IDOT contract 80B36 bid tabulation
Section 2025-1088-RS. Let by Illinois DOT on January 16, 2026, Will, District 01. 6 bids received; low bid $3,250,096 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 102
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $3,250,096 | Low |
| 2 | Gallagher Asphalt Corporation | $3,301,161 | +2.0% |
| 3 | Iroquois Paving Corporation | $3,394,876 | +4.0% |
| 4 | P. T. Ferro Construction Co. | $3,427,677 | +5.0% |
| 5 | K-Five Construction Corporation | $3,886,655 | +20% |
| 6 | Austin Tyler Construction, Inc. | $4,069,252 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Gallagher Asphalt Corporation | 3. Iroquois Paving Corporation | 4. P. T. Ferro Construction Co. | 5. K-Five Construction Corporation | 6. Austin Tyler Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Tree care (K0026700) | EACH | 20 | $220.00 | $980.00 | $950.00 | $300.00 | $210.00 | $900.00 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $10,000 | $2,500.00 | $8,400.00 | $32,356 | $10,000 | $19,000 |
| 3 | Ped signal post 5 FT (X1400378) | EACH | 22 | $1,372.29 | $1,480.00 | $1,275.00 | $1,204.23 | $1,300.00 | $2,100.00 |
| 4 | Tree remov acres SPL (X2010350) | ACRE | 0.20 | $38,500 | $10,350 | $21,135 | $20,000 | $9,500.00 | $20,000 |
| 5 | Selective clearing (X2010516) | UNIT | 18.30 | $715.00 | $250.00 | $423.00 | $400.00 | $230.00 | $400.00 |
| 6 | Prun safety/equip CLR (X2100002) | UNIT | 4 | $1,028.50 | $136.00 | $1,055.00 | $1,000.00 | $125.00 | $1,000.00 |
| 7 | PCC surf rem var DP (X4400100) | SY | 11,311 | $2.00 | $3.40 | $4.00 | $2.20 | $7.00 | $3.70 |
| 8 | CC&G RMVL repl < = 10 (X4400501) | LF | 270 | $65.00 | $90.00 | $145.00 | $95.00 | $60.00 | $105.00 |
| 9 | CC&G RMVL repl > 10FT (X4400503) | LF | 90 | $60.00 | $66.70 | $115.00 | $80.00 | $60.00 | $66.50 |
| 10 | SS cleaned 12 (X5537800) | LF | 480 | $1.10 | $1.10 | $3.70 | $1.00 | $1.00 | $50.00 |
| 11 | FR & lids adjust SPL (X6030310) | EACH | 20 | $1,000.00 | $860.00 | $1,600.00 | $0.01 | $1,385.00 | $1,500.00 |
| 12 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $5,000.00 | $3,500.00 | $3,000.00 | $2,500.00 | $3,500.00 | $3,000.00 |
| 13 | Temp info signing (X7200061) | SF | 411 | $30.00 | $32.70 | $32.00 | $15.00 | $30.00 | $30.00 |
| 14 | Accessible ped signal (X8760200) | EACH | 36 | $2,127.31 | $2,300.00 | $2,010.00 | $1,901.44 | $2,000.00 | $2,300.00 |
| 15 | Conc FDN TY A 12D (X8780012) | LF | 88 | $348.39 | $418.00 | $312.00 | $295.06 | $365.00 | $525.00 |
| 16 | Drainage STR cleaned (Z0018500) | EACH | 132 | $363.00 | $360.00 | $528.00 | $330.00 | $330.00 | $500.00 |
| 17 | RE-optimize TR sig sys 1 (Z0033044) | EACH | 5 | $726.00 | $606.00 | $698.00 | $660.00 | $325.00 | $1,000.00 |
| 18 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 19 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 20 | Tree remov over 15 (20100210) | UNIT | 21.70 | $55.00 | $27.20 | $40.00 | $38.00 | $25.00 | $38.00 |
| 21 | Tree prun 1-10 (20101300) | EACH | 10 | $165.00 | $54.40 | $79.50 | $75.00 | $50.00 | $75.00 |
| 22 | Tree prun over 10 (20101350) | EACH | 10 | $247.50 | $109.00 | $158.00 | $150.00 | $100.00 | $150.00 |
| 23 | Earth excavation (20200100) | CY | 45 | $100.00 | $115.00 | $113.00 | $175.00 | $65.00 | $90.00 |
| 24 | Topsoil F & P 4 (21101615) | SY | 150 | $17.60 | $5.50 | $5.25 | $15.00 | $35.00 | $5.00 |
| 25 | Sodding salt tolerant (25200110) | SY | 150 | $53.90 | $109.00 | $105.00 | $25.00 | $7.50 | $100.00 |
| 26 | Sub gran mat B (31101000) | TON | 740 | $35.00 | $34.00 | $49.00 | $45.00 | $50.00 | $75.00 |
| 27 | HMA base cse 8 (35501316) | SY | 3 | $750.00 | $241.00 | $250.00 | $500.00 | $750.00 | $80.00 |
| 28 | Bit matls tack CT (40600290) | LB | 12,966 | $0.01 | $1.15 | $1.75 | $5.00 | $3.95 | $0.01 |
| 29 | Long joint sealant (40600370) | LF | 18,784 | $4.07 | $3.30 | $3.75 | $3.75 | $2.79 | $3.30 |
| 30 | Mix CR JTS flangewys (40600400) | TON | 84 | $0.01 | $50.00 | $0.01 | $450.00 | $50.00 | $315.00 |
| 31 | HMA surf rem butt JT (40600982) | SY | 79 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $20.00 |
| 32 | PCC surf rem butt JT (40600985) | SY | 1,913 | $7.00 | $0.01 | $18.00 | $0.01 | $0.01 | $20.00 |
| 33 | P HMA BC IL-4.75 N50 (40603200) | TON | 3,054 | $98.00 | $105.00 | $127.00 | $107.00 | $115.00 | $98.00 |
| 34 | HMA SC IL-9.5 D N50 (40604060) | TON | 1 | $1,000.00 | $760.00 | $300.00 | $500.00 | $750.00 | $1,000.00 |
| 35 | P HMA SC IL-9.5 E N70 (40604172) | TON | 5,465 | $97.00 | $104.00 | $130.00 | $112.00 | $130.90 | $107.00 |
| 36 | Protective coat (42001300) | SY | 9,898 | $1.00 | $0.01 | $2.25 | $0.01 | $1.00 | $2.00 |
| 37 | PCC driveway pavt 8 (42300400) | SY | 9 | $200.00 | $290.00 | $250.00 | $500.00 | $110.00 | $150.00 |
| 38 | PC conc sidewalk 5 (42400200) | SF | 4,054 | $7.50 | $8.60 | $8.00 | $12.00 | $10.00 | $11.50 |
| 39 | Detectable warnings (42400800) | SF | 422 | $35.00 | $38.00 | $17.00 | $20.00 | $30.00 | $40.00 |
| 40 | HMA surf rem 2 1/2 (44000159) | SY | 935 | $4.00 | $9.30 | $21.00 | $7.25 | $10.00 | $14.00 |
| 41 | Drive pavement rem (44000200) | SY | 11 | $20.00 | $180.00 | $100.00 | $100.00 | $18.00 | $45.00 |
| 42 | Comb curb gutter rem (44000500) | LF | 10,268 | $7.00 | $16.50 | $5.75 | $7.40 | $12.00 | $14.00 |
| 43 | Sidewalk rem (44000600) | SF | 3,980 | $3.00 | $4.20 | $2.15 | $2.20 | $2.50 | $3.70 |
| 44 | Median removal (44003100) | SF | 51,067 | $2.50 | $2.20 | $2.25 | $1.40 | $4.00 | $2.10 |
| 45 | CL D patch T2 10 (44201765) | SY | 467 | $110.00 | $225.00 | $0.01 | $120.00 | $96.00 | $145.00 |
| 46 | CL D patch T3 10 (44201769) | SY | 300 | $110.00 | $165.00 | $0.01 | $97.00 | $96.00 | $135.00 |
| 47 | CL D patch T4 10 (44201771) | SY | 297 | $110.00 | $130.00 | $0.01 | $86.00 | $96.00 | $130.00 |
| 48 | CB adjust (60250200) | EACH | 2 | $900.00 | $380.00 | $950.00 | $500.00 | $525.00 | $400.00 |
| 49 | CB reconst (60252800) | EACH | 2 | $2,500.00 | $1,420.00 | $5,200.00 | $1,000.00 | $1,650.00 | $4,000.00 |
| 50 | Man adjust (60255500) | EACH | 3 | $1,000.00 | $350.00 | $950.00 | $1,000.00 | $650.00 | $425.00 |
| 51 | Man reconst (60257900) | EACH | 2 | $2,500.00 | $1,420.00 | $5,200.00 | $1,500.00 | $1,850.00 | $2,000.00 |
| 52 | FR & grates adjust (60300105) | EACH | 36 | $600.00 | $275.00 | $950.00 | $375.00 | $525.00 | $425.00 |
| 53 | FR & lids adjust (60300305) | EACH | 22 | $900.00 | $275.00 | $950.00 | $375.00 | $525.00 | $425.00 |
| 54 | FR & grates T24 (60404950) | EACH | 2 | $650.00 | $450.00 | $700.00 | $550.00 | $685.00 | $425.00 |
| 55 | FR & lids T1 OL (60406000) | EACH | 5 | $650.00 | $380.00 | $700.00 | $500.00 | $550.00 | $150.00 |
| 56 | FR & lids T1 CL (60406100) | EACH | 4 | $650.00 | $380.00 | $650.00 | $500.00 | $550.00 | $150.00 |
| 57 | Comb CC&G TY B-6.24 (60605000) | LF | 1,300 | $42.00 | $40.00 | $50.25 | $45.50 | $48.00 | $53.00 |
| 58 | Comb CC&G TM4.24 (60608582) | LF | 8,968 | $34.00 | $33.00 | $33.00 | $45.50 | $46.50 | $35.80 |
| 59 | Conc median surf 6 (60618320) | SF | 40,947 | $7.25 | $5.60 | $5.00 | $7.20 | $8.00 | $8.50 |
| 60 | Conc med TSB6.12 (60619600) | SF | 2,884 | $20.00 | $17.60 | $25.75 | $21.50 | $22.00 | $25.00 |
| 61 | Conc med TSM6.12 (60622800) | SF | 10,322 | $17.00 | $15.30 | $24.25 | $21.50 | $22.00 | $25.00 |
| 62 | Non SPL waste disposl (66900200) | CY | 45 | $100.00 | $107.00 | $55.00 | $100.00 | $100.00 | $200.00 |
| 63 | Soil disposal analy (66900530) | EACH | 1 | $1,750.00 | $1,578.00 | $1,900.00 | $3,950.00 | $1,400.00 | $1,875.00 |
| 64 | Reg sub P-const plan (66901001) | LS | 1 | $2,250.00 | $3,374.00 | $3,600.00 | $3,100.00 | $3,200.00 | $3,400.00 |
| 65 | Reg sub F con report (66901003) | LS | 1 | $2,250.00 | $1,306.00 | $2,540.00 | $1,200.00 | $1,300.00 | $500.00 |
| 66 | Reg sub mon (66901006) | CAL DAY | 5 | $1,000.00 | $740.00 | $1,430.00 | $680.00 | $680.00 | $770.00 |
| 67 | Mobilization (67100100) | LS | 1 | $100,000 | $195,000 | $105,000 | $205,600 | $233,000 | $240,000 |
| 68 | TR cont & prot 701606 (70102625) | LS | 1 | $0.01 | $19,436 | $18,755 | $3,388.00 | $88,190 | $200,000 |
| 69 | TR cont & prot 701601 (70102630) | LS | 1 | $132,899 | $109.00 | $106.00 | $3,388.00 | $100.00 | $100.00 |
| 70 | TR cont & prot 701602 (70102632) | LS | 1 | $0.01 | $109.00 | $106.00 | $3,388.00 | $100.00 | $100.00 |
| 71 | TR cont & prot 701701 (70102635) | LS | 1 | $0.01 | $272.00 | $265.00 | $3,388.00 | $250.00 | $250.00 |
| 72 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $272.00 | $265.00 | $3,388.00 | $250.00 | $250.00 |
| 73 | Short term pavt mking (70300100) | LF | 16,353 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $1.50 |
| 74 | SHRT TRM pavt MK rem (70300150) | SF | 13,562 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $2.50 |
| 75 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,281 | $0.01 | $0.01 | $0.01 | $1.75 | $0.01 | $2.15 |
| 76 | Temp PVT MK line 4 - paint (70300221) | LF | 16,954 | $0.01 | $0.01 | $0.01 | $0.35 | $0.01 | $0.35 |
| 77 | Temp PVT MK line 6 - paint (70300241) | LF | 7,170 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.35 |
| 78 | Temp PVT MK line 12 - paint (70300261) | LF | 764 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.35 |
| 79 | Temp PVT MK line 24 - paint (70300281) | LF | 684 | $0.01 | $0.01 | $0.01 | $1.60 | $0.01 | $2.15 |
| 80 | Temp PVT MK L4 T4 tape (70307120) | LF | 20,864 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $2.45 |
| 81 | THPL PVT MK LTR & sym (78000100) | SF | 1,281 | $0.01 | $6.30 | $5.80 | $5.75 | $5.75 | $5.75 |
| 82 | THPL PVT MK line 4 (78000200) | LF | 16,954 | $0.66 | $0.80 | $0.70 | $0.72 | $0.72 | $0.72 |
| 83 | THPL PVT MK line 6 (78000400) | LF | 7,170 | $1.10 | $0.90 | $1.05 | $0.85 | $0.85 | $0.85 |
| 84 | THPL PVT MK line 12 (78000600) | LF | 764 | $3.30 | $3.30 | $3.20 | $3.05 | $3.05 | $3.05 |
| 85 | THPL PVT MK line 24 (78000650) | LF | 684 | $7.15 | $6.30 | $5.80 | $5.75 | $5.75 | $5.75 |
| 86 | Raised refl pavt MKR (78100100) | EACH | 507 | $41.80 | $37.00 | $40.15 | $34.00 | $34.00 | $34.00 |
| 87 | Raised ref PVT MK rem (78300200) | EACH | 507 | $6.00 | $0.01 | $0.01 | $0.01 | $14.00 | $12.00 |
| 88 | PVT MKG rem WTR blast (78300202) | SF | 11,311 | $1.10 | $0.01 | $0.01 | $0.01 | $1.00 | $1.00 |
| 89 | Undrgrd C galvs 2 (81028200) | LF | 569 | $53.45 | $50.00 | $48.00 | $45.34 | $44.00 | $65.00 |
| 90 | Undrgrd C galvs 4 (81028240) | LF | 298 | $116.67 | $149.00 | $105.50 | $99.56 | $129.00 | $90.00 |
| 91 | HD handhole (81400200) | EACH | 5 | $5,249.38 | $6,530.00 | $4,722.00 | $4,469.00 | $5,700.00 | $6,000.00 |
| 92 | Main EX TR sig instal (85000200) | EACH | 5 | $6,714.81 | $606.00 | $5,992.50 | $5,671.28 | $525.00 | $2,500.00 |
| 93 | Elcbl C signal 14 2C (87301215) | LF | 3,693 | $3.27 | $3.10 | $2.95 | $2.76 | $2.70 | $3.30 |
| 94 | Elcbl C lead 14 1PR (87301305) | LF | 1,044 | $3.43 | $3.30 | $3.05 | $2.90 | $3.00 | $3.00 |
| 95 | Elcbl C egrdc 6 1C (87301900) | LF | 679 | $6.47 | $6.40 | $5.85 | $5.55 | $5.50 | $4.00 |
| 96 | Drill EX foundation (87900100) | EACH | 27 | $849.10 | $445.00 | $747.00 | $706.94 | $390.00 | $700.00 |
| 97 | Det loop T1 (88600100) | LF | 2,238 | $37.57 | $36.40 | $33.55 | $31.77 | $31.50 | $32.00 |
| 98 | Mod EX contr (89502200) | EACH | 3 | $1,149.98 | $606.00 | $1,059.00 | $1,002.13 | $525.00 | $2,000.00 |
| 99 | Rem elcbl FR con (89502300) | LF | 2,652 | $2.73 | $2.70 | $2.40 | $2.26 | $2.30 | $1.00 |
| 100 | Remov EX TS equip (89502375) | EACH | 5 | $1,089.96 | $1,568.00 | $955.50 | $904.26 | $1,400.00 | $1,000.00 |
| 101 | Rebuild EX handhole (89502376) | EACH | 2 | $3,128.68 | $5,069.00 | $2,822.25 | $2,671.01 | $4,400.00 | $3,000.00 |
| 102 | Remov EX handhole (89502380) | EACH | 5 | $1,425.70 | $3,318.00 | $1,255.10 | $1,187.82 | $2,900.00 | $1,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.