 | $1,019,000 | $790,000 | $1,130,345 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $650,000 | $172,500 | $523,475 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $1,500.00 | $34,500 | $22,150 |
| 0020 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $1,500.00 | $9,500.00 | $37,500 |
| 0025 | Work zone sign (0102-60) | ED | 40,992 | $0.20 | $0.27 | $0.20 |
| 0030 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 672 | $0.01 | $43.00 | $43.00 |
| 0035 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 4,176 | $0.01 | $14.50 | $15.00 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 66,125 | $0.10 | $0.12 | $0.10 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 165,929 | $0.06 | $0.09 | $0.05 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 553 | $5.25 | $5.00 | $5.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 1,326 | $9.50 | $12.00 | $9.50 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 2,530 | $42.00 | $18.70 | $41.00 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 2,530 | $12.50 | $47.60 | $12.00 |
| 0070 | Type III barricade (0102-115) | ED | 4,085 | $0.25 | $0.30 | $0.30 |
| 0075 | Removable tape, white, solid 6" (0102-913-21) | GM | 0.43 | $13,020 | $14,300 | $12,757 |
| 0080 | Removable tape, yellow, solid, (0102-913-31) | GM | 2.14 | $13,230 | $14,300 | $12,964 |
| 0085 | Inlet protection system (0104-18) | EACH | 62 | $250.00 | $150.00 | $80.00 |
| 0090 | Litter removal (0107-1) | ACRE | 472.69 | $28.00 | $30.00 | $27.00 |
| 0095 | Mowing (0107-2) | ACRE | 344.79 | $65.00 | $72.00 | $64.00 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $315,350 | $20,000 | $256,875 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 1,613 | $45.00 | $23.45 | $57.40 |
| 0110 | Embankment (0120-6) | CY | 3,716.60 | $0.01 | $19.56 | $41.95 |
| 0115 | Optional base, base group 09 (0285-709) | SY | 734 | $80.00 | $54.50 | $113.50 |
| 0120 | Optional base, base group 11 (0285-711) | SY | 209 | $120.00 | $99.53 | $132.80 |
| 0125 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 69,442 | $2.75 | $3.10 | $2.05 |
| 0130 | Milling existing asphalt pavement, 4 1/2" avg depth (0327-70-3) | SY | 27,144 | $2.75 | $3.65 | $2.95 |
| 0135 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 37,063 | $2.75 | $2.57 | $2.35 |
| 0140 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 27,005 | $3.50 | $1.99 | $14.90 |
| 0145 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 9,548 | $2.75 | $2.99 | $2.45 |
| 0150 | Milling exist asphalt pavement and limerock 10.5" (0327-70108) | SY | 734 | $25.00 | $8.15 | $42.05 |
| 0155 | Milling exist asphalt pavement and limerock 13" (0327-70109) | SY | 209 | $40.00 | $10.99 | $49.60 |
| 0160 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 16,660.40 | $137.50 | $167.90 | $172.15 |
| 0165 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 14,118 | $166.00 | $170.43 | $195.60 |
| 0170 | Manhole, adjust, utilities (0425-5-1) | EACH | 1 | $2,000.00 | $1,540.00 | $1,735.35 |
| 0175 | Valve boxes, adjust (0425-6) | EACH | 1 | $2,000.00 | $350.00 | $830.70 |
| 0180 | Concrete curb & gutter, type E (0520-1-7) | LF | 204 | $65.00 | $46.30 | $47.00 |
| 0185 | Concrete curb & gutter, type F (0520-1-10) | LF | 2,697 | $45.00 | $48.35 | $39.10 |
| 0190 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 57 | $165.00 | $75.29 | $92.35 |
| 0195 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 1,199 | $176.00 | $109.87 | $113.25 |
| 0200 | Detectable warnings (0527-2) | SF | 4,886 | $35.00 | $24.54 | $29.40 |
| 0205 | Performance turf, sod (0570-1-2) | SY | 11,259 | $8.00 | $3.65 | $5.05 |
| 0210 | Conduit, furnish & install, open trench (0630-2-11) | LF | 123 | $18.80 | $20.10 | $16.00 |
| 0215 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 49 | $24.05 | $25.89 | $38.00 |
| 0220 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 3 | $1,590.00 | $1,712.25 | $1,200.00 |
| 0225 | Traffic monitoring site vehicle sensor-non-weight, furnish & install (0695-1-1) | EACH | 6 | $3,030.00 | $3,262.42 | $2,385.00 |
| 0230 | Traffic monitoring site inductive loop assembly, & install, 2 loops (0695-6-12) | EACH | 6 | $2,310.00 | $2,489.47 | $1,865.00 |
| 0235 | Traffic monitoring site cabinet, F&I, type 3, 2 pane back, pedestal mount (0695-7162) | EACH | 2 | $7,450.00 | $8,028.03 | $5,837.00 |
| 0240 | Traffic monitoring site cabinet, remove existing cabinet (0695-7600) | EACH | 1 | $1,235.00 | $1,331.00 | $824.00 |
| 0245 | Raised pavement marker, type B (0706-1-3) | EACH | 2,874 | $4.60 | $4.95 | $4.50 |
| 0250 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 16.01 | $1,635.00 | $1,760.00 | $1,600.70 |
| 0255 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 10,146 | $1.05 | $1.10 | $1.00 |
| 0260 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 142 | $1.80 | $1.93 | $1.75 |
| 0265 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 4,831 | $2.60 | $2.75 | $2.50 |
| 0270 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 1.82 | $765.00 | $825.00 | $749.60 |
| 0275 | Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133) | GM | 0.08 | $1,335.00 | $1,540.00 | $1,493.35 |
| 0280 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 2.58 | $920.00 | $990.00 | $901.05 |
| 0285 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 159 | $56.50 | $60.50 | $55.00 |
| 0290 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 420 | $36.00 | $38.50 | $35.00 |
| 0295 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 10.57 | $1,635.00 | $1,760.00 | $1,600.90 |
| 0300 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 1,080 | $2.10 | $2.20 | $2.00 |
| 0305 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 5.31 | $765.00 | $825.00 | $751.00 |
| 0310 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.33 | $904.50 | $990.00 | $913.85 |
| 0315 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $98,000 | $98,000 | $98,000 |
| 0320 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $91,682 | $91,682 | $91,682 |
| 0325 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 13 | $790.00 | $695.00 | $625.00 |
| 0330 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $1,385.00 | $2,331.00 | $3,100.00 |
| 0335 | Single column ground sign assembly, remove (0700-1600) | EACH | 15 | $250.00 | $75.00 | $15.00 |
| 0340 | Raised pavement marker, type B (0706-1-3) | EACH | 3,523 | $4.60 | $4.95 | $4.50 |
| 0345 | Painted pavement markings, surface (0710-90) | LS | 1 | $91,000 | $81,230 | $89,000 |
| 0350 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 8,091 | $3.10 | $3.30 | $3.00 |
| 0355 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 142 | $4.80 | $5.12 | $4.65 |
| 0360 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,978 | $7.20 | $7.70 | $7.00 |
| 0365 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 2.58 | $2,550.00 | $2,750.00 | $2,502.90 |
| 0370 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 29 | $155.00 | $165.00 | $150.00 |
| 0375 | Thermoplastic, standard, arrow (0711-11170) | EACH | 290 | $105.00 | $110.00 | $100.00 |
| 0380 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 1,080 | $4.80 | $5.12 | $4.65 |
| 0385 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.33 | $2,515.00 | $2,750.00 | $2,538.45 |
| 0390 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 3,128 | $15.50 | $16.50 | $15.00 |
| 0395 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 130 | $204.50 | $220.00 | $200.00 |
| 0400 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 130 | $102.10 | $110.00 | $100.00 |
| 0405 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 11.49 | $5,000.00 | $5,390.00 | $4,902.55 |
| 0410 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.67 | $1,525.00 | $1,650.00 | $1,500.90 |
| 0415 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.23 | $3,065.00 | $1,650.00 | $3,000.00 |
| 0420 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 9.68 | $5,000.00 | $5,390.00 | $4,902.55 |
| 0425 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 5.31 | $1,530.00 | $1,650.00 | $1,502.00 |
| 0430 | Conduit, furnish & install, open trench (0630-2-11) | LF | 3,290 | $14.50 | $16.31 | $14.00 |
| 0435 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 5,177 | $32.00 | $26.94 | $31.00 |
| 0440 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 2 | $6,265.00 | $14,062 | $6,137.00 |
| 0445 | Signal cable, remove- intersection (0632-7-6) | PI | 2 | $805.00 | $2,662.00 | $786.00 |
| 0450 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 97 | $1,225.00 | $1,890.98 | $1,200.00 |
| 0455 | Aluminum signals pole, (0646-1-11) | EACH | 1 | $2,805.00 | $3,923.81 | $2,745.00 |
| 0460 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 1 | $2,805.00 | $2,749.11 | $2,745.00 |
| 0465 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 4 | $1,615.00 | $2,277.80 | $1,581.00 |
| 0470 | Vehicular traffic signal, furnish & install aluminum, 4 section, 1 way (0650-1-16) | AS | 2 | $2,100.00 | $2,756.07 | $2,037.00 |
| 0475 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 4 | $405.00 | $332.75 | $393.00 |
| 0480 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $2,100.00 | $2,700.93 | $2,027.00 |
| 0485 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 12 | $400.00 | $843.64 | $382.00 |
| 0490 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 16 | $430.00 | $843.64 | $420.00 |
| 0495 | Loop assembly, F&I, type B (0660-2102) | AS | 48 | $1,520.00 | $1,920.11 | $1,484.00 |
| 0500 | Loop assembly, F&I, type F (0660-2106) | AS | 42 | $1,785.00 | $2,210.13 | $1,749.00 |
| 0505 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 2 | $515.00 | $553.11 | $1,032.00 |
| 0510 | Traffic controller, modify (0671-2-40) | EACH | 3 | $1,405.00 | $3,260.95 | $1,373.00 |
| 0515 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 10 | $1,405.00 | $3,394.65 | $1,373.00 |
| 0520 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 2 | $1,360.00 | $954.86 | $1,329.00 |
| 0525 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 2 | $1,055.00 | $755.48 | $1,054.00 |
| 0530 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 20" (1050-51220) | LF | 31 | $900.00 | $905.35 | $850.00 |
| 0535 | Utility pipe- ductile iron/cast iron, furnish & install, water/sewer, 30" (1050-51230) | LF | 592 | $900.00 | $954.69 | $729.60 |
| 0540 | Utility fittings, ductile iron, furnish & install elbow, (1055-51130) | EACH | 4 | $7,000.00 | $15,327 | $22,000 |
| 0545 | Utility fittings, ductile iron, furnish & install tee, 30" (1055-51230) | EACH | 1 | $2,500.00 | $18,240 | $28,000 |
| 0550 | Utility fittings, ductile iron, furnish & install cap/plug, 30" (1055-51530) | EACH | 2 | $2,500.00 | $10,590 | $13,000 |
| 0555 | Utility structure, below ground, F&I, water / sewer > 80 FT3, 0 - 6' (1060-11221) | EACH | 1 | $25,000 | $12,890 | $16,000 |
| 0560 | Utility fixture, valve/meter box, furnish & install, 20" (1080-21120) | EACH | 1 | $5,000.00 | $24,792 | $4,250.00 |
| 0565 | Utility fixture, valve/meter box, furnish & install, 30" (1080-21130) | EACH | 1 | $5,000.00 | $94,575 | $4,250.00 |
| 0570 | Utility fixture- tapping saddle/sleeve, furnish & 24" (1080-23124) | EACH | 1 | $7,500.00 | $69,250 | $21,645 |
| 0575 | Utility fixture, valve assembly, furnish and install, 20" (1080-24120) | EACH | 1 | $21,000 | $39,535 | $30,000 |
| 0580 | Utility fixture, valve assembly, furnish and install, 30" (1080-24130) | EACH | 1 | $21,000 | $69,987 | $58,000 |
| 0585 | Utility fixture, vac/air furnish & install 30" (1080-26130) | EACH | 1 | $8,500.00 | $34,832 | $80,000 |