FDOT contract T7604 bid tabulation
MIDDLE SCHOOL SIDEWALKS AT VARIOUS LOCATIONS AS SHOWN IN THE PLANS. Let by Florida DOT on August 26, 2026, Hillsborough, District 7. 9 bids received; low bid $1,554,537 by Leon America Construction.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 70
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Leon America Construction | $1,554,537 | Low |
| 2 | American Design Engineering Construction Inc. | $1,697,037 | +9.0% |
| 3 | Blacktip Services Incorporated | $1,828,516 | +18% |
| 4 | Vector Paving LLC | $1,832,300 | +18% |
| 5 | Central Concrete Products, Inc. | $2,060,660 | +33% |
| 6 | Garcia Civil Contractors | $2,084,208 | +34% |
| 7 | Estep Construction, Inc. | $2,133,048 | +37% |
| 8 | Yoroca Engineering Contractors, LLC | $2,266,798 | +46% |
| 9 | Maer Homes, LLC | $2,352,511 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Leon America Construction | 2. American Design Engineering Construction Inc. | 3. Blacktip Services Incorporated | 4. Vector Paving LLC | 5. Central Concrete Products, Inc. | 6. Garcia Civil Contractors |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $100,000 | $200,000 | $89,000 | $116,568 | $120,000 | $155,521 |
| 0010 | Mobilization (0101-1) | LS | 1 | $100,000 | $150,000 | $89,000 | $138,671 | $80,000 | $103,681 |
| 0015 | Maintenance of traffic (0102-1) | DA | 1 | $80,000 | $15,000 | $15,875 | $61,992 | $101,250 | $73,121 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $80,000 | $15,000 | $15,875 | $70,072 | $87,250 | $38,700 |
| 0025 | Work zone sign (0102-60) | ED | 15,736 | $0.20 | $3.50 | $0.23 | $0.37 | $0.41 | $0.26 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 13,276 | $0.10 | $3.50 | $0.11 | $0.31 | $0.21 | $0.21 |
| 0035 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 360 | $0.06 | $3.50 | $0.90 | $0.25 | $0.20 | $0.14 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 30 | $5.00 | $35.00 | $7.00 | $12.39 | $9.00 | $15.33 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 551 | $10.00 | $40.00 | $12.00 | $24.78 | $14.00 | $16.66 |
| 0050 | Type III barricade (0102-115) | ED | 1,330 | $0.60 | $3.50 | $0.32 | $0.43 | $0.70 | $0.69 |
| 0055 | Sediment barrier (0104-10-3) | LF | 8,795 | $2.50 | $6.00 | $1.25 | $2.81 | $2.30 | $1.77 |
| 0060 | Soil tracking prevention device (0104-15) | EACH | 4 | $4,000.00 | $3,000.00 | $500.00 | $2,687.50 | $3,500.00 | $207.05 |
| 0065 | Inlet protection system (0104-18) | EACH | 14 | $176.00 | $65.00 | $50.00 | $154.80 | $200.00 | $158.16 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $40,000 | $10,000 | $119,000 | $38,177 | $120,000 | $62,019 |
| 0075 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $60,000 | $10,000 | $119,000 | $16,190 | $120,000 | $93,029 |
| 0080 | Removal of existing concrete (0110-4-10) | SY | 433 | $35.00 | $10.00 | $50.00 | $49.17 | $40.00 | $63.11 |
| 0085 | Mailbox, F&I single (0110-7-1) | EACH | 27 | $450.00 | $200.00 | $200.00 | $233.13 | $600.00 | $228.22 |
| 0090 | Tree protection barrier (0110-21) | LF | 807 | $4.60 | $8.00 | $2.00 | $7.00 | $8.00 | $10.46 |
| 0095 | Tree root and branch pruning (0110-22) | EACH | 21 | $650.00 | $80.00 | $100.00 | $1,208.30 | $710.00 | $864.58 |
| 0100 | Tree removal (0110-23) | EACH | 5 | $500.00 | $100.00 | $1,500.00 | $4,064.58 | $2,000.00 | $516.00 |
| 0105 | Regular excavation (0120-1) | CY | 826.30 | $6.00 | $15.00 | $49.00 | $43.59 | $30.00 | $86.10 |
| 0110 | Embankment (0120-6) | CY | 292.10 | $9.00 | $15.00 | $30.00 | $35.71 | $40.00 | $84.47 |
| 0115 | Type B stabilization (0160-4) | SY | 480 | $5.00 | $15.00 | $50.00 | $40.31 | $15.00 | $35.84 |
| 0120 | Optional base, base group 02 (0285-702) | SY | 480 | $22.00 | $15.00 | $50.00 | $81.00 | $76.00 | $41.62 |
| 0125 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 38.70 | $150.00 | $395.00 | $200.00 | $409.53 | $600.00 | $741.78 |
| 0130 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 15.40 | $836.00 | $1,950.00 | $900.00 | $1,201.13 | $1,500.00 | $1,366.88 |
| 0135 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 7 | $6,000.00 | $15,000 | $6,200.00 | $5,127.49 | $6,350.00 | $9,379.90 |
| 0140 | Inlets, DT bot, type C,jbot, <10' (0425-1523) | EACH | 1 | $11,000 | $15,000 | $20,000 | $14,700 | $12,500 | $12,015 |
| 0145 | Inlets, ditch bottom, type C modified- back of sidewalk, <10' (0425-1531) | EACH | 3 | $8,200.00 | $15,000 | $6,000.00 | $5,430.33 | $8,300.00 | $8,795.35 |
| 0150 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 8 | $7,800.00 | $15,000 | $6,900.00 | $5,240.64 | $6,300.00 | $11,287 |
| 0155 | Manholes, P-8, <10' (0425-2-61) | EACH | 2 | $8,200.00 | $15,000 | $8,000.00 | $9,624.26 | $12,000 | $13,942 |
| 0160 | Manholes, J-8, <10' (0425-2-91) | EACH | 1 | $12,000 | $15,000 | $8,800.00 | $8,067.28 | $7,800.00 | $14,137 |
| 0165 | Pipe culvert,optional material,round, 12"S/CD (0430-175112) | LF | 4 | $170.00 | $75.00 | $237.00 | $1,229.13 | $372.00 | $903.47 |
| 0170 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 187 | $210.00 | $40.00 | $237.00 | $172.07 | $111.00 | $177.08 |
| 0175 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 1,198 | $100.00 | $50.00 | $237.00 | $101.88 | $121.00 | $175.99 |
| 0180 | Pipe culvert, opt material, round, 30"S/CD (0430-175130) | LF | 13 | $180.00 | $105.00 | $237.00 | $716.17 | $192.00 | $654.79 |
| 0185 | Pipe culvert,optional material,other-elip/arch, (0430-175215) | LF | 13 | $180.00 | $60.00 | $237.00 | $609.59 | $145.00 | $478.91 |
| 0190 | Pipe culvert,optional material,other-elip/arch, (0430-175218) | LF | 509 | $180.00 | $72.00 | $237.00 | $134.32 | $157.00 | $230.36 |
| 0195 | Mitered end section, optional round, 12" CD (0430-982121) | EACH | 1 | $2,500.00 | $1,500.00 | $500.00 | $2,138.49 | $2,750.00 | $1,696.74 |
| 0200 | Mitered end section, optional round, 15" CD (0430-982123) | EACH | 1 | $2,500.00 | $1,500.00 | $650.00 | $3,407.46 | $2,750.00 | $2,678.95 |
| 0205 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 1 | $2,900.00 | $1,500.00 | $700.00 | $2,321.99 | $2,950.00 | $2,876.96 |
| 0210 | Mitered end section, optional - elliptical / arch, 15" CD (0430-982623) | EACH | 2 | $2,500.00 | $1,500.00 | $650.00 | $2,518.08 | $3,350.00 | $2,099.80 |
| 0215 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 78 | $130.00 | $135.00 | $74.00 | $62.35 | $80.00 | $86.43 |
| 0220 | Concrete curb & gutter, type F (0520-1-10) | LF | 67 | $35.00 | $35.00 | $52.00 | $66.83 | $48.00 | $101.55 |
| 0225 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 5,065 | $60.00 | $75.00 | $70.00 | $91.32 | $99.00 | $79.90 |
| 0230 | Concrete ditch pavement, 4", reinforced (0524-1-29) | SY | 16 | $140.00 | $65.00 | $69.00 | $157.60 | $75.00 | $281.99 |
| 0235 | Pavers, architectural, (0526-1-2) | SY | 27 | $180.00 | $40.00 | $105.00 | $165.00 | $147.00 | $119.44 |
| 0240 | Detectable warnings (0527-2) | SF | 718 | $20.00 | $18.00 | $24.00 | $30.00 | $40.00 | $25.15 |
| 0245 | Performance turf, sod (0570-1-2) | SY | 6,158 | $4.00 | $4.95 | $3.60 | $8.25 | $6.50 | $9.38 |
| 0250 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $40,000 | $40,000 | $40,000 | $40,000 | $40,000 | $40,000 |
| 0255 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 | $10,000 |
| 0260 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 30 | $540.00 | $600.00 | $600.00 | $885.62 | $625.00 | $670.83 |
| 0265 | Single column ground sign assembly, relocate (0700-1500) | EACH | 23 | $350.00 | $300.00 | $300.00 | $590.42 | $450.00 | $287.50 |
| 0270 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 2 | $300.00 | $240.00 | $450.00 | $460.53 | $275.00 | $603.75 |
| 0275 | Enhanced highway sign solar powered, relocate - ground mount (0700-142802) | EACH | 2 | $2,200.00 | $900.00 | $1,500.00 | $3,306.34 | $5,300.00 | $3,162.50 |
| 0280 | Object marker, type 3 (0705-10-3) | EACH | 1 | $280.00 | $65.00 | $75.00 | $295.21 | $382.00 | $230.00 |
| 0285 | Raised pavement marker, type B (0706-1-3) | EACH | 42 | $4.50 | $3.00 | $6.00 | $5.51 | $16.00 | $11.50 |
| 0290 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,000 | $2,000.00 | $2,000.00 | $2,215.42 | $4,000.00 | $5,126.70 |
| 0295 | Painted pavement markings, surface (0710-90) | LS | 1 | $15,000 | $2,000.00 | $2,000.00 | $2,011.52 | $3,500.00 | $2,563.35 |
| 0300 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,583 | $3.50 | $5.00 | $6.00 | $4.41 | $7.00 | $3.60 |
| 0305 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 135 | $7.00 | $6.00 | $12.00 | $7.94 | $11.00 | $7.24 |
| 0310 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $170.00 | $171.00 | $300.00 | $220.44 | $325.00 | $80.50 |
| 0315 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 945 | $16.00 | $7.00 | $17.00 | $14.88 | $27.00 | $18.74 |
| 0320 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.20 | $5,000.00 | $3,500.00 | $8,000.00 | $7,457.66 | $12,500 | $8,582.09 |
| 0325 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.04 | $2,500.00 | $3,500.00 | $3,000.00 | $7,889.47 | $11,500 | $2,421.05 |
| 0330 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 541 | $4.28 | $18.00 | $15.00 | $7.13 | $7.50 | $3.61 |
| 0335 | Conduit, furnish & install, open trench (0630-2-11) | LF | 5 | $16.45 | $20.00 | $35.00 | $62.52 | $200.00 | $115.00 |
| 0340 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 5 | $9.62 | $5.00 | $500.00 | $14.57 | $600.00 | $115.00 |
| 0345 | Aluminum signals pole, (0646-1-40) | EACH | 1 | $1,700.00 | $950.00 | $2,200.00 | $3,725.06 | $3,500.00 | $575.00 |
| 0350 | Midblock crosswalk: rectangular rapid flashing beacon, furnish & install- complete sign assembly- back back (0654-2-22) | AS | 2 | $10,000 | $7,500.00 | $22,000 | $15,343 | $9,000.00 | $12,363 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.