IDOT contract 61L74 bid tabulation

Hampshire, section 24-00021-00-SW. Let by Illinois DOT on September 19, 2025, Kane, District 01. 8 bids received; low bid $354,811 by Triggi Construction, Inc..

Owner
Illinois DOT
Letting
19 SEP 2025
Pay items
40
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Triggi Construction, Inc.$354,811Low
2Everlast Blacktop Inc.$523,898+48%
3Landmark Contractors, Inc.$526,619+48%
4Martam Construction Incorporated$542,502+53%
5Alliance Contractors, Inc.$554,612+56%
6Copenhaver Construction, Inc.$604,224+70%
7Acura Inc.$658,433+86%
8Davis Concrete Construction Co.$773,572+118%
IDOT contract 61L74: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Triggi Construction, Inc.2. Everlast Blacktop Inc.3. Landmark Contractors, Inc.4. Martam Construction Incorporated5. Alliance Contractors, Inc.6. Copenhaver Construction, Inc.
1HMA driveway pavt 3 (X4060280)SY267$50.00$45.00$90.00$64.48$87.00$67.00
2CC&G RMVL repl < = 10 (X4400501)LF38$55.00$97.00$140.40$87.96$94.00$150.00
3CC&G RMVL repl > 10FT (X4400503)LF280$42.00$62.00$85.00$61.28$94.00$51.00
4Sanitary manhole adj (X6026050)EACH3$750.00$950.00$1,250.00$1,356.49$1,500.00$1,400.00
5Tree trunk protection (20101100)EACH13$105.00$270.00$105.00$364.00$250.00$140.00
6Tree root pruning (20101200)EACH13$110.00$270.00$110.00$150.80$145.00$40.00
7Tree prun 1-10 (20101300)EACH2$50.00$160.00$50.00$182.00$175.00$50.00
8Tree prun over 10 (20101350)EACH11$100.00$330.00$100.00$234.00$225.00$60.00
9Earth excavation (20200100)CY764$45.00$36.00$66.45$57.95$40.00$55.00
10Topsoil F & P 4 (21101615)SY2,735$0.10$5.20$6.95$7.28$7.00$4.00
11Grading & shap ditch (21400100)LF50$15.00$20.00$12.70$23.19$20.00$50.00
12Seeding CL 2A (25000210)ACRE0.75$28,500$1,600.00$3,000.00$5,200.00$5,000.00$5,000.00
13Nitrogen fert nutr (25000400)LB68$5.00$1.00$5.00$3.12$3.00$1.00
14Phosphorus fert nutr (25000500)LB68$5.00$1.00$5.00$3.12$3.00$1.00
15Potassium fert nutr (25000600)LB68$5.00$1.00$5.00$3.12$3.00$1.00
16Erosion contr blanket (25100630)SY2,735$2.00$2.00$1.95$1.40$1.35$2.00
17Inlet filters (28000510)EACH4$150.00$200.00$175.00$234.00$250.00$200.00
18Agg base cse B (35101400)TON528$25.00$35.00$58.15$46.14$60.00$40.00
19Agg surf course TY B (40200800)TON1$100.00$35.00$485.00$312.97$200.00$300.00
20PCC driveway pavt 6 (42300200)SY133$60.00$112.00$85.50$124.04$100.00$130.00
21PC conc sidewalk 5 (42400200)SF21,345$6.25$10.75$7.65$9.08$10.00$12.00
22PC conc sidewalk 6 (42400300)SF2,730$7.25$12.00$8.65$10.09$11.00$13.00
23Detectable warnings (42400800)SF284$25.00$60.00$30.00$43.13$20.00$35.00
24Drive pavement rem (44000200)SY677$20.00$14.00$32.85$12.23$40.00$16.00
25Sidewalk rem (44000600)SF2,290$2.50$2.00$1.65$1.85$4.00$4.00
26CL D patch T1 2 (44201670)SY42$35.00$74.00$205.00$104.00$85.00$85.00
27CL D patch T2 2 (44201672)SY90$27.50$64.00$130.00$104.00$85.00$85.00
28CL D patch T4 2 (44201676)SY135$20.00$64.00$25.00$104.00$85.00$85.00
29Fire hydnts to BE rem (56400500)EACH1$1,250.00$1,200.00$5,125.00$791.46$6,000.00$3,000.00
30Fire hyd W/A V VB & T (56400825)EACH1$23,880$11,000$25,000$9,920.17$20,000$18,000
31Man adjust (60255500)EACH1$500.00$600.00$200.00$808.80$500.00$800.00
32Mobilization (67100100)LS1$7,500.00$22,560$54,000$32,550$34,228$40,000
33TR cont & prot 701501 (70102620)LS1$9,250.00$30,000$3,500.00$49,542$7,800.00$39,000
34TR cont & prot 701801 (70102640)LS1$1.00$1,200.00$1,200.00$1.04$1.00$100.00
35Sign panel T1 (72000100)SF34$36.00$42.00$40.00$27.04$26.00$33.00
36Remov sign panel T1 (72400310)SF36$10.00$33.00$30.00$15.60$15.00$31.00
37Reloc sin pan assy TA (72400500)EACH1$250.00$170.00$150.00$260.00$250.00$200.00
38Teles STL sin support (72800100)LF45$20.00$44.00$40.00$20.80$20.00$22.00
39THPL PVT MK line 12 (78000600)LF900$3.85$9.00$3.85$4.00$3.85$5.00
40THPL PVT MK line 24 (78000650)LF197$7.25$15.00$7.25$7.54$7.25$8.00
IDOT contract 61L74: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy