IDOT contract 61K77 bid tabulation
Wood Dale, section 22-00055-00-BT. Let by Illinois DOT on August 1, 2025, Dupage, District 01. 8 bids received; low bid $553,433 by R. W. Dunteman Company.
- Owner
- Illinois DOT
- Letting
- 01 AUG 2025
- Pay items
- 81
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R. W. Dunteman Company | $553,433 | Low |
| 2 | Martam Construction Incorporated | $567,916 | +3.0% |
| 3 | Acura Inc. | $569,722 | +3.0% |
| 4 | Schroeder Asphalt Services, Inc. | $588,764 | +6.0% |
| 5 | MYS, Incorporated | $610,598 | +10% |
| 6 | K-Five Construction Corporation | $652,380 | +18% |
| 7 | A Lamp Concrete Contractors, Inc. | $659,129 | +19% |
| 8 | Alliance Contractors, Inc. | $684,717 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R. W. Dunteman Company | 2. Martam Construction Incorporated | 3. Acura Inc. | 4. Schroeder Asphalt Services, Inc. | 5. MYS, Incorporated | 6. K-Five Construction Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | E-thuja occid 5' (D2003760) | EACH | 70 | $315.00 | $364.00 | $330.00 | $390.00 | $349.79 | $350.00 |
| 2 | Shrub removal (K0026830) | EACH | 6 | $80.00 | $156.00 | $160.00 | $100.00 | $111.04 | $150.00 |
| 3 | Weed contr pre-EM GRN (K0029634) | LB | 3 | $20.00 | $104.00 | $25.00 | $120.00 | $22.21 | $20.00 |
| 4 | Mulch placement 4 (K0036120) | SY | 263 | $11.00 | $20.80 | $15.00 | $23.00 | $12.22 | $6.00 |
| 5 | Prun safety/equip CLR (K1004595) | LS | 1 | $3,400.00 | $6,760.00 | $7,500.00 | $3,900.00 | $7,218.01 | $6,500.00 |
| 6 | Fold down bollards (X0350805) | EACH | 1 | $1,700.00 | $1,446.75 | $3,500.00 | $2,500.00 | $3,331.39 | $2,500.00 |
| 7 | Ped signal post 5 FT (X1400378) | EACH | 1 | $1,600.00 | $1,382.58 | $3,000.00 | $1,500.00 | $1,476.25 | $1,600.00 |
| 8 | Explor trench SPL (X2130010) | LF | 200 | $20.00 | $49.04 | $22.00 | $22.00 | $22.21 | $50.00 |
| 9 | Rem & rel sign panel (X2600011) | EACH | 4 | $75.00 | $78.00 | $265.00 | $100.00 | $83.29 | $75.00 |
| 10 | Temp access- com ent (X4022000) | EACH | 2 | $530.00 | $1,062.07 | $1,500.00 | $250.00 | $2,414.91 | $935.50 |
| 11 | Pavement patching SPL (X4420201) | SY | 22 | $536.00 | $292.10 | $150.00 | $150.00 | $133.25 | $10.09 |
| 12 | Sanitary manhole adj (X6026050) | EACH | 1 | $1,250.00 | $1,147.16 | $2,500.00 | $1,500.00 | $1,388.08 | $1,900.00 |
| 13 | Temp info signing (X7200061) | SF | 103 | $20.00 | $20.80 | $20.00 | $23.00 | $222.09 | $20.00 |
| 14 | Remove sign special (X7240302) | EACH | 1 | $8,650.00 | $449.39 | $2,000.00 | $5,000.00 | $2,887.20 | $6,676.28 |
| 15 | Decorative sign post (X7290004) | EACH | 1 | $3,500.00 | $2,704.00 | $2,500.00 | $3,250.00 | $555.23 | $2,600.00 |
| 16 | Accessible ped signal (X8760200) | EACH | 2 | $3,890.00 | $3,726.05 | $4,500.00 | $3,900.00 | $3,978.52 | $3,890.00 |
| 17 | Conc FDN TY A 12D (X8780012) | LF | 4 | $676.25 | $640.84 | $800.00 | $675.00 | $684.26 | $676.25 |
| 18 | Construction layout (Z0013798) | LS | 1 | $8,500.00 | $11,453 | $15,000 | $10,000 | $9,438.94 | $13,600 |
| 19 | Rem EX sign post (Z0051398) | EACH | 1 | $500.00 | $520.00 | $250.00 | $600.00 | $277.62 | $500.00 |
| 20 | Tree trunk protection (20101100) | EACH | 6 | $200.00 | $130.00 | $300.00 | $220.00 | $305.37 | $125.00 |
| 21 | Tree root pruning (20101200) | EACH | 3 | $250.00 | $130.00 | $130.00 | $275.00 | $144.36 | $125.00 |
| 22 | Earth excavation (20200100) | CY | 269 | $61.75 | $85.68 | $60.00 | $55.00 | $70.12 | $108.79 |
| 23 | Rem & disp uns matl (20201200) | CY | 688 | $72.00 | $72.42 | $45.00 | $60.00 | $91.98 | $73.33 |
| 24 | Trench backfill (20800150) | CY | 14 | $23.00 | $86.38 | $50.00 | $27.00 | $25.54 | $86.25 |
| 25 | Topsoil exc & plac (21101505) | CY | 1,083 | $42.00 | $27.13 | $20.00 | $30.00 | $7.77 | $58.19 |
| 26 | Seeding CL 2A (25000210) | ACRE | 2 | $2,000.00 | $2,600.00 | $2,500.00 | $2,800.00 | $2,220.93 | $3,650.00 |
| 27 | Nitrogen fert nutr (25000400) | LB | 180 | $3.75 | $5.20 | $4.00 | $6.00 | $4.16 | $3.00 |
| 28 | Potassium fert nutr (25000600) | LB | 180 | $3.75 | $5.20 | $4.00 | $6.00 | $4.16 | $3.00 |
| 29 | Erosion contr blanket (25100630) | SY | 6,500 | $1.15 | $1.92 | $1.25 | $2.10 | $1.28 | $1.10 |
| 30 | Supple watering (25200200) | UNIT | 8 | $0.50 | $1.04 | $1.00 | $1.50 | $0.56 | $100.00 |
| 31 | Temp eros contr seed (28000250) | LB | 200 | $4.00 | $1.04 | $4.20 | $1.50 | $4.44 | $1.00 |
| 32 | Temp ditch checks (28000305) | LF | 90 | $9.75 | $15.60 | $10.00 | $17.00 | $10.83 | $8.00 |
| 33 | Perimeter eros bar (28000400) | LF | 1,394 | $3.50 | $4.16 | $4.00 | $4.75 | $3.89 | $2.00 |
| 34 | Inlet filters (28000510) | EACH | 1 | $200.00 | $520.00 | $550.00 | $550.00 | $222.09 | $350.00 |
| 35 | Temp eros contr blank (28001100) | SY | 6,500 | $0.95 | $0.01 | $1.00 | $0.02 | $1.05 | $1.10 |
| 36 | Agg subgrade improve (30300001) | CY | 95 | $77.40 | $58.61 | $50.00 | $60.00 | $76.12 | $94.93 |
| 37 | Sub gran mat B 2 (31101180) | SY | 99 | $10.70 | $5.42 | $15.00 | $12.00 | $8.35 | $17.35 |
| 38 | Sub gran mat B 6 (31101400) | SY | 2,851 | $12.50 | $9.26 | $18.00 | $16.00 | $14.63 | $20.00 |
| 39 | Agg base cse B 8 (35102000) | SY | 323 | $23.50 | $12.11 | $25.00 | $20.70 | $18.64 | $25.64 |
| 40 | HMA base cse 6 (35501308) | SY | 323 | $53.25 | $41.60 | $75.00 | $65.00 | $44.42 | $56.21 |
| 41 | Bit matls PR CT (40600275) | LB | 7,140 | $0.01 | $0.52 | $0.01 | $0.01 | $0.56 | $0.01 |
| 42 | Bit matls tack CT (40600290) | LB | 910 | $0.01 | $1.04 | $0.01 | $0.01 | $1.11 | $0.01 |
| 43 | HMA BC IL-9.5 N50 (40602978) | TON | 291 | $113.00 | $171.60 | $175.00 | $140.00 | $183.23 | $161.45 |
| 44 | HMA SC IL-9.5 D N50 (40604060) | TON | 291 | $118.00 | $172.80 | $180.00 | $150.00 | $184.50 | $161.45 |
| 45 | PC conc sidewalk 5 (42400200) | SF | 889 | $9.95 | $12.21 | $16.00 | $22.50 | $13.59 | $11.65 |
| 46 | Detectable warnings (42400800) | SF | 168 | $35.45 | $46.15 | $50.00 | $62.00 | $53.27 | $33.60 |
| 47 | Pavement rem (44000100) | SY | 2 | $341.35 | $191.02 | $50.00 | $300.00 | $392.88 | $196.00 |
| 48 | Drive pavement rem (44000200) | SY | 313 | $29.50 | $12.97 | $25.00 | $17.00 | $25.77 | $15.35 |
| 49 | Comb curb gutter rem (44000500) | LF | 109 | $12.00 | $5.84 | $15.00 | $27.50 | $13.38 | $19.25 |
| 50 | Sidewalk rem (44000600) | SF | 1,241 | $3.50 | $2.01 | $4.00 | $5.60 | $2.89 | $3.80 |
| 51 | Pipe culvert remov (50105220) | LF | 172 | $15.00 | $10.61 | $20.00 | $17.00 | $16.66 | $29.00 |
| 52 | P cul CL A 1 15 (542A0220) | LF | 178 | $185.00 | $80.34 | $200.00 | $210.00 | $205.44 | $113.00 |
| 53 | PRC flar end sec 15 (54213660) | EACH | 6 | $1,265.00 | $1,742.95 | $1,500.00 | $1,500.00 | $1,404.17 | $1,940.10 |
| 54 | Inl recon new T1F OL (60262900) | EACH | 1 | $1,450.00 | $1,683.46 | $1,600.00 | $1,700.00 | $1,610.17 | $1,505.00 |
| 55 | VV adj new T1F CL (60265900) | EACH | 3 | $1,285.00 | $1,068.97 | $1,500.00 | $1,450.00 | $1,426.94 | $1,160.00 |
| 56 | Conc curb TB (60600605) | LF | 80 | $50.50 | $65.87 | $70.00 | $165.00 | $94.38 | $37.45 |
| 57 | Comb CC&G TB6.12 (60603800) | LF | 60 | $66.50 | $59.49 | $70.00 | $165.00 | $59.51 | $55.50 |
| 58 | Mobilization (67100100) | LS | 1 | $27,500 | $34,075 | $33,000 | $25,000 | $35,400 | $39,200 |
| 59 | TR cont & prot 701501 (70102620) | LS | 1 | $43,000 | $41,817 | $5,000.00 | $7,500.00 | $20,447 | $55,443 |
| 60 | TR cont & prot 701801 (70102640) | LS | 1 | $800.00 | $104.00 | $2,000.00 | $2,000.00 | $1,776.74 | $100.00 |
| 61 | Sign panel T1 (72000100) | SF | 116 | $39.13 | $31.20 | $28.00 | $38.00 | $33.32 | $30.00 |
| 62 | Sign panel T2 (72000200) | SF | 26 | $40.00 | $41.60 | $32.00 | $50.00 | $44.42 | $40.00 |
| 63 | Remov sin pan assy TA (72400100) | EACH | 17 | $75.00 | $78.00 | $85.00 | $90.00 | $83.29 | $75.00 |
| 64 | Teles STL sin support (72800100) | LF | 345 | $17.00 | $17.68 | $20.00 | $20.00 | $18.88 | $17.00 |
| 65 | THPL PVT MK LTR & sym (78000100) | SF | 134 | $14.25 | $14.46 | $35.00 | $22.50 | $15.82 | $9.38 |
| 66 | THPL PVT MK line 4 (78000200) | LF | 50 | $2.50 | $3.74 | $6.00 | $3.00 | $2.78 | $2.35 |
| 67 | THPL PVT MK line 6 (78000400) | LF | 130 | $3.60 | $7.70 | $9.00 | $3.95 | $4.00 | $3.00 |
| 68 | THPL PVT MK line 12 (78000600) | LF | 360 | $7.25 | $16.69 | $17.00 | $8.00 | $8.05 | $6.00 |
| 69 | THPL PVT MK line 24 (78000650) | LF | 40 | $14.25 | $32.76 | $35.00 | $16.00 | $15.82 | $11.25 |
| 70 | PVT MKG rem WTR blast (78300202) | SF | 56 | $55.00 | $46.80 | $60.00 | $225.00 | $49.97 | $55.00 |
| 71 | Undrgrd C galvs 2 (81028200) | LF | 10 | $34.03 | $215.71 | $36.00 | $225.00 | $230.33 | $34.03 |
| 72 | Rem LT U no salv (84200600) | EACH | 4 | $902.50 | $1,013.89 | $1,000.00 | $1,050.00 | $1,082.59 | $902.50 |
| 73 | Rem pole FDN (84200804) | EACH | 2 | $940.00 | $1,587.79 | $1,000.00 | $1,650.00 | $1,695.37 | $940.00 |
| 74 | Main EX TR sig instal (85000200) | EACH | 1 | $1,860.00 | $6,067.08 | $1,990.00 | $6,200.00 | $6,474.73 | $1,860.00 |
| 75 | Elcbl C signal 14 2C (87301215) | LF | 35 | $2.18 | $5.62 | $3.00 | $6.00 | $6.00 | $2.18 |
| 76 | Elcbl C egrdc 6 1C (87301900) | LF | 35 | $3.48 | $7.58 | $4.00 | $7.90 | $8.10 | $3.48 |
| 77 | Elcbl as sigl 14 2C (87302212) | LF | 140 | $3.00 | $22.13 | $4.00 | $23.00 | $23.63 | $3.00 |
| 78 | Elcbl as sigl 14 3C (87302225) | LF | 135 | $3.25 | $22.31 | $3.60 | $23.00 | $23.82 | $3.25 |
| 79 | Ped SH LED 1F BM CDT (88102717) | EACH | 2 | $1,120.00 | $859.07 | $1,200.00 | $900.00 | $917.28 | $1,120.00 |
| 80 | Mod EX contr (89502200) | EACH | 1 | $1,121.25 | $88.37 | $1,200.00 | $90.00 | $94.35 | $1,121.25 |
| 81 | Mod EX contr cab (89502210) | EACH | 1 | $1,652.50 | $589.11 | $1,750.00 | $610.00 | $629.02 | $1,652.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.