IDOT contract 61L13 bid tabulation
Romeoville, section 24-00078-00-RS. Let by Illinois DOT on March 7, 2025, Will, District 01. 7 bids received; low bid $392,397 by P. T. Ferro Construction Co..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 47
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | P. T. Ferro Construction Co. | $392,397 | Low |
| 2 | Austin Tyler Construction, Inc. | $433,704 | +11% |
| 3 | Builders Paving, LLC | $456,202 | +16% |
| 4 | K-Five Construction Corporation | $460,556 | +17% |
| 5 | Schroeder Asphalt Services, Inc. | $482,817 | +23% |
| 6 | Gallagher Asphalt Corporation | $515,753 | +31% |
| 7 | Brothers Asphalt Paving, Inc. | $526,239 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. P. T. Ferro Construction Co. | 2. Austin Tyler Construction, Inc. | 3. Builders Paving, LLC | 4. K-Five Construction Corporation | 5. Schroeder Asphalt Services, Inc. | 6. Gallagher Asphalt Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Det loop repl (X8860105) | LF | 250 | $28.73 | $32.10 | $28.75 | $28.73 | $32.00 | $29.00 |
| 2 | Drain util STR adj (Z0017400) | EACH | 22 | $400.00 | $450.00 | $765.00 | $485.00 | $820.00 | $422.00 |
| 3 | Drain util STR recon (Z0017700) | EACH | 1 | $1,500.00 | $1,350.00 | $2,350.00 | $2,300.00 | $2,600.00 | $1,400.00 |
| 4 | Temp info signing (Z0030850) | SF | 25 | $30.00 | $18.00 | $30.00 | $30.00 | $33.00 | $30.00 |
| 5 | Supple watering (20101700) | UNIT | 18 | $0.01 | $0.01 | $20.00 | $20.00 | $22.00 | $0.01 |
| 6 | Topsoil F & P 4 (21101615) | SY | 385 | $5.12 | $5.12 | $9.25 | $9.25 | $10.15 | $5.20 |
| 7 | Seeding CL 1A (25000110) | ACRE | 0.25 | $3,750.00 | $3,750.00 | $3,000.00 | $3,000.00 | $3,400.00 | $3,800.00 |
| 8 | Nitrogen fert nutr (25000400) | LB | 10 | $3.00 | $3.00 | $3.00 | $3.00 | $3.30 | $3.00 |
| 9 | Phosphorus fert nutr (25000500) | LB | 10 | $3.00 | $3.00 | $3.00 | $3.00 | $3.30 | $3.00 |
| 10 | Potassium fert nutr (25000600) | LB | 10 | $3.00 | $3.00 | $3.00 | $3.00 | $3.30 | $3.00 |
| 11 | Erosion contr blanket (25100630) | SY | 385 | $15.25 | $15.25 | $4.00 | $4.00 | $5.00 | $15.30 |
| 12 | Inlet filters (28000510) | EACH | 23 | $0.01 | $90.00 | $200.00 | $260.00 | $215.00 | $189.00 |
| 13 | Agg base cse B 4 (35101600) | SY | 320 | $8.00 | $20.00 | $10.00 | $5.70 | $11.00 | $10.00 |
| 14 | Preparation of base (35800100) | SY | 275 | $0.01 | $5.00 | $12.00 | $1.00 | $4.50 | $0.01 |
| 15 | Agg base repair (35800200) | TON | 50 | $0.01 | $40.00 | $28.00 | $14.25 | $35.00 | $0.01 |
| 16 | Aggregate-temp access (40201000) | TON | 10 | $0.01 | $50.00 | $50.00 | $95.00 | $20.00 | $75.00 |
| 17 | Bit matls tack CT (40600290) | LB | 8,850 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 18 | Long joint sealant (40600370) | LF | 3,700 | $4.00 | $5.00 | $4.50 | $4.14 | $3.75 | $3.95 |
| 19 | Mix CR JTS flangewys (40600400) | TON | 20 | $0.01 | $445.00 | $200.00 | $50.00 | $300.00 | $50.00 |
| 20 | HMA surf rem butt JT (40600982) | SY | 315 | $0.01 | $0.01 | $15.00 | $1.00 | $8.00 | $20.00 |
| 21 | P HMA BC IL-4.75 N50 (40603200) | TON | 570 | $100.00 | $98.00 | $97.00 | $121.00 | $120.00 | $128.00 |
| 22 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,135 | $80.00 | $78.00 | $70.00 | $86.00 | $91.50 | $94.00 |
| 23 | PCC driveway pavt 6 (42300200) | SY | 110 | $90.00 | $85.00 | $103.50 | $107.00 | $105.00 | $95.00 |
| 24 | PC conc sidewalk 5 (42400200) | SF | 2,885 | $9.50 | $9.00 | $12.00 | $9.90 | $13.50 | $12.00 |
| 25 | Detectable warnings (42400800) | SF | 230 | $30.00 | $25.00 | $38.00 | $49.00 | $46.50 | $42.00 |
| 26 | HMA surf rem 2 (44000157) | SY | 13,110 | $2.50 | $3.00 | $4.00 | $3.20 | $2.15 | $3.60 |
| 27 | Drive pavement rem (44000200) | SY | 110 | $19.00 | $44.00 | $27.00 | $16.00 | $15.00 | $20.00 |
| 28 | Comb curb gutter rem (44000500) | LF | 1,250 | $10.00 | $8.00 | $14.35 | $10.85 | $14.50 | $13.00 |
| 29 | Sidewalk rem (44000600) | SF | 2,885 | $3.50 | $4.00 | $4.05 | $2.95 | $4.40 | $4.00 |
| 30 | CL D patch T1 7 (44201725) | SY | 5 | $115.00 | $60.00 | $175.00 | $21.00 | $80.00 | $600.00 |
| 31 | CL D patch T2 7 (44201729) | SY | 15 | $100.00 | $60.00 | $120.00 | $21.00 | $78.00 | $300.00 |
| 32 | CL D patch T3 7 (44201733) | SY | 25 | $100.00 | $60.00 | $80.00 | $21.00 | $75.00 | $255.00 |
| 33 | CL D patch T4 7 (44201735) | SY | 230 | $60.00 | $55.00 | $69.00 | $21.00 | $70.00 | $86.00 |
| 34 | Comb CC&G TB6.12 (60603800) | LF | 1,250 | $42.00 | $40.00 | $38.00 | $40.35 | $54.00 | $49.00 |
| 35 | Mobilization (67100100) | LS | 1 | $14,000 | $26,500 | $28,500 | $27,638 | $9,000.00 | $30,000 |
| 36 | TR cont & prot 701501 (70102620) | LS | 1 | $1,500.00 | $8,000.00 | $1,500.00 | $26,957 | $4,500.00 | $7,500.00 |
| 37 | TR cont & prot 701701 (70102635) | LS | 1 | $100.00 | $1.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 38 | TR cont & prot 701801 (70102640) | LS | 1 | $1,000.00 | $2,200.00 | $1,000.00 | $1,000.00 | $2,000.00 | $2,200.00 |
| 39 | Short term pavt mking (70300100) | LF | 85 | $0.01 | $4.50 | $5.00 | $1.00 | $10.00 | $2.00 |
| 40 | SHRT TRM pavt MK rem (70300150) | SF | 28 | $0.01 | $4.50 | $0.01 | $2.00 | $12.00 | $12.00 |
| 41 | Sign panel T1 (72000100) | SF | 18 | $37.50 | $32.00 | $25.00 | $37.50 | $40.00 | $37.50 |
| 42 | Teles STL sin support (72800100) | LF | 32 | $28.00 | $20.00 | $15.00 | $28.00 | $31.00 | $28.00 |
| 43 | THPL PVT MK LTR & sym (78000100) | SF | 110 | $5.85 | $5.75 | $6.00 | $6.00 | $7.50 | $6.00 |
| 44 | THPL PVT MK line 4 (78000200) | LF | 5,900 | $1.00 | $1.20 | $1.00 | $1.00 | $1.30 | $1.00 |
| 45 | THPL PVT MK line 6 (78000400) | LF | 730 | $1.35 | $1.40 | $1.25 | $1.25 | $2.00 | $1.50 |
| 46 | THPL PVT MK line 12 (78000600) | LF | 120 | $3.00 | $3.10 | $3.00 | $3.00 | $4.00 | $3.00 |
| 47 | THPL PVT MK line 24 (78000650) | LF | 245 | $5.85 | $5.00 | $6.00 | $6.00 | $8.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.