FDOT contract T7605 bid tabulation
SR 45 (US 41 / S FLORIDA AVE) FROM CR 480 TO E TOWER TR. Let by Florida DOT on August 26, 2026, Citrus, District 7. 12 bids received; low bid $894,226 by Leon America Construction.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 49
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Leon America Construction | $894,226 | Low |
| 2 | Concept Construction and Demoli | $1,078,070 | +21% |
| 3 | Hartman Civil Construction Company, Inc. | $1,093,738 | +22% |
| 4 | Yoroca Engineering Contractors, LLC | $1,097,789 | +23% |
| 5 | Garcia Civil Contractors | $1,158,674 | +30% |
| 6 | American Design Engineering Construction Inc. | $1,305,527 | +46% |
| 7 | Environmental Land Development | $1,338,208 | +50% |
| 8 | Maer Homes, LLC | $1,357,857 | +52% |
| 9 | Estep Construction, Inc. | $1,399,539 | +57% |
| 10 | Blacktip Services Incorporated | $1,512,151 | +69% |
| 11 | Vector Paving LLC | $1,555,959 | +74% |
| 12 | Sparks Concrete, LLC | $1,568,435 | +75% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Leon America Construction | 2. Concept Construction and Demoli | 3. Hartman Civil Construction Company, Inc. | 4. Yoroca Engineering Contractors, LLC | 5. Garcia Civil Contractors | 6. American Design Engineering Construction Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $120,000 | $118,110 | $95,000 | $100,000 | $138,486 | $200,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $60,000 | $50,000 | $55,000 | $20,000 | $29,080 | $20,000 |
| 0015 | Work zone sign (0102-60) | ED | 6,812 | $0.20 | $0.27 | $0.50 | $0.19 | $0.36 | $4.00 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 43,230 | $0.10 | $0.11 | $0.20 | $0.11 | $0.19 | $4.00 |
| 0025 | Portable changeable message sign, temporary (0102-99) | ED | 538 | $10.00 | $10.75 | $15.00 | $9.90 | $23.22 | $4.00 |
| 0030 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 524 | $15.00 | $24.50 | $20.00 | $1.00 | $77.40 | $200.00 |
| 0035 | Artificial coverings /rolled erosion control products (0104-1) | SY | 114 | $7.00 | $10.00 | $20.00 | $6.00 | $6.38 | $35.00 |
| 0040 | Sediment barrier (0104-10-3) | LF | 1,624 | $2.50 | $1.00 | $3.00 | $5.00 | $2.11 | $10.00 |
| 0045 | Soil tracking prevention device (0104-15) | EACH | 1 | $4,000.00 | $1,500.00 | $4,500.00 | $4,000.00 | $276.06 | $3,500.00 |
| 0050 | Inlet protection system (0104-18) | EACH | 1 | $176.00 | $100.00 | $500.00 | $2,250.00 | $82.82 | $60.00 |
| 0055 | Chemical treatment- powdered, for erosion control (0104-19) | SY | 114 | $46.00 | $25.00 | $10.00 | $50.00 | $22.49 | $65.00 |
| 0060 | Litter removal (0107-1) | ACRE | 65.67 | $24.00 | $50.00 | $100.00 | $1.00 | $107.53 | $100.00 |
| 0065 | Mowing (0107-2) | ACRE | 44.12 | $30.00 | $50.00 | $100.00 | $1.00 | $187.13 | $50.00 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $80,000 | $200,000 | $78,700 | $40,000 | $95,665 | $35,000 |
| 0075 | Removal of existing concrete (0110-4-10) | SY | 1 | $35.00 | $1,500.00 | $500.00 | $100.00 | $637.10 | $100.00 |
| 0080 | Mailbox, F&I single (0110-7-1) | EACH | 8 | $40.00 | $500.00 | $250.00 | $250.00 | $269.70 | $200.00 |
| 0085 | Tree root and branch pruning (0110-22) | EACH | 1 | $650.00 | $250.00 | $2,500.00 | $1,000.00 | $637.10 | $150.00 |
| 0090 | Regular excavation (0120-1) | CY | 863.60 | $6.00 | $51.00 | $25.00 | $40.00 | $49.88 | $20.00 |
| 0095 | Embankment (0120-6) | CY | 1,617.20 | $9.00 | $50.00 | $30.00 | $40.00 | $56.42 | $20.00 |
| 0100 | Optional base, base group 06 (0285-706) | SY | 318 | $18.00 | $72.25 | $40.00 | $200.00 | $79.17 | $115.00 |
| 0105 | Turnout construction- asphalt/driveway base- asphalt material (0286-2) | TN | 269.60 | $270.00 | $269.60 | $340.00 | $200.00 | $340.61 | $300.00 |
| 0110 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 457 | $10.00 | $31.15 | $40.00 | $15.00 | $19.06 | $35.00 |
| 0115 | Superpave asphaltic conc, traffic B (0334-1-12) | TN | 165 | $150.00 | $293.50 | $400.00 | $220.00 | $333.57 | $320.00 |
| 0120 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $6,700.00 | $5,000.00 | $9,500.00 | $10,000 | $6,288.88 | $25,000 |
| 0125 | Pipe culvert, optional material, round, 15"SD (0430-174115) | LF | 76 | $140.00 | $84.85 | $110.00 | $215.00 | $106.31 | $65.00 |
| 0130 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 313 | $150.00 | $87.85 | $130.00 | $215.00 | $116.97 | $75.00 |
| 0135 | Pipe culvert, optional material, other shape - ellip/arch, 18"SD (0430-174218) | LF | 238 | $180.00 | $132.85 | $160.00 | $215.00 | $122.97 | $85.00 |
| 0140 | Mitered end section, optional round, 15" SD (0430-984123) | EACH | 4 | $2,500.00 | $1,300.00 | $3,000.00 | $2,000.00 | $3,239.53 | $1,500.00 |
| 0145 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 4 | $2,500.00 | $1,400.00 | $3,200.00 | $2,000.00 | $2,512.34 | $1,500.00 |
| 0150 | Mitered end sect, optional - elliptical / arch, 18" SD (0430-984625) | EACH | 12 | $2,500.00 | $1,500.00 | $3,300.00 | $1,500.00 | $2,535.90 | $1,500.00 |
| 0155 | Concrete curb, type A (0520-2-1) | LF | 27 | $25.00 | $75.00 | $50.00 | $50.00 | $81.66 | $35.00 |
| 0160 | Concrete curb, type B (0520-2-2) | LF | 30 | $45.00 | $75.00 | $50.00 | $50.00 | $81.92 | $35.00 |
| 0165 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 2,541 | $60.00 | $45.00 | $72.00 | $100.00 | $50.66 | $65.00 |
| 0170 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 601 | $65.00 | $63.00 | $87.00 | $100.00 | $91.26 | $75.00 |
| 0175 | Concrete ditch pavt, non reinforced, 3" (0524-1-1) | SY | 22 | $70.00 | $100.00 | $150.00 | $100.00 | $139.39 | $85.00 |
| 0180 | Detectable warnings (0527-2) | SF | 289 | $30.00 | $22.00 | $35.00 | $20.00 | $20.00 | $20.00 |
| 0185 | Performance turf, sod (0570-1-2) | SY | 11,421 | $3.00 | $4.00 | $5.00 | $5.00 | $6.42 | $6.00 |
| 0190 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0195 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 11 | $500.00 | $588.00 | $600.00 | $700.00 | $805.00 | $850.00 |
| 0200 | Single column ground sign assembly, relocate (0700-1500) | EACH | 5 | $350.00 | $480.00 | $400.00 | $450.00 | $517.50 | $250.00 |
| 0205 | Single column ground sign assembly, remove (0700-1600) | EACH | 11 | $50.00 | $50.00 | $100.00 | $100.00 | $57.50 | $50.00 |
| 0210 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 3 | $170.00 | $150.00 | $200.00 | $700.00 | $115.00 | $250.00 |
| 0215 | Object marker, type 4 (0705-10-4) | EACH | 6 | $310.00 | $210.00 | $400.00 | $350.00 | $345.00 | $100.00 |
| 0220 | Raised pavement marker, type B (0706-1-3) | EACH | 16 | $4.80 | $5.00 | $12.00 | $5.00 | $16.75 | $3.00 |
| 0225 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,000.00 | $1,850.00 | $2,000.00 | $5,000.00 | $5,750.00 | $3,500.00 |
| 0230 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 631 | $3.80 | $5.10 | $6.00 | $3.00 | $8.05 | $6.00 |
| 0235 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 108 | $7.00 | $9.00 | $11.00 | $5.00 | $13.80 | $8.00 |
| 0240 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 302 | $8.50 | $17.00 | $20.00 | $25.00 | $28.75 | $8.00 |
| 0245 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.09 | $5,000.00 | $6,980.00 | $10,000 | $9,000.00 | $11,500 | $6,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.