IDOT contract 61L04 bid tabulation
Woodridge, section 19-00083-00-FP. Let by Illinois DOT on January 17, 2025, Dupage, District 01. 5 bids received; low bid $2,756,923 by K-Five Construction Corporation.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 89
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | K-Five Construction Corporation | $2,756,923 | Low |
| 2 | A Lamp Concrete Contractors, Inc. | $2,789,405 | +1.0% |
| 3 | Schroeder Asphalt Services, Inc. | $2,876,133 | +4.0% |
| 4 | R. W. Dunteman Company | $2,967,351 | +8.0% |
| 5 | Alliance Contractors, Inc. | $3,146,474 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. K-Five Construction Corporation | 2. A Lamp Concrete Contractors, Inc. | 3. Schroeder Asphalt Services, Inc. | 4. R. W. Dunteman Company | 5. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $7,800.00 | $5,000.00 | $9,000.00 | $3,300.00 | $7,995.00 |
| 2 | Storm sew CL B 1 8 (XX009453) | LF | 126 | $165.00 | $255.00 | $145.00 | $255.00 | $131.00 |
| 3 | Structure adj (X0326862) | EACH | 32 | $1,200.00 | $550.00 | $730.00 | $550.00 | $650.00 |
| 4 | Temp access- priv ent (X4021000) | EACH | 37 | $200.00 | $250.00 | $125.00 | $191.83 | $265.00 |
| 5 | Temp access- com ent (X4022000) | EACH | 1 | $350.00 | $595.00 | $200.00 | $305.36 | $265.00 |
| 6 | Temp access- road (X4023000) | EACH | 11 | $500.00 | $595.00 | $300.00 | $323.42 | $265.00 |
| 7 | Temporary ramp SPL (X4060995) | SY | 576 | $20.00 | $18.25 | $25.00 | $9.77 | $23.89 |
| 8 | PCC driveway PVT 6 SP (X4230710) | SY | 67 | $115.00 | $120.00 | $110.00 | $101.56 | $119.70 |
| 9 | Sidewalk rem SPL (X4404700) | SF | 4,153 | $4.00 | $1.85 | $5.00 | $10.28 | $3.00 |
| 10 | Sanitary manhole adj (X6026050) | EACH | 1 | $1,400.00 | $1,850.00 | $1,900.00 | $1,850.00 | $1,700.00 |
| 11 | Conc med TSB6.12 SPL (X6061900) | SF | 242 | $40.00 | $53.00 | $26.00 | $24.20 | $22.00 |
| 12 | Traf cont & prot SPL (X7010216) | LS | 1 | $80,800 | $133,000 | $150,000 | $146,769 | $69,698 |
| 13 | HMA driveway pavt 3 (Z0004510) | SY | 19 | $37.00 | $96.50 | $80.00 | $94.09 | $67.42 |
| 14 | HMA driveway pavt 8 (Z0004530) | SY | 296 | $90.00 | $90.00 | $83.00 | $131.77 | $79.11 |
| 15 | Stab constr entrance (Z0013797) | SY | 284 | $24.00 | $1.00 | $25.00 | $29.94 | $1.00 |
| 16 | Construction layout (Z0013798) | LS | 1 | $22,700 | $13,900 | $18,000 | $23,300 | $13,900 |
| 17 | Dust control watering (Z0019600) | UNIT | 50 | $100.00 | $1.00 | $100.00 | $27.81 | $100.00 |
| 18 | Temp info signing (Z0030850) | SF | 289 | $14.00 | $15.00 | $20.00 | $15.00 | $15.00 |
| 19 | Temp pavement (Z0062456) | SY | 92 | $90.00 | $53.50 | $55.00 | $63.00 | $143.46 |
| 20 | Temp TR signal timing (Z0073510) | EACH | 4 | $414.00 | $650.00 | $475.00 | $414.00 | $650.00 |
| 21 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 22 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 23 | Temporary fence (20101000) | LF | 1,280 | $3.50 | $4.00 | $7.00 | $3.10 | $3.50 |
| 24 | Tree root pruning (20101200) | EACH | 32 | $110.00 | $225.00 | $150.00 | $100.00 | $90.00 |
| 25 | Earth excavation (20200100) | CY | 5,481 | $45.00 | $45.50 | $39.00 | $31.71 | $10.00 |
| 26 | Rem & disp uns matl (20201200) | CY | 318 | $45.00 | $47.00 | $60.00 | $69.13 | $15.00 |
| 27 | Geotech fab F/GR stab (21001000) | SY | 19,323 | $2.00 | $1.40 | $1.30 | $2.56 | $3.00 |
| 28 | Topsoil F & P 4 (21101615) | SY | 2,115 | $0.10 | $6.00 | $11.00 | $5.12 | $0.10 |
| 29 | Seeding CL 2A (25000210) | ACRE | 0.44 | $29,040 | $5,000.00 | $5,800.00 | $4,300.00 | $29,040 |
| 30 | Nitrogen fert nutr (25000400) | LB | 43 | $1.00 | $3.00 | $2.00 | $3.00 | $1.00 |
| 31 | Potassium fert nutr (25000600) | LB | 43 | $1.00 | $3.00 | $2.00 | $3.00 | $1.00 |
| 32 | Erosion contr blanket (25100630) | SY | 2,115 | $2.00 | $2.50 | $4.00 | $3.35 | $2.00 |
| 33 | Temp eros contr seed (28000250) | LB | 52 | $0.10 | $5.00 | $0.02 | $3.31 | $0.10 |
| 34 | Inlet filters (28000510) | EACH | 32 | $225.00 | $185.00 | $330.00 | $200.00 | $25.00 |
| 35 | Temp eros contr blank (28001100) | SY | 1,884 | $0.10 | $0.10 | $0.02 | $1.25 | $0.10 |
| 36 | Agg subgrade improve (30300001) | CY | 318 | $25.00 | $45.00 | $64.00 | $62.22 | $55.00 |
| 37 | Agg subgrade impr 12 (30300112) | SY | 19,323 | $16.00 | $14.00 | $17.00 | $17.73 | $27.05 |
| 38 | Agg base cse B 4 (35101600) | SY | 608 | $0.01 | $7.00 | $9.00 | $8.70 | $8.00 |
| 39 | HMA base cse 7 (35501312) | SY | 17,183 | $35.00 | $36.50 | $34.50 | $35.03 | $36.31 |
| 40 | Bit matls tack CT (40600290) | LB | 15,464 | $0.01 | $0.01 | $0.01 | $1.39 | $0.01 |
| 41 | Long joint sealant (40600370) | LF | 9,530 | $3.05 | $2.97 | $3.65 | $5.14 | $3.45 |
| 42 | HMA surf rem butt JT (40600982) | SY | 86 | $25.00 | $20.00 | $12.00 | $26.08 | $72.09 |
| 43 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,925 | $89.00 | $102.00 | $94.00 | $94.11 | $110.50 |
| 44 | PC conc sidewalk 5 (42400200) | SF | 4,153 | $13.00 | $9.50 | $11.00 | $13.32 | $12.25 |
| 45 | Detectable warnings (42400800) | SF | 239 | $50.00 | $30.00 | $45.00 | $37.00 | $40.00 |
| 46 | Pavement rem (44000100) | SY | 17,139 | $8.00 | $13.50 | $11.50 | $11.00 | $27.55 |
| 47 | Drive pavement rem (44000200) | SY | 371 | $30.00 | $10.00 | $18.00 | $39.21 | $25.00 |
| 48 | Comb curb gutter rem (44000500) | LF | 4,972 | $9.00 | $5.55 | $8.00 | $12.45 | $15.00 |
| 49 | Pipe underdr T 2 4 (60108204) | LF | 300 | $45.00 | $88.00 | $40.00 | $88.00 | $36.00 |
| 50 | CB TA 4 dia T11F&G (60201105) | EACH | 1 | $6,800.00 | $8,650.00 | $4,850.00 | $8,650.00 | $4,350.00 |
| 51 | CB TA 4 dia T12F&G (60201205) | EACH | 1 | $6,800.00 | $8,950.00 | $5,350.00 | $8,950.00 | $4,725.00 |
| 52 | Inlets TA T11F&G (60236800) | EACH | 1 | $1,800.00 | $3,650.00 | $2,900.00 | $3,650.00 | $2,600.00 |
| 53 | Man reconst (60257900) | EACH | 1 | $1,800.00 | $1,650.00 | $3,200.00 | $1,650.00 | $2,820.00 |
| 54 | Valve box adj (60266600) | EACH | 1 | $1,000.00 | $425.00 | $450.00 | $425.00 | $401.00 |
| 55 | FR & grates T9 (60404600) | EACH | 1 | $1,100.00 | $685.00 | $1,000.00 | $685.00 | $900.00 |
| 56 | FR & grates T11 (60404800) | EACH | 15 | $850.00 | $650.00 | $1,025.00 | $650.00 | $925.00 |
| 57 | FR & grates T12 (60404900) | EACH | 10 | $850.00 | $985.00 | $1,500.00 | $985.00 | $1,300.00 |
| 58 | FR & lids T1 OL (60406000) | EACH | 1 | $650.00 | $450.00 | $800.00 | $450.00 | $725.00 |
| 59 | FR & lids T1 CL (60406100) | EACH | 5 | $650.00 | $450.00 | $800.00 | $450.00 | $725.00 |
| 60 | Remov catch bas (60500050) | EACH | 1 | $800.00 | $550.00 | $675.00 | $550.00 | $600.00 |
| 61 | Remov inlets (60500060) | EACH | 1 | $500.00 | $225.00 | $675.00 | $225.00 | $600.00 |
| 62 | Comb CC&G TB6.12 (60603800) | LF | 4,253 | $38.00 | $30.00 | $39.00 | $31.00 | $23.55 |
| 63 | Comb CC&G TM4.12 (60608562) | LF | 719 | $45.00 | $35.00 | $39.00 | $34.00 | $42.00 |
| 64 | Non SPL waste disposl (66900200) | CY | 3,327 | $85.00 | $70.00 | $110.00 | $85.22 | $80.00 |
| 65 | Soil disposal analy (66900530) | EACH | 5 | $1,170.00 | $1,170.00 | $1,350.00 | $1,520.00 | $1,300.00 |
| 66 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,400.00 | $3,800.00 | $2,800.00 | $3,000.00 |
| 67 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $550.00 | $2,400.00 | $2,000.00 |
| 68 | Reg sub mon (66901006) | CAL DAY | 6 | $700.00 | $700.00 | $900.00 | $1,000.00 | $1,450.00 |
| 69 | Mobilization (67100100) | LS | 1 | $162,000 | $167,000 | $45,000 | $175,359 | $188,000 |
| 70 | Changeable message SN (70107025) | CAL DAY | 30 | $50.00 | $50.00 | $60.00 | $35.00 | $35.00 |
| 71 | Short term pavt mking (70300100) | LF | 6,000 | $0.01 | $0.50 | $2.00 | $1.06 | $0.50 |
| 72 | SHRT TRM pavt MK rem (70300150) | SF | 2,000 | $0.01 | $1.00 | $3.00 | $1.69 | $0.25 |
| 73 | Temp PVT MK line 4 - paint (70300221) | LF | 16,321 | $0.01 | $0.30 | $0.35 | $0.35 | $0.35 |
| 74 | Temp PVT MK line 6 - paint (70300241) | LF | 100 | $1.00 | $6.00 | $7.00 | $0.53 | $0.53 |
| 75 | Temp PVT MK line 12 - paint (70300261) | LF | 492 | $2.50 | $2.25 | $2.75 | $1.06 | $1.06 |
| 76 | Temp PVT MK line 24 - paint (70300281) | LF | 107 | $5.00 | $8.00 | $9.00 | $1.60 | $1.60 |
| 77 | Sign panel T1 (72000100) | SF | 33 | $40.00 | $40.00 | $45.00 | $30.00 | $30.00 |
| 78 | Remov sign panel T1 (72400310) | SF | 17 | $20.00 | $40.00 | $45.00 | $28.00 | $28.00 |
| 79 | Reloc sign panel T1 (72400710) | SF | 10 | $20.00 | $75.00 | $85.00 | $110.00 | $110.00 |
| 80 | Teles STL sin support (72800100) | LF | 19 | $25.00 | $30.00 | $35.00 | $18.00 | $18.00 |
| 81 | RM rel GRND MNT S sup (73500300) | EACH | 1 | $750.00 | $1,200.00 | $1,400.00 | $1,000.00 | $250.00 |
| 82 | THPL PVT MK LTR & sym (78000100) | SF | 142 | $8.50 | $6.00 | $6.75 | $5.00 | $5.00 |
| 83 | THPL PVT MK line 4 (78000200) | LF | 2,603 | $1.00 | $1.20 | $1.38 | $1.25 | $1.25 |
| 84 | THPL PVT MK line 6 (78000400) | LF | 1,184 | $2.35 | $1.50 | $1.70 | $1.94 | $1.94 |
| 85 | THPL PVT MK line 12 (78000600) | LF | 1,171 | $3.55 | $3.00 | $3.40 | $3.88 | $3.88 |
| 86 | THPL PVT MK line 24 (78000650) | LF | 222 | $8.50 | $6.00 | $6.75 | $7.75 | $7.75 |
| 87 | PVT MKG rem grinding (78300201) | SF | 6,936 | $1.00 | $0.90 | $1.30 | $1.50 | $1.50 |
| 88 | Main EX TR sig instal (85000200) | EACH | 1 | $545.00 | $1,500.00 | $750.00 | $543.57 | $1,500.00 |
| 89 | Det loop T1 (88600100) | LF | 793 | $17.65 | $28.25 | $20.00 | $17.62 | $28.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way