IDOT contract 61J63 bid tabulation
Rolling Meadows, section 19-00123-00-BT. Let by Illinois DOT on January 17, 2025, Cook, District 01. 7 bids received; low bid $1,051,893 by Martam Construction Incorporated.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 96
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martam Construction Incorporated | $1,051,893 | Low |
| 2 | PirTano Construction Co., LLC | $1,087,000 | +3.0% |
| 3 | R. W. Dunteman Company | $1,158,000 | +10% |
| 4 | Schroeder Asphalt Services, Inc. | $1,196,773 | +14% |
| 5 | Performance Construction and Engineering, LLC | $1,238,413 | +18% |
| 6 | A Lamp Concrete Contractors, Inc. | $1,284,991 | +22% |
| 7 | Alliance Contractors, Inc. | $1,341,333 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martam Construction Incorporated | 2. PirTano Construction Co., LLC | 3. R. W. Dunteman Company | 4. Schroeder Asphalt Services, Inc. | 5. Performance Construction and Engineering, LLC | 6. A Lamp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | T-celtis occid 2-1/2 (A2002920) | EACH | 4 | $600.00 | $524.00 | $524.00 | $675.00 | $600.00 | $575.00 |
| 2 | T-tilia amer 2-1/2 (A2007820) | EACH | 4 | $620.00 | $560.00 | $560.00 | $675.00 | $600.00 | $575.00 |
| 3 | T-ulmus amer PRNC 2.5 (A2008470) | EACH | 2 | $660.00 | $596.00 | $596.00 | $650.00 | $600.00 | $550.00 |
| 4 | S-buxus micro WG 2 (C2C01024) | EACH | 12 | $105.00 | $94.00 | $94.00 | $90.00 | $120.00 | $80.00 |
| 5 | Wood fence (XX000882) | LF | 200 | $60.00 | $53.48 | $53.48 | $60.00 | $125.00 | $53.48 |
| 6 | Sign to BE relocated (XX006066) | EACH | 2 | $2,200.00 | $500.00 | $286.45 | $600.00 | $2,000.00 | $2,000.00 |
| 7 | Safety fence (XX007037) | LF | 1,613 | $102.00 | $92.61 | $92.61 | $105.00 | $160.00 | $92.61 |
| 8 | Washout basin (X0326806) | LS | 1 | $2,500.00 | $1,500.00 | $1,500.00 | $2,600.00 | $1,000.00 | $500.00 |
| 9 | Ped signal post 10 FT (X1400367) | EACH | 1 | $1,400.00 | $2,811.00 | $1,356.22 | $1,600.00 | $1,350.00 | $2,811.00 |
| 10 | Stump removal only (X2010400) | UNIT | 256 | $30.00 | $25.00 | $25.00 | $14.00 | $7.00 | $12.00 |
| 11 | Detectable warn SPL (X4240800) | SF | 156 | $48.00 | $50.50 | $42.46 | $54.00 | $50.00 | $25.00 |
| 12 | Remov EX flar end sec (X5427602) | EACH | 1 | $500.00 | $258.81 | $961.05 | $1,110.00 | $1,000.00 | $500.00 |
| 13 | Man TA 6D T1F CL R-P (X6020094) | EACH | 3 | $14,400 | $15,423 | $20,500 | $10,823 | $12,000 | $16,500 |
| 14 | Accessible ped signal (X8760200) | EACH | 2 | $3,500.00 | $4,922.00 | $3,313.88 | $3,600.00 | $3,200.00 | $4,922.00 |
| 15 | Conc FDN TY A 12D (X8780012) | LF | 4 | $360.00 | $1,029.00 | $348.97 | $600.00 | $350.00 | $1,029.00 |
| 16 | HMA driveway pavt 3 (Z0004510) | SY | 48 | $58.00 | $103.92 | $45.80 | $39.00 | $30.00 | $34.00 |
| 17 | HMA driveway pavt 4 (Z0004514) | SY | 69 | $65.00 | $138.80 | $75.29 | $50.00 | $36.00 | $34.00 |
| 18 | HMA driveway pavt 8 (Z0004530) | SY | 137 | $102.00 | $162.48 | $96.09 | $79.00 | $73.00 | $60.00 |
| 19 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $8,500.00 | $8,500.00 | $12,000 | $10,519 | $8,500.00 |
| 20 | Temp info signing (Z0030850) | SF | 104 | $22.00 | $15.00 | $15.00 | $25.00 | $20.00 | $20.00 |
| 21 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 1 | $820.00 | $1,703.00 | $772.76 | $1,100.00 | $775.03 | $1,703.00 |
| 22 | Tree root pruning (20101200) | EACH | 3 | $90.00 | $75.00 | $75.00 | $170.00 | $100.00 | $150.00 |
| 23 | Tree prun 1-10 (20101300) | EACH | 4 | $60.00 | $50.00 | $50.00 | $170.00 | $100.00 | $150.00 |
| 24 | Tree prun over 10 (20101350) | EACH | 2 | $70.00 | $60.00 | $60.00 | $275.00 | $100.00 | $250.00 |
| 25 | Nitrogen fert nutr (20101400) | LB | 54 | $3.00 | $3.00 | $3.00 | $4.00 | $2.00 | $3.00 |
| 26 | Phosphorus fert nutr (20101500) | LB | 54 | $3.00 | $3.00 | $3.00 | $4.00 | $2.00 | $3.00 |
| 27 | Potassium fert nutr (20101600) | LB | 54 | $3.00 | $3.00 | $3.00 | $4.00 | $2.00 | $3.00 |
| 28 | Earth excavation (20200100) | CY | 424 | $45.00 | $88.99 | $71.25 | $48.50 | $65.00 | $49.00 |
| 29 | Rem & disp uns matl (20201200) | CY | 834 | $45.00 | $49.75 | $62.55 | $50.00 | $55.00 | $25.00 |
| 30 | Furnished excavation (20400800) | CY | 371 | $28.00 | $34.44 | $16.95 | $30.00 | $15.00 | $30.00 |
| 31 | Trench backfill (20800150) | CY | 245 | $60.00 | $90.34 | $90.00 | $52.75 | $25.00 | $64.00 |
| 32 | Geotech fab F/GR stab (21001000) | SY | 2,140 | $2.00 | $2.54 | $3.75 | $3.00 | $2.50 | $2.00 |
| 33 | Topsoil F & P 4 (21101615) | SY | 2,740 | $6.00 | $6.00 | $1.00 | $7.00 | $5.00 | $5.50 |
| 34 | Seeding CL 1A (25000110) | ACRE | 0.50 | $5,000.00 | $4,319.00 | $4,319.00 | $9,500.00 | $5,000.00 | $8,000.00 |
| 35 | Erosion contr blanket (25100630) | SY | 1,757 | $1.40 | $1.20 | $1.20 | $1.30 | $1.20 | $1.00 |
| 36 | Sodding (25200100) | SY | 984 | $12.00 | $11.00 | $11.00 | $22.00 | $11.00 | $20.00 |
| 37 | Supple watering (25200200) | UNIT | 55 | $1.00 | $0.01 | $0.01 | $5.00 | $1.00 | $1.00 |
| 38 | Temp eros contr seed (28000250) | LB | 57 | $5.00 | $4.00 | $4.00 | $7.00 | $6.00 | $5.00 |
| 39 | Perimeter eros bar (28000400) | LF | 1,262 | $2.80 | $2.50 | $2.50 | $4.15 | $5.00 | $3.00 |
| 40 | Inlet filters (28000510) | EACH | 9 | $150.00 | $125.00 | $125.00 | $250.00 | $200.00 | $15.00 |
| 41 | Agg subgrade improve (30300001) | CY | 60 | $78.00 | $95.39 | $67.11 | $80.00 | $55.00 | $25.00 |
| 42 | Sub gran mat B 6 (31101400) | SY | 104 | $6.00 | $26.86 | $14.05 | $15.00 | $16.00 | $11.25 |
| 43 | Agg base cse B 4 (35101600) | SY | 837 | $6.00 | $17.73 | $9.52 | $10.00 | $14.00 | $7.75 |
| 44 | Agg base cse B 6 (35101800) | SY | 2,331 | $9.00 | $24.51 | $15.93 | $14.00 | $16.00 | $14.75 |
| 45 | Agg base cse B 10 (35102200) | SY | 69 | $29.00 | $40.49 | $21.75 | $20.00 | $22.00 | $25.00 |
| 46 | Bit matls PR CT (40600275) | LB | 5,245 | $0.10 | $0.01 | $0.60 | $0.01 | $0.01 | $0.01 |
| 47 | HMA SC IL-9.5 D N50 (40604060) | TON | 512 | $120.00 | $137.51 | $123.50 | $115.00 | $140.00 | $126.00 |
| 48 | PCC driveway pavt 8 (42300400) | SY | 478 | $90.00 | $70.50 | $70.56 | $160.00 | $100.00 | $115.00 |
| 49 | PC conc sidewalk 8 (42400410) | SF | 1,993 | $10.00 | $12.00 | $10.60 | $14.50 | $14.00 | $13.00 |
| 50 | Drive pavement rem (44000200) | SY | 822 | $12.00 | $11.85 | $18.51 | $18.00 | $10.00 | $18.00 |
| 51 | Curb rem (44000300) | LF | 124 | $8.00 | $15.43 | $12.81 | $16.50 | $10.00 | $7.00 |
| 52 | Comb curb gutter rem (44000500) | LF | 483 | $8.00 | $17.89 | $13.08 | $16.50 | $15.00 | $9.00 |
| 53 | Sidewalk rem (44000600) | SF | 10,935 | $1.00 | $2.62 | $2.26 | $3.50 | $8.00 | $1.00 |
| 54 | Seg conc block wall (52200800) | SF | 1,771 | $48.00 | $38.00 | $38.00 | $69.00 | $48.00 | $55.00 |
| 55 | Storm sew CL A 1 12 (550A0050) | LF | 170 | $89.00 | $74.57 | $123.00 | $94.35 | $85.00 | $119.00 |
| 56 | Storm sew CL A 1 24 (550A0120) | LF | 194 | $149.00 | $110.87 | $162.00 | $133.20 | $140.00 | $187.00 |
| 57 | Storm sew CL A 1 36 (550A0160) | LF | 181 | $185.00 | $151.97 | $242.00 | $160.95 | $185.00 | $271.00 |
| 58 | Storm sew CL A 2 12 (550A0340) | LF | 174 | $105.00 | $72.54 | $113.00 | $116.55 | $85.00 | $130.00 |
| 59 | Storm sewer rem 15 (55100700) | LF | 249 | $10.00 | $26.53 | $17.00 | $22.20 | $50.00 | $17.50 |
| 60 | P undr for struct 4 (60146304) | LF | 843 | $23.00 | $45.17 | $40.00 | $53.30 | $20.00 | $52.50 |
| 61 | CB TA 4 dia T8G (60200805) | EACH | 4 | $4,400.00 | $4,224.42 | $4,925.00 | $4,717.50 | $3,500.00 | $4,775.00 |
| 62 | CB TC T8G (60207605) | EACH | 2 | $2,800.00 | $2,204.25 | $2,635.00 | $3,385.50 | $2,500.00 | $2,900.00 |
| 63 | Man TA 5 dia T1F OL (60221000) | EACH | 1 | $5,500.00 | $5,643.23 | $6,275.00 | $5,272.50 | $5,500.00 | $6,350.00 |
| 64 | Man TA 6 dia T1F CL (60223800) | EACH | 1 | $8,200.00 | $9,322.43 | $9,508.00 | $7,492.50 | $8,700.00 | $11,550 |
| 65 | CB adjust (60250200) | EACH | 2 | $500.00 | $922.06 | $603.00 | $832.50 | $600.00 | $550.00 |
| 66 | CB adj new T4F&G (60250700) | EACH | 1 | $950.00 | $1,447.16 | $1,731.00 | $2,053.50 | $1,600.00 | $1,125.00 |
| 67 | Man adjust (60255500) | EACH | 4 | $500.00 | $922.05 | $605.00 | $832.50 | $600.00 | $700.00 |
| 68 | Valve box adj (60266600) | EACH | 2 | $300.00 | $310.70 | $500.00 | $555.00 | $600.00 | $550.00 |
| 69 | Remov manholes (60500040) | EACH | 2 | $400.00 | $250.56 | $600.00 | $555.00 | $750.00 | $575.00 |
| 70 | Remov catch bas (60500050) | EACH | 1 | $400.00 | $258.81 | $600.00 | $555.00 | $500.00 | $550.00 |
| 71 | Conc curb TB (60600605) | LF | 209 | $36.00 | $32.00 | $24.33 | $84.00 | $43.00 | $44.00 |
| 72 | Comb CC&G TB6.12 (60603800) | LF | 357 | $36.00 | $35.00 | $31.51 | $84.00 | $40.00 | $50.00 |
| 73 | Comb CC&G TY B-6.24 (60605000) | LF | 346 | $48.00 | $44.55 | $42.87 | $84.00 | $44.00 | $60.00 |
| 74 | Non SPL waste disposl (66900200) | CY | 105 | $95.00 | $113.73 | $97.79 | $110.00 | $60.00 | $100.00 |
| 75 | Soil disposal analy (66900530) | EACH | 1 | $1,400.00 | $1,270.00 | $1,270.00 | $1,500.00 | $1,200.00 | $1,270.00 |
| 76 | Reg sub P-const plan (66901001) | LS | 1 | $3,700.00 | $3,400.00 | $3,400.00 | $3,900.00 | $1,400.00 | $3,400.00 |
| 77 | Reg sub F con report (66901003) | LS | 1 | $600.00 | $500.00 | $500.00 | $550.00 | $500.00 | $500.00 |
| 78 | Reg sub mon (66901006) | CAL DAY | 10 | $770.00 | $700.00 | $700.00 | $900.00 | $1,000.00 | $700.00 |
| 79 | Mobilization (67100100) | LS | 1 | $60,000 | $43,306 | $70,000 | $25,000 | $72,000 | $77,000 |
| 80 | TR cont & prot 701501 (70102620) | LS | 1 | $1.00 | $5,000.00 | $93,893 | $150.00 | $1.00 | $1.00 |
| 81 | TR cont & prot 701602 (70102632) | LS | 1 | $1.00 | $1.00 | $1.00 | $20,000 | $1.00 | $1.00 |
| 82 | TR cont & prot 701701 (70102635) | LS | 1 | $56,500 | $1.00 | $1.00 | $150.00 | $10,000 | $160,700 |
| 83 | TR cont & prot 701801 (70102640) | LS | 1 | $2,500.00 | $1.00 | $1.00 | $150.00 | $2,500.00 | $2,000.00 |
| 84 | THPL PVT MK line 6 (78000400) | LF | 329 | $5.00 | $3.80 | $4.00 | $5.00 | $4.50 | $4.50 |
| 85 | THPL PVT MK line 12 (78000600) | LF | 546 | $10.00 | $7.50 | $5.00 | $6.00 | $9.00 | $9.00 |
| 86 | THPL PVT MK line 24 (78000650) | LF | 37 | $20.00 | $13.65 | $7.00 | $8.00 | $18.00 | $18.00 |
| 87 | PVT MKG rem WTR blast (78300202) | SF | 180 | $22.00 | $12.05 | $14.00 | $22.00 | $25.00 | $20.00 |
| 88 | Undrgrd C galvs 2 (81028200) | LF | 13 | $60.00 | $179.80 | $56.28 | $60.00 | $55.00 | $179.80 |
| 89 | Main EX TR sig instal (85000200) | EACH | 1 | $5,000.00 | $12,800 | $3,751.77 | $4,250.00 | $8,000.00 | $12,800 |
| 90 | Elcbl C signal 14 2C (87301215) | LF | 448 | $5.20 | $2.90 | $5.09 | $5.75 | $5.00 | $2.90 |
| 91 | Elcbl C signal 14 3C (87301225) | LF | 462 | $5.50 | $3.40 | $5.22 | $5.85 | $5.00 | $3.40 |
| 92 | Elcbl C egrdc 6 1C (87301900) | LF | 26 | $7.00 | $3.80 | $6.70 | $7.15 | $7.00 | $3.80 |
| 93 | Drill EX handhole (87900200) | EACH | 1 | $1,000.00 | $2,577.00 | $966.57 | $1,250.00 | $1,000.00 | $2,577.00 |
| 94 | Ped SH LED 1F BM CDT (88102717) | EACH | 2 | $850.00 | $641.00 | $817.01 | $850.00 | $1,600.00 | $641.00 |
| 95 | Mod EX contr (89502200) | EACH | 1 | $1,100.00 | $3,135.00 | $1,041.39 | $1,250.00 | $3,000.00 | $3,135.00 |
| 96 | Rebuild EX handhole (89502376) | EACH | 1 | $2,400.00 | $3,595.00 | $2,391.06 | $3,300.00 | $3,000.00 | $3,595.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.