IDOT contract 62T22 bid tabulation
Section FAP. Let by Illinois DOT on June 13, 2025, Cook, District 01. 6 bids received; low bid $1,747,368 by Martam Construction Incorporated.
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 44
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martam Construction Incorporated | $1,747,368 | Low |
| 2 | Areatha Construction Co., Inc. | $1,754,826 | 0.0% |
| 3 | D. Construction, Inc. | $1,821,212 | +4.0% |
| 4 | MYS, Incorporated | $1,895,228 | +8.0% |
| 5 | Rausch Infrastructure, LLC | $1,992,308 | +14% |
| 6 | Lorig Construction Company | $2,097,385 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martam Construction Incorporated | 2. Areatha Construction Co., Inc. | 3. D. Construction, Inc. | 4. MYS, Incorporated | 5. Rausch Infrastructure, LLC | 6. Lorig Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | BR deck grooving long (X5030250) | SY | 1,996 | $7.00 | $6.55 | $7.04 | $9.72 | $9.00 | $7.50 |
| 2 | Struct steel repair (X5051206) | LB | 970 | $34.00 | $34.75 | $48.00 | $53.30 | $29.20 | $35.00 |
| 3 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,200.00 | $2,500.00 | $5,000.00 | $3,082.67 | $7,296.70 | $3,500.00 |
| 4 | Traf cont & prot SPL (X7010216) | LS | 1 | $141,000 | $24,950 | $61,500 | $38,386 | $30,314 | $185,000 |
| 5 | Temp info signing (X7200061) | SF | 340 | $26.00 | $25.00 | $16.50 | $16.20 | $30.30 | $25.00 |
| 6 | RRPM reflector removl (X7830050) | EACH | 12 | $10.00 | $5.00 | $20.00 | $37.81 | $6.00 | $5.00 |
| 7 | RRPM reflector replac (X7830052) | EACH | 12 | $25.00 | $40.00 | $44.00 | $54.01 | $60.70 | $100.00 |
| 8 | BR DK LTX C oly 2 3/4 (Z0006016) | SY | 2,994 | $118.00 | $122.30 | $125.00 | $118.29 | $112.00 | $120.00 |
| 9 | BR deck scar 3/4 (Z0012130) | SY | 2,994 | $46.00 | $60.95 | $50.00 | $49.10 | $48.30 | $54.00 |
| 10 | STR rep con DP = < 5 (Z0012754) | SF | 359 | $215.00 | $143.15 | $200.00 | $178.25 | $243.80 | $340.00 |
| 11 | STR rep con DP over 5 (Z0012755) | SF | 16 | $255.00 | $213.45 | $300.00 | $216.06 | $273.30 | $550.00 |
| 12 | Drainage STR cleaned (Z0018500) | EACH | 4 | $1,300.00 | $800.00 | $500.00 | $1,000.00 | $1,458.00 | $800.00 |
| 13 | Diamond grind BR sec (Z0029090) | SY | 2,661 | $8.00 | $10.25 | $8.95 | $11.02 | $9.20 | $9.00 |
| 14 | Temp pavemt var depth (Z0062458) | TON | 7 | $360.00 | $1.00 | $400.00 | $1,741.27 | $536.30 | $1,650.00 |
| 15 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 16 | Bit matls tack CT (40600290) | LB | 144 | $3.00 | $0.10 | $0.01 | $0.05 | $0.10 | $0.05 |
| 17 | Long joint sealant (40600370) | LF | 480 | $42.00 | $18.00 | $22.31 | $39.26 | $21.80 | $37.00 |
| 18 | HMA surf rem butt JT (40600982) | SY | 640 | $16.00 | $28.05 | $0.01 | $34.48 | $18.20 | $33.00 |
| 19 | HMA SC IL-9.5 D N70 (40604062) | TON | 62 | $588.00 | $425.00 | $150.00 | $623.67 | $516.30 | $600.00 |
| 20 | Protective coat (42001300) | SY | 3,292 | $1.00 | $2.40 | $1.00 | $3.58 | $7.20 | $2.25 |
| 21 | Pavement rem (44000100) | SY | 74.50 | $32.00 | $1.00 | $25.00 | $59.70 | $58.90 | $30.00 |
| 22 | Conc rem (50102400) | CY | 74.50 | $1,800.00 | $1,771.30 | $2,400.00 | $2,808.86 | $2,809.20 | $3,300.00 |
| 23 | Slope wall remov (50104650) | SY | 123 | $98.00 | $52.70 | $45.00 | $142.95 | $40.30 | $150.00 |
| 24 | Protective shield (50157300) | SY | 736 | $24.00 | $88.80 | $90.00 | $85.38 | $111.50 | $45.00 |
| 25 | Conc sup-STR (50300255) | CY | 87.10 | $2,400.00 | $2,634.35 | $2,600.00 | $3,457.05 | $3,297.90 | $2,900.00 |
| 26 | Reinf bars, epoxy CTD (50800205) | LB | 12,930 | $2.00 | $2.45 | $3.98 | $4.22 | $2.70 | $3.80 |
| 27 | Bar splicers (50800515) | EACH | 184 | $63.00 | $51.65 | $48.83 | $104.88 | $69.70 | $61.00 |
| 28 | Slope wall 4 (51100100) | SY | 123 | $234.00 | $181.30 | $100.00 | $172.67 | $273.30 | $190.00 |
| 29 | Pref JT strip seal (52000110) | LF | 549 | $245.00 | $370.50 | $240.00 | $226.07 | $294.90 | $280.00 |
| 30 | Concrete sealer (58700300) | SF | 1,475 | $3.00 | $2.30 | $2.00 | $3.31 | $2.40 | $5.00 |
| 31 | FR & grates adjust (60300105) | EACH | 4 | $500.00 | $850.00 | $800.00 | $564.61 | $1,097.70 | $2,000.00 |
| 32 | Mobilization (67100100) | LS | 1 | $100,000 | $105,000 | $103,087 | $64,352 | $119,000 | $120,000 |
| 33 | Changeable message SN (70107025) | CAL DAY | 126 | $44.00 | $40.00 | $33.00 | $34.57 | $48.60 | $40.00 |
| 34 | SHRT TRM pavt MK rem (70300150) | SF | 918 | $1.00 | $1.00 | $2.00 | $3.24 | $3.90 | $1.00 |
| 35 | Temp PVT MK L4 T4 tape (70307120) | LF | 13,346 | $1.30 | $1.25 | $1.38 | $1.40 | $1.50 | $1.25 |
| 36 | Temp conc barrier (70400100) | LF | 2,422 | $28.00 | $18.70 | $30.00 | $28.90 | $32.50 | $13.00 |
| 37 | Rel temp conc barrier (70400200) | LF | 2,422 | $4.00 | $6.55 | $15.00 | $3.24 | $3.60 | $2.00 |
| 38 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $6,000.00 | $5,950.00 | $6,000.00 | $4,861.48 | $7,229.20 | $6,000.00 |
| 39 | Imp attn rel FRN TL3 (70600332) | EACH | 2 | $2,000.00 | $1,850.00 | $2,200.00 | $2,160.66 | $2,247.70 | $1,900.00 |
| 40 | THPL PVT MK line 4 (78000200) | LF | 1,230 | $5.50 | $5.00 | $4.68 | $4.32 | $5.10 | $5.00 |
| 41 | Pref PL PM TD STD L 7 (78004635) | LF | 230 | $17.00 | $15.00 | $17.05 | $13.50 | $18.80 | $15.00 |
| 42 | Mod ureth PM line 4 (78009004) | LF | 1,780 | $6.60 | $6.00 | $3.25 | $3.78 | $3.50 | $6.00 |
| 43 | GRV RCSD PVT MRKG 8 (78011040) | LF | 1,654 | $1.60 | $1.50 | $3.08 | $3.24 | $3.40 | $1.50 |
| 44 | PVT MKG rem WTR blast (78300202) | SF | 2,532 | $3.00 | $3.00 | $3.85 | $1.89 | $3.60 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.