IDOT contract 62T27 bid tabulation

Section FAP. Let by Illinois DOT on April 25, 2025, Will, District 01. 5 bids received; low bid $1,260,740 by D. Construction, Inc..

Owner
Illinois DOT
Letting
25 APR 2025
Pay items
104
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$1,260,740Low
2Martam Construction Incorporated$1,394,444+11%
3Alliance Contractors, Inc.$1,735,701+38%
4Areatha Construction Co., Inc.$1,751,824+39%
5Rausch Infrastructure, LLC$1,897,476+51%
IDOT contract 62T27: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. Martam Construction Incorporated3. Alliance Contractors, Inc.4. Areatha Construction Co., Inc.5. Rausch Infrastructure, LLC
1Acrylic coating (X0325748)SY10$192.50$35.00$22.00$30.00$33.00
2Fiber wrap (X0325749)SF41$137.50$85.00$160.00$75.00$84.00
3Seeding CL 4 mod (X2501800)ACRE0.25$12,210$12,000$11,100$11,100$12,000
4BR deck grooving long (X5030250)SY553$21.00$18.00$22.15$11.60$13.00
5Floor drains cleaned (X5030539)EACH10$100.00$250.00$250.00$520.00$500.00
6Clean/paint bearings (X5060700)EACH22$2,566.30$2,500.00$2,750.00$2,333.00$2,600.00
7FR & lids adjust SPL (X6030310)EACH6$1,000.00$1,200.00$2,300.00$1,500.00$1,400.00
8Engrs FLD ofc TY A D1 (X6700407)CAL MO12$5,000.00$3,200.00$500.00$2,500.00$5,000.00
9Traf cont & prot SPL (X7010216)LS1$25,000$110,325$58,325$35,000$60,000
10Temp info signing (X7200061)SF95$30.00$20.00$19.00$20.00$22.00
11RRPM reflector removl (X7830050)EACH149$10.00$7.00$6.00$10.00$11.00
12RRPM reflector replac (X7830052)EACH149$24.20$24.00$22.00$17.55$19.00
13Appr slab repair (PD) (Z0001800)SY6$1,000.00$1,500.00$3,695.00$1,122.90$2,000.00
14BR DK LTX C oly 2 3/4 (Z0006016)SY588$135.00$145.00$320.00$334.60$240.00
15BR deck scar 3/4 (Z0012130)SY588$60.00$63.00$196.50$204.05$180.00
16STR rep con DP = < 5 (Z0012754)SF77$150.00$220.00$220.00$200.00$220.00
17Conc pavt scar (Z0012800)SY512$12.00$29.00$33.22$45.85$27.00
18Deck slab rep (FD-T2) (Z0016002)SY20$1,400.00$1,800.00$1,595.00$2,038.90$2,000.00
19Drill-grout bars (Z0018905)EACH60$25.00$28.00$30.00$24.60$33.00
20Diamond grind BR sec (Z0029090)SY542$33.00$31.00$33.65$36.85$26.00
21P P conc I-BM repair (Z0043800)SF5$650.00$330.00$360.00$300.00$339.00
22Temp pavement (Z0062456)SY49$75.00$122.00$331.70$300.00$674.00
23Temp pavemt var depth (Z0062458)TON18$300.00$250.00$440.66$500.00$497.00
24Temp TR signal timing (Z0073510)EACH1$660.00$1,000.00$600.00$975.00$678.00
25Earth excavation (20200100)CY495$30.00$36.00$10.00$81.35$85.00
26Topsoil exc & plac (21101505)CY9$100.00$122.00$120.00$303.00$1,100.00
27Supple watering (25200200)UNIT4$27.50$50.00$25.00$25.00$28.00
28Inlet filters (28000510)EACH10$302.50$280.00$25.00$275.00$310.00
29Stone riprap CL A7 (28100113)SY171$150.00$135.00$165.00$106.80$164.00
30Agg subgrade impr 12 (30300112)SY934$22.00$18.00$24.00$10.00$33.00
31Sub gran mat B 4 (31101200)SY500$8.00$8.00$8.00$0.01$12.00
32Sub gran mat B 10 (31101800)SY61$70.00$26.00$20.00$0.01$42.00
33HMA base cse 10 (35501324)SY360$68.00$72.00$127.31$125.00$143.00
34Bit matls tack CT (40600290)LB651$0.01$1.00$0.01$0.01$0.01
35Long joint sealant (40600370)LF638$19.00$12.00$27.39$25.00$30.00
36HMA surf rem butt JT (40600982)SY544$0.01$16.00$22.43$0.01$25.00
37HMA SC IL-9.5 D N70 (40604062)TON162$110.00$155.00$276.60$225.00$312.00
38Protective coat (42001300)SY538$2.00$1.00$0.01$2.45$5.00
39Pavement rem (44000100)SY500$16.00$28.00$25.00$55.90$71.00
40Comb curb gutter rem (44000500)LF1,177$10.00$8.00$15.00$16.30$24.00
41Median removal (44003100)SF1,746$7.00$7.00$5.00$6.50$14.00
42Dowel bars 1 (44201297)EACH60$25.00$35.00$30.00$31.20$80.00
43CL D patch T1 14 (44201811)SY28$170.00$285.00$295.00$350.00$550.00
44CL D patch T2 14 (44201815)SY28$170.00$275.00$295.00$300.00$550.00
45CL D patch T3 14 (44201819)SY28$170.00$270.00$295.00$250.00$550.00
46CL D patch T4 14 (44201821)SY28$170.00$268.00$295.00$200.00$550.00
47Conc rem (50102400)CY27.40$2,500.00$1,800.00$4,950.00$3,500.00$2,600.00
48Conc struct (50300225)CY2$3,000.00$5,500.00$4,435.00$4,637.85$4,500.00
49Conc sup-STR (50300255)CY53.50$2,500.00$2,400.00$2,950.00$2,030.20$2,800.00
50Protective coat (50300300)SY809$2.00$1.00$3.10$2.60$11.00
51Reinf bars, epoxy CTD (50800205)LB13,740$2.50$3.00$2.48$2.45$2.00
52Bar splicers (50800515)EACH32$60.00$63.00$75.00$69.15$160.00
53Drilled shaft in soil (51603000)CY0.70$10,000$3,800.00$2,800.00$16,620$10,000
54Pref JT strip seal (52000110)LF168$230.00$245.00$250.00$459.35$347.00
55Anchor bolts 1 1/4 (52100530)EACH3$200.00$150.00$225.00$352.30$904.00
56Granular backfill STR (58600101)CY1$500.00$550.00$130.00$759.00$919.00
57Concrete sealer (58700300)SF2,701$1.00$3.00$6.00$2.35$1.50
58Epoxy crack injection (59000200)LF18$100.00$66.00$120.00$60.00$67.00
59CB reconst (60252800)EACH1$2,000.00$1,600.00$1,950.00$1,000.00$3,600.00
60FR & grates adjust (60300105)EACH6$800.00$600.00$350.00$900.00$1,400.00
61FR & lids adjust (60300305)EACH1$800.00$600.00$350.00$900.00$847.00
62Comb CC&G TB6.12 (60603800)LF59$60.00$48.00$37.00$171.60$62.00
63Comb CC&G TY B-6.24 (60605000)LF308$50.00$55.00$60.00$123.20$62.00
64Conc med TSB6.12 (60619600)SF2,942$12.50$21.00$27.00$25.50$31.00
65Corrugated med (60624600)SF1,030$20.00$18.00$25.00$25.55$31.00
66SPBGR TY A 9FT posts (63000003)LF50$46.20$46.00$42.16$42.15$47.00
67Traf bar term T5 (63100070)EACH2$1,320.00$1,400.00$1,219.00$1,219.00$1,377.00
68Traf bar term T6 (63100085)EACH2$4,290.00$5,300.00$4,976.90$4,976.90$5,623.00
69TR bar TRM T1 SPL tan (63100167)EACH2$3,630.00$3,700.00$3,437.00$3,437.00$3,883.00
70Guardrail remov (63200310)LF247$11.00$11.00$9.83$9.85$11.00
71Non SPL waste disposl (66900200)CY185$85.00$75.00$100.00$160.35$121.00
72Soil disposal analy (66900530)EACH3$1,750.00$1,100.00$1,400.00$1,050.00$2,034.00
73Reg sub P-const plan (66901001)LS1$2,250.00$5,000.00$3,700.00$4,550.00$3,164.00
74Reg sub F con report (66901003)LS1$2,250.00$600.00$500.00$500.00$3,616.00
75Reg sub mon (66901006)CAL DAY3$900.00$770.00$775.00$700.00$1,073.00
76Mobilization (67100100)LS1$71,360$80,000$100,000$104,900$114,000
77Changeable message SN (70107025)CAL DAY120$50.00$40.00$35.00$35.00$39.00
78Short term pavt mking (70300100)LF9,848$0.50$1.00$1.00$1.00$1.10
79SHRT TRM pavt MK rem (70300150)SF22,296$0.25$0.50$0.01$0.40$0.40
80Temp PVT MK LTR & sym T4 tape (70307100)SF293$5.00$4.00$3.50$6.00$6.70
81Temp PVT MK L4 T4 tape (70307120)LF51,198$1.00$1.30$1.20$1.00$1.10
82Temp PVT MK L6 T4 tape (70307130)LF1,664$1.51$1.60$1.50$1.50$1.70
83Temp PVT MK L12 T4 tape (70307160)LF570$3.00$3.80$3.50$3.00$3.30
84Temp PVT MK L24 T4 tape (70307210)LF436$6.00$7.60$7.00$6.00$6.70
85Temp conc barrier (70400100)LF1,013$30.00$28.00$32.95$65.00$47.00
86Rel temp conc barrier (70400200)LF400$15.00$10.00$14.25$22.45$9.00
87Imp attn temp sun TL2 (70600275)EACH3$12,000$5,200.00$4,883.00$6,500.00$5,500.00
88Imp attn rel S U TL2 (70600355)EACH4$2,000.00$2,400.00$2,184.00$2,184.00$2,450.00
89Rem & rel sign panel asmbly TA (72400205)EACH2$275.00$270.00$250.00$500.00$565.00
90Terminal marker - DA (72501000)EACH2$22.00$40.00$35.00$35.00$39.00
91Teles STL sin support (72800100)LF24$16.50$18.00$15.00$30.00$33.00
92THPL PVT MK LTR & sym (78000100)SF182$6.33$6.00$5.75$6.65$7.50
93THPL PVT MK line 4 (78000200)LF7,205$1.60$1.50$1.45$0.90$1.00
94THPL PVT MK line 6 (78000400)LF1,080$1.89$1.80$1.72$1.50$1.70
95THPL PVT MK line 12 (78000600)LF517$3.65$3.60$3.32$3.35$3.70
96THPL PVT MK line 24 (78000650)LF164$6.33$6.00$5.75$6.65$7.50
97Pref PL PM TD STD L 7 (78004635)LF43$71.50$70.00$65.00$30.85$34.80
98Mod ureth PM line 4 (78009004)LF170$22.22$22.00$20.20$9.70$10.90
99Mod ureth PM line 6 (78009006)LF86$25.30$25.00$23.00$14.55$16.40
100GRV RCSD PVT MRKG 8 (78011040)LF43$36.30$37.00$33.00$20.95$23.60
101Raised refl pavt MKR (78100100)EACH19$335.50$330.00$305.00$172.50$194.00
102Barr wall ref type C (78200011)EACH114$7.70$8.00$7.00$13.25$6.00
103Raised ref PVT MK rem (78300200)EACH10$20.00$30.00$95.00$20.00$16.00
104PVT MKG rem WTR blast (78300202)SF1,310$3.50$3.00$2.75$2.75$3.10
IDOT contract 62T27: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy