IDOT contract 66N22 bid tabulation
Section (3)CR-2514. Let by Illinois DOT on February 27, 2026, Kendall, District 03. 4 bids received; low bid $199,416 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 42
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $199,416 | Low |
| 2 | Austin Tyler Construction, Inc. | $214,746 | +8.0% |
| 3 | Gillan Construction LLC | $221,731 | +11% |
| 4 | Performance Construction and Engineering, LLC | $249,020 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. | 3. Gillan Construction LLC | 4. Performance Construction and Engineering, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Fill exist culverts (X6050208) | CY | 44 | $400.00 | $376.00 | $442.00 | $525.00 |
| 2 | Delineator removal (X6350120) | EACH | 1 | $50.00 | $25.00 | $25.00 | $15.00 |
| 3 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $5,440.00 | $5,000.00 | $13,000 |
| 4 | Earth excavation (20200100) | CY | 150 | $50.00 | $150.00 | $43.00 | $30.00 |
| 5 | Furnished excavation (20400800) | CY | 600 | $30.00 | $37.00 | $57.00 | $44.00 |
| 6 | Trench backfill (20800150) | CY | 11 | $65.00 | $44.00 | $80.00 | $120.00 |
| 7 | Seeding CL 2A (25000210) | ACRE | 0.75 | $1,331.00 | $1,210.00 | $5,879.00 | $2,200.00 |
| 8 | Nitrogen fert nutr (25000400) | LB | 68 | $3.30 | $3.00 | $5.50 | $5.00 |
| 9 | Phosphorus fert nutr (25000500) | LB | 68 | $3.30 | $3.00 | $5.50 | $5.00 |
| 10 | Potassium fert nutr (25000600) | LB | 68 | $3.30 | $3.00 | $5.50 | $5.00 |
| 11 | Erosion contr blanket (25100630) | SY | 2,910 | $3.30 | $3.00 | $2.20 | $2.00 |
| 12 | Temp ditch checks (28000305) | LF | 149 | $22.00 | $20.00 | $15.00 | $15.00 |
| 13 | Inlet & pipe protect (28000500) | EACH | 5 | $220.00 | $150.00 | $250.00 | $200.00 |
| 14 | Stone riprap CL A3 (28100105) | SY | 20 | $100.00 | $91.00 | $80.00 | $100.00 |
| 15 | Filter fabric (28200200) | SY | 20 | $10.00 | $4.00 | $3.50 | $15.00 |
| 16 | CL D patch T3 10 (44201769) | SY | 17 | $175.00 | $295.00 | $300.00 | $135.00 |
| 17 | Agg wedge SHLD type B (48102100) | TON | 14 | $55.00 | $182.00 | $200.00 | $100.00 |
| 18 | Conc headwall removal (50104400) | EACH | 4 | $2,000.00 | $704.00 | $1,700.00 | $4,000.00 |
| 19 | Pipe culvert remov (50105220) | LF | 48 | $50.00 | $133.00 | $20.00 | $35.00 |
| 20 | P cul CL A 2 30 (542A1075) | LF | 49 | $195.00 | $153.00 | $220.00 | $200.00 |
| 21 | P cul CL D 1 30 (542D0235) | LF | 114 | $245.00 | $147.00 | $160.00 | $140.00 |
| 22 | P cul CL D 2 15 (542D1060) | LF | 22 | $157.00 | $116.00 | $132.00 | $130.00 |
| 23 | PRC flar end sec 30 (54213675) | EACH | 1 | $3,000.00 | $3,088.00 | $2,000.00 | $2,500.00 |
| 24 | Metal FL end sec 15" (54262715) | EACH | 1 | $500.00 | $800.00 | $550.00 | $350.00 |
| 25 | Metal FL end sec 30" (54262730) | EACH | 1 | $1,600.00 | $1,300.00 | $1,500.00 | $800.00 |
| 26 | Insert cul lin 36 (54390230) | LF | 62 | $100.00 | $355.00 | $230.00 | $375.00 |
| 27 | Man TA 6 dia T1F CL (60223800) | EACH | 1 | $8,540.00 | $5,990.00 | $6,500.00 | $5,000.00 |
| 28 | Guardrail remov (63200310) | LF | 576 | $10.00 | $10.58 | $11.00 | $10.00 |
| 29 | Delineators (63500105) | EACH | 2 | $137.50 | $95.00 | $100.00 | $65.00 |
| 30 | Non SPL waste disposl (66900200) | CY | 116 | $100.00 | $0.01 | $110.00 | $65.00 |
| 31 | Soil disposal analy (66900530) | EACH | 2 | $1,815.00 | $1,450.00 | $1,900.00 | $2,900.00 |
| 32 | Reg sub P-const plan (66901001) | LS | 1 | $2,475.00 | $2,400.00 | $2,500.00 | $2,400.00 |
| 33 | Reg sub F con report (66901003) | LS | 1 | $2,475.00 | $2,400.00 | $2,000.00 | $2,400.00 |
| 34 | Reg sub mon (66901006) | CAL DAY | 4 | $800.00 | $0.01 | $1,300.00 | $1,200.00 |
| 35 | Mobilization (67100100) | LS | 1 | $11,000 | $12,500 | $12,500 | $14,760 |
| 36 | Traf cont-prot 701201 (70100450) | LS | 1 | $15,000 | $23,500 | $10,000 | $32,000 |
| 37 | Traf cont-prot 701206 (70100455) | LS | 1 | $0.01 | $0.01 | $6,500.00 | $2,500.00 |
| 38 | Night work zone light (70200100) | LS | 1 | $0.01 | $0.01 | $0.02 | $1,000.00 |
| 39 | Sign panel T1 (72000100) | SF | 20 | $27.50 | $90.00 | $50.00 | $155.00 |
| 40 | Remov sin pan assy TA (72400100) | EACH | 2 | $93.50 | $300.00 | $400.00 | $300.00 |
| 41 | Remov sign panel T1 (72400310) | SF | 6 | $55.00 | $30.00 | $50.00 | $55.00 |
| 42 | Wood sin support (73000100) | LF | 47 | $27.50 | $50.00 | $50.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.