IDOT contract 62T27 bid tabulation
Section FAP. Let by Illinois DOT on April 25, 2025, Will, District 01. 5 bids received; low bid $1,260,740 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 104
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $1,260,740 | Low |
| 2 | Martam Construction Incorporated | $1,394,444 | +11% |
| 3 | Alliance Contractors, Inc. | $1,735,701 | +38% |
| 4 | Areatha Construction Co., Inc. | $1,751,824 | +39% |
| 5 | Rausch Infrastructure, LLC | $1,897,476 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Martam Construction Incorporated | 3. Alliance Contractors, Inc. | 4. Areatha Construction Co., Inc. | 5. Rausch Infrastructure, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 10 | $192.50 | $35.00 | $22.00 | $30.00 | $33.00 |
| 2 | Fiber wrap (X0325749) | SF | 41 | $137.50 | $85.00 | $160.00 | $75.00 | $84.00 |
| 3 | Seeding CL 4 mod (X2501800) | ACRE | 0.25 | $12,210 | $12,000 | $11,100 | $11,100 | $12,000 |
| 4 | BR deck grooving long (X5030250) | SY | 553 | $21.00 | $18.00 | $22.15 | $11.60 | $13.00 |
| 5 | Floor drains cleaned (X5030539) | EACH | 10 | $100.00 | $250.00 | $250.00 | $520.00 | $500.00 |
| 6 | Clean/paint bearings (X5060700) | EACH | 22 | $2,566.30 | $2,500.00 | $2,750.00 | $2,333.00 | $2,600.00 |
| 7 | FR & lids adjust SPL (X6030310) | EACH | 6 | $1,000.00 | $1,200.00 | $2,300.00 | $1,500.00 | $1,400.00 |
| 8 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $3,200.00 | $500.00 | $2,500.00 | $5,000.00 |
| 9 | Traf cont & prot SPL (X7010216) | LS | 1 | $25,000 | $110,325 | $58,325 | $35,000 | $60,000 |
| 10 | Temp info signing (X7200061) | SF | 95 | $30.00 | $20.00 | $19.00 | $20.00 | $22.00 |
| 11 | RRPM reflector removl (X7830050) | EACH | 149 | $10.00 | $7.00 | $6.00 | $10.00 | $11.00 |
| 12 | RRPM reflector replac (X7830052) | EACH | 149 | $24.20 | $24.00 | $22.00 | $17.55 | $19.00 |
| 13 | Appr slab repair (PD) (Z0001800) | SY | 6 | $1,000.00 | $1,500.00 | $3,695.00 | $1,122.90 | $2,000.00 |
| 14 | BR DK LTX C oly 2 3/4 (Z0006016) | SY | 588 | $135.00 | $145.00 | $320.00 | $334.60 | $240.00 |
| 15 | BR deck scar 3/4 (Z0012130) | SY | 588 | $60.00 | $63.00 | $196.50 | $204.05 | $180.00 |
| 16 | STR rep con DP = < 5 (Z0012754) | SF | 77 | $150.00 | $220.00 | $220.00 | $200.00 | $220.00 |
| 17 | Conc pavt scar (Z0012800) | SY | 512 | $12.00 | $29.00 | $33.22 | $45.85 | $27.00 |
| 18 | Deck slab rep (FD-T2) (Z0016002) | SY | 20 | $1,400.00 | $1,800.00 | $1,595.00 | $2,038.90 | $2,000.00 |
| 19 | Drill-grout bars (Z0018905) | EACH | 60 | $25.00 | $28.00 | $30.00 | $24.60 | $33.00 |
| 20 | Diamond grind BR sec (Z0029090) | SY | 542 | $33.00 | $31.00 | $33.65 | $36.85 | $26.00 |
| 21 | P P conc I-BM repair (Z0043800) | SF | 5 | $650.00 | $330.00 | $360.00 | $300.00 | $339.00 |
| 22 | Temp pavement (Z0062456) | SY | 49 | $75.00 | $122.00 | $331.70 | $300.00 | $674.00 |
| 23 | Temp pavemt var depth (Z0062458) | TON | 18 | $300.00 | $250.00 | $440.66 | $500.00 | $497.00 |
| 24 | Temp TR signal timing (Z0073510) | EACH | 1 | $660.00 | $1,000.00 | $600.00 | $975.00 | $678.00 |
| 25 | Earth excavation (20200100) | CY | 495 | $30.00 | $36.00 | $10.00 | $81.35 | $85.00 |
| 26 | Topsoil exc & plac (21101505) | CY | 9 | $100.00 | $122.00 | $120.00 | $303.00 | $1,100.00 |
| 27 | Supple watering (25200200) | UNIT | 4 | $27.50 | $50.00 | $25.00 | $25.00 | $28.00 |
| 28 | Inlet filters (28000510) | EACH | 10 | $302.50 | $280.00 | $25.00 | $275.00 | $310.00 |
| 29 | Stone riprap CL A7 (28100113) | SY | 171 | $150.00 | $135.00 | $165.00 | $106.80 | $164.00 |
| 30 | Agg subgrade impr 12 (30300112) | SY | 934 | $22.00 | $18.00 | $24.00 | $10.00 | $33.00 |
| 31 | Sub gran mat B 4 (31101200) | SY | 500 | $8.00 | $8.00 | $8.00 | $0.01 | $12.00 |
| 32 | Sub gran mat B 10 (31101800) | SY | 61 | $70.00 | $26.00 | $20.00 | $0.01 | $42.00 |
| 33 | HMA base cse 10 (35501324) | SY | 360 | $68.00 | $72.00 | $127.31 | $125.00 | $143.00 |
| 34 | Bit matls tack CT (40600290) | LB | 651 | $0.01 | $1.00 | $0.01 | $0.01 | $0.01 |
| 35 | Long joint sealant (40600370) | LF | 638 | $19.00 | $12.00 | $27.39 | $25.00 | $30.00 |
| 36 | HMA surf rem butt JT (40600982) | SY | 544 | $0.01 | $16.00 | $22.43 | $0.01 | $25.00 |
| 37 | HMA SC IL-9.5 D N70 (40604062) | TON | 162 | $110.00 | $155.00 | $276.60 | $225.00 | $312.00 |
| 38 | Protective coat (42001300) | SY | 538 | $2.00 | $1.00 | $0.01 | $2.45 | $5.00 |
| 39 | Pavement rem (44000100) | SY | 500 | $16.00 | $28.00 | $25.00 | $55.90 | $71.00 |
| 40 | Comb curb gutter rem (44000500) | LF | 1,177 | $10.00 | $8.00 | $15.00 | $16.30 | $24.00 |
| 41 | Median removal (44003100) | SF | 1,746 | $7.00 | $7.00 | $5.00 | $6.50 | $14.00 |
| 42 | Dowel bars 1 (44201297) | EACH | 60 | $25.00 | $35.00 | $30.00 | $31.20 | $80.00 |
| 43 | CL D patch T1 14 (44201811) | SY | 28 | $170.00 | $285.00 | $295.00 | $350.00 | $550.00 |
| 44 | CL D patch T2 14 (44201815) | SY | 28 | $170.00 | $275.00 | $295.00 | $300.00 | $550.00 |
| 45 | CL D patch T3 14 (44201819) | SY | 28 | $170.00 | $270.00 | $295.00 | $250.00 | $550.00 |
| 46 | CL D patch T4 14 (44201821) | SY | 28 | $170.00 | $268.00 | $295.00 | $200.00 | $550.00 |
| 47 | Conc rem (50102400) | CY | 27.40 | $2,500.00 | $1,800.00 | $4,950.00 | $3,500.00 | $2,600.00 |
| 48 | Conc struct (50300225) | CY | 2 | $3,000.00 | $5,500.00 | $4,435.00 | $4,637.85 | $4,500.00 |
| 49 | Conc sup-STR (50300255) | CY | 53.50 | $2,500.00 | $2,400.00 | $2,950.00 | $2,030.20 | $2,800.00 |
| 50 | Protective coat (50300300) | SY | 809 | $2.00 | $1.00 | $3.10 | $2.60 | $11.00 |
| 51 | Reinf bars, epoxy CTD (50800205) | LB | 13,740 | $2.50 | $3.00 | $2.48 | $2.45 | $2.00 |
| 52 | Bar splicers (50800515) | EACH | 32 | $60.00 | $63.00 | $75.00 | $69.15 | $160.00 |
| 53 | Drilled shaft in soil (51603000) | CY | 0.70 | $10,000 | $3,800.00 | $2,800.00 | $16,620 | $10,000 |
| 54 | Pref JT strip seal (52000110) | LF | 168 | $230.00 | $245.00 | $250.00 | $459.35 | $347.00 |
| 55 | Anchor bolts 1 1/4 (52100530) | EACH | 3 | $200.00 | $150.00 | $225.00 | $352.30 | $904.00 |
| 56 | Granular backfill STR (58600101) | CY | 1 | $500.00 | $550.00 | $130.00 | $759.00 | $919.00 |
| 57 | Concrete sealer (58700300) | SF | 2,701 | $1.00 | $3.00 | $6.00 | $2.35 | $1.50 |
| 58 | Epoxy crack injection (59000200) | LF | 18 | $100.00 | $66.00 | $120.00 | $60.00 | $67.00 |
| 59 | CB reconst (60252800) | EACH | 1 | $2,000.00 | $1,600.00 | $1,950.00 | $1,000.00 | $3,600.00 |
| 60 | FR & grates adjust (60300105) | EACH | 6 | $800.00 | $600.00 | $350.00 | $900.00 | $1,400.00 |
| 61 | FR & lids adjust (60300305) | EACH | 1 | $800.00 | $600.00 | $350.00 | $900.00 | $847.00 |
| 62 | Comb CC&G TB6.12 (60603800) | LF | 59 | $60.00 | $48.00 | $37.00 | $171.60 | $62.00 |
| 63 | Comb CC&G TY B-6.24 (60605000) | LF | 308 | $50.00 | $55.00 | $60.00 | $123.20 | $62.00 |
| 64 | Conc med TSB6.12 (60619600) | SF | 2,942 | $12.50 | $21.00 | $27.00 | $25.50 | $31.00 |
| 65 | Corrugated med (60624600) | SF | 1,030 | $20.00 | $18.00 | $25.00 | $25.55 | $31.00 |
| 66 | SPBGR TY A 9FT posts (63000003) | LF | 50 | $46.20 | $46.00 | $42.16 | $42.15 | $47.00 |
| 67 | Traf bar term T5 (63100070) | EACH | 2 | $1,320.00 | $1,400.00 | $1,219.00 | $1,219.00 | $1,377.00 |
| 68 | Traf bar term T6 (63100085) | EACH | 2 | $4,290.00 | $5,300.00 | $4,976.90 | $4,976.90 | $5,623.00 |
| 69 | TR bar TRM T1 SPL tan (63100167) | EACH | 2 | $3,630.00 | $3,700.00 | $3,437.00 | $3,437.00 | $3,883.00 |
| 70 | Guardrail remov (63200310) | LF | 247 | $11.00 | $11.00 | $9.83 | $9.85 | $11.00 |
| 71 | Non SPL waste disposl (66900200) | CY | 185 | $85.00 | $75.00 | $100.00 | $160.35 | $121.00 |
| 72 | Soil disposal analy (66900530) | EACH | 3 | $1,750.00 | $1,100.00 | $1,400.00 | $1,050.00 | $2,034.00 |
| 73 | Reg sub P-const plan (66901001) | LS | 1 | $2,250.00 | $5,000.00 | $3,700.00 | $4,550.00 | $3,164.00 |
| 74 | Reg sub F con report (66901003) | LS | 1 | $2,250.00 | $600.00 | $500.00 | $500.00 | $3,616.00 |
| 75 | Reg sub mon (66901006) | CAL DAY | 3 | $900.00 | $770.00 | $775.00 | $700.00 | $1,073.00 |
| 76 | Mobilization (67100100) | LS | 1 | $71,360 | $80,000 | $100,000 | $104,900 | $114,000 |
| 77 | Changeable message SN (70107025) | CAL DAY | 120 | $50.00 | $40.00 | $35.00 | $35.00 | $39.00 |
| 78 | Short term pavt mking (70300100) | LF | 9,848 | $0.50 | $1.00 | $1.00 | $1.00 | $1.10 |
| 79 | SHRT TRM pavt MK rem (70300150) | SF | 22,296 | $0.25 | $0.50 | $0.01 | $0.40 | $0.40 |
| 80 | Temp PVT MK LTR & sym T4 tape (70307100) | SF | 293 | $5.00 | $4.00 | $3.50 | $6.00 | $6.70 |
| 81 | Temp PVT MK L4 T4 tape (70307120) | LF | 51,198 | $1.00 | $1.30 | $1.20 | $1.00 | $1.10 |
| 82 | Temp PVT MK L6 T4 tape (70307130) | LF | 1,664 | $1.51 | $1.60 | $1.50 | $1.50 | $1.70 |
| 83 | Temp PVT MK L12 T4 tape (70307160) | LF | 570 | $3.00 | $3.80 | $3.50 | $3.00 | $3.30 |
| 84 | Temp PVT MK L24 T4 tape (70307210) | LF | 436 | $6.00 | $7.60 | $7.00 | $6.00 | $6.70 |
| 85 | Temp conc barrier (70400100) | LF | 1,013 | $30.00 | $28.00 | $32.95 | $65.00 | $47.00 |
| 86 | Rel temp conc barrier (70400200) | LF | 400 | $15.00 | $10.00 | $14.25 | $22.45 | $9.00 |
| 87 | Imp attn temp sun TL2 (70600275) | EACH | 3 | $12,000 | $5,200.00 | $4,883.00 | $6,500.00 | $5,500.00 |
| 88 | Imp attn rel S U TL2 (70600355) | EACH | 4 | $2,000.00 | $2,400.00 | $2,184.00 | $2,184.00 | $2,450.00 |
| 89 | Rem & rel sign panel asmbly TA (72400205) | EACH | 2 | $275.00 | $270.00 | $250.00 | $500.00 | $565.00 |
| 90 | Terminal marker - DA (72501000) | EACH | 2 | $22.00 | $40.00 | $35.00 | $35.00 | $39.00 |
| 91 | Teles STL sin support (72800100) | LF | 24 | $16.50 | $18.00 | $15.00 | $30.00 | $33.00 |
| 92 | THPL PVT MK LTR & sym (78000100) | SF | 182 | $6.33 | $6.00 | $5.75 | $6.65 | $7.50 |
| 93 | THPL PVT MK line 4 (78000200) | LF | 7,205 | $1.60 | $1.50 | $1.45 | $0.90 | $1.00 |
| 94 | THPL PVT MK line 6 (78000400) | LF | 1,080 | $1.89 | $1.80 | $1.72 | $1.50 | $1.70 |
| 95 | THPL PVT MK line 12 (78000600) | LF | 517 | $3.65 | $3.60 | $3.32 | $3.35 | $3.70 |
| 96 | THPL PVT MK line 24 (78000650) | LF | 164 | $6.33 | $6.00 | $5.75 | $6.65 | $7.50 |
| 97 | Pref PL PM TD STD L 7 (78004635) | LF | 43 | $71.50 | $70.00 | $65.00 | $30.85 | $34.80 |
| 98 | Mod ureth PM line 4 (78009004) | LF | 170 | $22.22 | $22.00 | $20.20 | $9.70 | $10.90 |
| 99 | Mod ureth PM line 6 (78009006) | LF | 86 | $25.30 | $25.00 | $23.00 | $14.55 | $16.40 |
| 100 | GRV RCSD PVT MRKG 8 (78011040) | LF | 43 | $36.30 | $37.00 | $33.00 | $20.95 | $23.60 |
| 101 | Raised refl pavt MKR (78100100) | EACH | 19 | $335.50 | $330.00 | $305.00 | $172.50 | $194.00 |
| 102 | Barr wall ref type C (78200011) | EACH | 114 | $7.70 | $8.00 | $7.00 | $13.25 | $6.00 |
| 103 | Raised ref PVT MK rem (78300200) | EACH | 10 | $20.00 | $30.00 | $95.00 | $20.00 | $16.00 |
| 104 | PVT MKG rem WTR blast (78300202) | SF | 1,310 | $3.50 | $3.00 | $2.75 | $2.75 | $3.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.