IDOT contract 46940 bid tabulation

Section GLP. Let by Illinois DOT on April 25, 2025, Grundy, District 03. 3 bids received; low bid $1,889,874 by D. Construction, Inc..

Owner
Illinois DOT
Letting
25 APR 2025
Pay items
95
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$1,889,874Low
2Austin Tyler Construction, Inc.$1,987,187+5.0%
3P. T. Ferro Construction Co.$2,258,305+19%
IDOT contract 46940: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. Austin Tyler Construction, Inc.3. P. T. Ferro Construction Co.
1Remov EX gate (X0300249)EACH5$914.10$900.00$1,000.00
2Rem EX parking blocks (X0301339)EACH93$50.00$110.00$45.00
3Prec conc park block (X0301430)EACH109$125.00$120.00$120.00
4Tubular steel gate (X0323013)EACH7$18,965$17,250$19,000
5Rem & rel flagpole (X0323256)EACH1$2,500.00$3,000.00$5,000.00
6Traffic counter (X0323388)EACH1$0.01$33,100$40,000
7Rem EX wood bollard (X0324056)EACH7$100.00$200.00$150.00
8Park lot seal CT (X0325800)SY11,259$2.75$1.75$2.00
9Clearing & grubbing (X2010512)SY113$42.90$39.00$50.00
10Furn & plce sand fill (X2090213)CY15$100.00$140.00$130.00
11Explor trench SPL (X2130010)LF188$0.01$0.01$45.00
12Seeding CL 4A mod (X2502014)ACRE1.75$4,400.00$1,500.00$4,000.00
13Rem & salv sign panel (X2600007)EACH4$500.00$800.00$100.00
14HMA surf rem var DP (X4401198)SY357$10.00$10.00$15.00
15Rem conc end sec (X5010523)EACH4$350.00$500.00$500.00
16Traf cont & prot SPL (X7010216)LS1$101,800$10,000$55,555
17Rem RE-erect EX sign (X7240600)EACH2$500.00$1,400.00$1,000.00
18LT P 25FMH 4FTARM SPL (X8302393)EACH8$3,575.00$5,150.00$5,150.00
19LT P A 25MH 4FT TW SPL (X8302395)EACH1$3,925.00$5,250.00$5,250.00
20Construction layout (Z0013798)LS1$20,000$52,000$65,000
21Earth excavation (20200100)CY6,375$20.00$18.00$40.00
22Trench backfill (20800150)CY60$60.00$70.00$100.00
23Geotech fab F/GR stab (21001000)SY7,242$3.00$2.25$2.20
24Topsoil F & P 8 (21101630)SY20,584$5.50$7.00$8.00
25Grading & shap ditch (21400100)LF3,888$12.00$9.00$8.00
26Seeding CL 1 (25000100)ACRE1.50$2,200.00$2,000.00$2,000.00
27Seeding CL 1B (25000115)ACRE1.25$2,200.00$2,000.00$2,000.00
28Nitrogen fert nutr (25000400)LB410$2.20$4.00$2.00
29Phosphorus fert nutr (25000500)LB410$2.20$4.00$2.00
30Potassium fert nutr (25000600)LB410$2.20$4.00$2.00
31Mulch method 2 (25100115)ACRE3$2,035.00$3,000.00$1,850.00
32Erosion contr blanket (25100630)SY4,926$1.49$2.00$1.35
33HD eros contr blanket (25100635)SY1,748$1.93$3.00$1.75
34Temp ditch checks (28000305)LF382$11.00$20.00$10.00
35Perimeter eros bar (28000400)LF2,107$3.30$4.00$3.00
36Inlet & pipe protect (28000500)EACH17$220.00$0.01$200.00
37Agg base cse B (35101500)CY2,181$50.00$65.00$60.00
38Agg base cse B 4 (35101600)SY723$8.00$20.00$12.00
39Preparation of base (35800100)SY12,855$2.00$2.00$1.50
40Agg base repair (35800200)TON122$30.00$60.00$25.00
41Agg surf cse B (40200900)CY15$65.00$80.00$95.00
42Bit matls PR CT (40600275)LB58,202$0.01$0.01$0.01
43Bit matls tack CT (40600290)LB3,336$0.01$0.01$0.01
44HMA surf rem butt JT (40600982)SY595$0.01$0.01$0.01
45HMA BC IL-19.0 N50 (40603080)TON1,218$75.00$95.00$90.00
46HMA SC IL-9.5 C N50 (40604050)TON2,228$78.00$100.00$95.00
47HMA pavt FD 6 (40701801)SY3,977$26.00$34.00$35.00
48PC conc sidewalk 4 (42400100)SF6,506$8.50$6.50$10.00
49Detectable warnings (42400800)SF131$35.00$20.00$26.00
50Pavement rem (44000100)SY14,081$7.00$4.25$6.00
51HMA surf rem 2 (44000157)SY12,232$2.50$2.50$4.00
52HMA surf rem 2 1/2 (44000159)SY5,805$3.50$3.00$5.00
53Comb curb gutter rem (44000500)LF1,582$10.00$6.00$15.00
54Sidewalk rem (44000600)SF1,581$3.50$2.50$4.00
55Crack filling (45100200)LB3,403$1.93$2.15$2.15
56Agg wedge SHLD type B (48102100)TON93$50.00$70.00$65.00
57Conc rem (50102400)CY15$500.00$90.00$125.00
58Conc headwall removal (50104400)EACH6$350.00$250.00$500.00
59Pipe culvert remov (50105220)LF455$20.00$25.00$20.00
60P cul CL A 1 12 (542A0217)LF145$75.00$75.00$75.00
61P cul CL A 1 15 (542A0220)LF129$85.00$79.00$90.00
62P cul CL A 1 eqrs 24 (542A5479)LF249$145.00$140.00$110.00
63PRC flar end sec 12 (54213657)EACH6$1,000.00$1,700.00$1,200.00
64PRC flar end sec 15 (54213660)EACH4$1,200.00$1,800.00$1,400.00
65PRC flar end sec 24 (54213669)EACH2$1,650.00$2,400.00$1,800.00
66PRC FL end S EQ RS 24 (54214509)EACH8$1,550.00$2,700.00$2,000.00
67Remov inlets (60500060)EACH6$500.00$500.00$500.00
68Class SI conc outlet (60600095)CY5$550.00$800.00$1,500.00
69Comb CC&G TB6.12 (60603800)LF65$50.00$45.00$60.00
70Comb CC&G TM4.12 (60608562)LF1,898$27.50$26.00$35.00
71Pipe culv cleaned 18 (60920018)LF22$25.00$33.00$30.00
72Pipe culv cleaned 24 (60920024)LF47$27.50$34.00$50.00
73Pipe culv cleaned ers 24 (60921024)LF48$30.00$35.00$60.00
74Engr field office A (67000400)CAL MO6$4,500.00$2,000.00$1.00
75Mobilization (67100100)LS1$105,000$115,000$100,000
76Sign panel T1 (72000100)SF31$27.50$35.00$25.00
77Sign panel T2 (72000200)SF12$22.00$70.00$20.00
78Remov sin pan assy TA (72400100)EACH4$82.50$125.00$75.00
79Rem & rel sign panel T1 (72400735)SF8$16.50$75.00$15.00
80Teles STL sin support (72800100)LF72$16.50$18.00$15.00
81Wood sin support (73000100)LF84$27.50$33.00$25.00
82Base tel STL sin supp (73100100)EACH6$247.50$250.00$225.00
83Mod ureth PM LTR-sym (78009000)SF526$12.76$7.45$11.60
84Mod ureth PM line 4 (78009004)LF41,272$1.49$1.25$1.35
85Mod ureth PM line 6 (78009006)LF104$4.62$1.87$4.20
86Mod ureth PM line 12 (78009012)LF96$10.34$3.73$9.40
87Mod ureth PM line 24 (78009024)LF84$17.60$7.45$16.00
88PVT MKG rem WTR blast (78300202)SF25$110.00$100.00$100.00
89Undrgrd C CNC 2 (81028750)LF200$18.00$20.00$20.00
90UD 2#8 #8G xlpuse 3/4 (81603000)LF950$10.30$25.00$25.00
91Lum LED rdwy F (82110006)EACH10$6.65$950.00$950.00
92Light pole FDN 24D (83600200)LF45$320.00$350.00$350.00
93Rem LT U no salv (84200600)EACH7$300.00$1,000.00$1,000.00
94Rem pole FDN (84200804)EACH7$600.00$750.00$750.00
95Reloc EX TS equip (89501250)EACH1$100.00$5,280.00$5,280.00
IDOT contract 46940: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy