IDOT contract 66P51 bid tabulation
Section (92)RS-4. Let by Illinois DOT on March 7, 2025, Grundy, District 03. 4 bids received; low bid $680,856 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 45
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $680,856 | Low |
| 2 | Austin Tyler Construction, Inc. | $811,495 | +19% |
| 3 | P. T. Ferro Construction Co. | $864,641 | +27% |
| 4 | Gallagher Asphalt Corporation | $893,941 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. | 3. P. T. Ferro Construction Co. | 4. Gallagher Asphalt Corporation |
|---|---|---|---|---|---|---|---|
| 1 | Furnished excav SPL (X2040805) | CY | 50 | $75.00 | $115.00 | $50.00 | $125.00 |
| 2 | HMA surf rem var DP (X4401198) | SY | 1,643 | $4.00 | $12.00 | $0.01 | $12.00 |
| 3 | Temp info signing (Z0030850) | SF | 42 | $25.00 | $25.00 | $25.00 | $26.00 |
| 4 | Earth excavation (20200100) | CY | 18 | $100.00 | $135.00 | $40.00 | $49.00 |
| 5 | Trench backfill (20800150) | CY | 20 | $242.00 | $135.00 | $90.00 | $220.00 |
| 6 | Grading & shap ditch (21400100) | LF | 760 | $15.00 | $17.00 | $12.00 | $22.00 |
| 7 | Seeding CL 2A (25000210) | ACRE | 0.50 | $6,600.00 | $3,500.00 | $15,000 | $1,210.00 |
| 8 | Nitrogen fert nutr (25000400) | LB | 40 | $5.50 | $3.00 | $3.00 | $3.00 |
| 9 | Phosphorus fert nutr (25000500) | LB | 40 | $5.50 | $33.00 | $3.00 | $3.00 |
| 10 | Potassium fert nutr (25000600) | LB | 40 | $5.50 | $3.00 | $3.00 | $3.00 |
| 11 | Erosion contr blanket (25100630) | SY | 1,940 | $5.50 | $1.50 | $2.00 | $8.00 |
| 12 | Agg surf course TY B (40200800) | TON | 11 | $60.00 | $125.00 | $100.00 | $125.00 |
| 13 | Bit matls tack CT (40600290) | LB | 10,800 | $0.01 | $0.01 | $0.01 | $0.01 |
| 14 | Long joint sealant (40600370) | LF | 6,096 | $3.55 | $3.70 | $3.65 | $3.40 |
| 15 | Mix CR JTS flangewys (40600400) | TON | 5 | $300.00 | $350.00 | $600.00 | $800.00 |
| 16 | Matl transfer device (40600405) | TON | 3,129 | $5.00 | $4.00 | $3.00 | $3.60 |
| 17 | Temporary ramp (40600990) | SY | 282 | $0.01 | $0.01 | $0.01 | $31.50 |
| 18 | HMA BC IL-19.0 N50 (40603080) | TON | 1,877 | $71.00 | $74.00 | $95.00 | $88.00 |
| 19 | HMA SC IL-9.5 C N50 (40604050) | TON | 1,252 | $78.65 | $79.00 | $100.00 | $96.00 |
| 20 | Incidental HMA surf (40800050) | TON | 242 | $120.00 | $120.00 | $95.00 | $170.00 |
| 21 | HMA surf rem 3 3/4 (44000164) | SY | 14,897 | $3.10 | $4.30 | $7.00 | $3.80 |
| 22 | CL A patch T2 13 (44200610) | SY | 303 | $140.00 | $330.00 | $320.00 | $350.00 |
| 23 | CL A patch T3 13 (44200612) | SY | 36 | $140.00 | $315.00 | $320.00 | $350.00 |
| 24 | CL A patch T4 13 (44200614) | SY | 182 | $140.00 | $305.00 | $310.00 | $350.00 |
| 25 | Patch reinforcement (44213000) | SY | 521 | $75.00 | $22.00 | $55.00 | $60.00 |
| 26 | Saw cuts (44213200) | LF | 1,316 | $5.00 | $11.00 | $0.01 | $0.01 |
| 27 | Tie bars 1 (44213202) | EACH | 789 | $20.00 | $30.00 | $0.01 | $0.01 |
| 28 | Tie bars 3/4 (44213204) | EACH | 56 | $20.00 | $18.00 | $0.01 | $0.01 |
| 29 | Agg wedge SHLD type B (48102100) | TON | 434 | $50.00 | $43.00 | $50.00 | $54.00 |
| 30 | Conc headwall removal (50104400) | EACH | 6 | $275.00 | $550.00 | $500.00 | $250.00 |
| 31 | Pipe culvert remov (50105220) | LF | 192 | $20.74 | $55.85 | $40.00 | $19.00 |
| 32 | P cul CL A 1 eqrs 18 (542A5473) | LF | 212 | $145.92 | $120.00 | $150.00 | $138.00 |
| 33 | PRC FL end S EQ RS 18 (54214503) | EACH | 8 | $1,534.50 | $1,550.00 | $1,500.00 | $1,450.00 |
| 34 | Delineators (63500105) | EACH | 6 | $55.00 | $250.00 | $150.00 | $155.00 |
| 35 | Perm surv MKRS T1 (66700205) | EACH | 1 | $1,000.00 | $1,000.00 | $3,500.00 | $1,600.00 |
| 36 | Engr field office A (67000400) | CAL MO | 2 | $4,000.00 | $5,000.00 | $4,500.00 | $3,800.00 |
| 37 | Mobilization (67100100) | LS | 1 | $40,850 | $48,000 | $30,000 | $52,000 |
| 38 | Traf cont-prot 701201 (70100450) | LS | 1 | $0.01 | $1,000.00 | $6,395.00 | $8,000.00 |
| 39 | Traf cont-prot 701306 (70100460) | LS | 1 | $7,500.00 | $1,000.00 | $100.00 | $100.00 |
| 40 | Traf cont-prot 701336 (70100600) | LS | 1 | $0.01 | $4,750.00 | $12,100 | $13,000 |
| 41 | Short term pavt mking (70300100) | LF | 1,717 | $0.01 | $2.00 | $2.00 | $5.00 |
| 42 | SHRT TRM pavt MK rem (70300150) | SF | 574 | $0.01 | $3.00 | $2.00 | $0.01 |
| 43 | Mod ureth PM line 4 (78009004) | LF | 25,136 | $0.72 | $0.65 | $0.92 | $0.65 |
| 44 | Mod ureth PM line 6 (78009006) | LF | 3,146 | $0.99 | $2.25 | $1.50 | $0.90 |
| 45 | Raised refl pavt MKR (78100100) | EACH | 81 | $66.00 | $95.00 | $85.00 | $60.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.