IDOT contract 85764 bid tabulation
Project Number: 9Uaj-753 / /, section 18-00655-00-BR. Let by Illinois DOT on September 19, 2025, Winnebago, District 02. 4 bids received; low bid $6,340,772 by Civil Constructors, Inc. d/b/a/ Helm Civil.
- Owner
- Illinois DOT
- Letting
- 19 SEP 2025
- Pay items
- 72
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Civil Constructors, Inc. d/b/a/ Helm Civil | $6,340,772 | Low |
| 2 | Martin & Company Excavating | $6,997,327 | +10% |
| 3 | IHC Construction Companies, L.L.C. | $8,830,960 | +39% |
| 4 | Dunnet Bay Construction Company | $10,401,446 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Civil Constructors, Inc. d/b/a/ Helm Civil | 2. Martin & Company Excavating | 3. IHC Construction Companies, L.L.C. | 4. Dunnet Bay Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Earth excavation SPL (X2020410) | CY | 980 | $47.00 | $82.00 | $50.00 | $87.00 |
| 2 | Seeding CL 2A SPL (X2501020) | ACRE | 1 | $3,108.84 | $6,000.00 | $3,108.84 | $3,108.84 |
| 3 | Stone riprap CL A4 SP (X2810108) | SY | 96 | $90.00 | $90.00 | $125.00 | $235.00 |
| 4 | Stone riprap CL A5 SP (X2810110) | SY | 1,212 | $88.00 | $65.00 | $100.00 | $200.00 |
| 5 | BR deck grooving long (X5030250) | SY | 1,315 | $8.50 | $12.00 | $6.48 | $6.74 |
| 6 | Bar terminators (X5080530) | EACH | 252 | $26.50 | $35.00 | $55.00 | $18.00 |
| 7 | Drainage scuppr DS-11 (X5230174) | EACH | 6 | $2,200.00 | $2,250.00 | $2,000.00 | $1,750.00 |
| 8 | Traf cont & prot SPL (X7010216) | LS | 1 | $20,000 | $25,000 | $20,000 | $25,000 |
| 9 | Construction layout (Z0013798) | LS | 1 | $14,000 | $15,000 | $65,000 | $1.00 |
| 10 | Diamond grind BR sec (Z0029090) | SY | 1,669 | $12.00 | $12.00 | $7.86 | $12.00 |
| 11 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 12 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 13 | Tree remov acres (20100500) | ACRE | 0.30 | $49,900 | $40,000 | $49,900 | $49,900 |
| 14 | Channel excavation (20300100) | CY | 74 | $32.00 | $40.00 | $62.00 | $100.00 |
| 15 | Topsoil F & P 4 (21101615) | SY | 3,853 | $9.45 | $5.55 | $9.45 | $9.45 |
| 16 | Erosion contr blanket (25100630) | SY | 3,853 | $1.34 | $5.50 | $1.34 | $1.34 |
| 17 | Temp eros contr seed (28000250) | LB | 16 | $30.00 | $55.00 | $30.00 | $30.00 |
| 18 | Perimeter eros bar (28000400) | LF | 2,450 | $3.70 | $8.00 | $3.70 | $3.70 |
| 19 | Agg subgrade improve (30300011) | TON | 884 | $36.50 | $28.00 | $43.00 | $64.00 |
| 20 | Bit matls tack CT (40600290) | LB | 204 | $3.00 | $1.00 | $3.00 | $3.00 |
| 21 | HMA SC IL-9.5 C N50 (40604050) | TON | 21 | $350.00 | $225.00 | $350.00 | $350.00 |
| 22 | PVT con HMA BR app SL (42000070) | SY | 80 | $303.39 | $180.00 | $303.39 | $303.39 |
| 23 | Pavement rem (44000100) | SY | 261 | $85.00 | $15.00 | $60.00 | $37.00 |
| 24 | CL B patch T4 10 (44200976) | SY | 182 | $258.00 | $190.00 | $220.72 | $255.00 |
| 25 | Dowel bars 1 1/2 (44201299) | EACH | 40 | $60.00 | $30.00 | $26.33 | $50.00 |
| 26 | Tie bars 1 1/4 (44213208) | EACH | 20 | $28.00 | $30.00 | $20.36 | $50.00 |
| 27 | Aggregate SHLDS B 6 (48101500) | SY | 1,216 | $14.00 | $10.00 | $23.00 | $32.00 |
| 28 | HMA shoulders 6 (48203021) | SY | 899 | $51.81 | $43.00 | $51.81 | $51.81 |
| 29 | Rem exist struct (50100100) | EACH | 1 | $716,000 | $1,100,000 | $900,000 | $3,100,000 |
| 30 | Structure excavation (50200100) | CY | 179 | $50.00 | $40.00 | $70.00 | $175.00 |
| 31 | Cofferdam excavation (50200300) | CY | 961 | $70.00 | $40.00 | $80.00 | $200.00 |
| 32 | Cofferdam typ 2 loc 1 (50201121) | EACH | 1 | $165,000 | $200,000 | $480,000 | $500,000 |
| 33 | Cofferdam typ 2 loc 2 (50201122) | EACH | 1 | $165,000 | $200,000 | $300,000 | $500,000 |
| 34 | Conc struct (50300225) | CY | 498.50 | $850.00 | $890.00 | $1,700.00 | $1,100.00 |
| 35 | Conc sup-STR (50300255) | CY | 613.70 | $1,100.00 | $1,095.00 | $2,250.00 | $1,650.00 |
| 36 | Seal coat conc (50300265) | CY | 484 | $300.00 | $300.00 | $300.00 | $290.00 |
| 37 | Concrete encasement (50300280) | CY | 12 | $1,130.00 | $925.00 | $1,500.00 | $1,850.00 |
| 38 | Protective coat (50300300) | SY | 2,190 | $1.80 | $5.00 | $8.00 | $2.35 |
| 39 | Conc supstr app slab (50301350) | CY | 97.10 | $510.00 | $750.00 | $700.00 | $615.00 |
| 40 | F & E struct steel (50500105) | LS | 1 | $1,545,000 | $1,680,000 | $2,000,000 | $1,483,000 |
| 41 | Stud shear connectors (50500505) | EACH | 4,200 | $5.50 | $7.25 | $12.10 | $4.11 |
| 42 | Reinf bars, epoxy CTD (50800205) | LB | 233,550 | $2.00 | $1.75 | $1.60 | $1.75 |
| 43 | Bar splicers (50800515) | EACH | 1,527 | $39.00 | $35.00 | $25.00 | $27.00 |
| 44 | Bicycle railing (50901720) | LF | 28 | $468.00 | $475.00 | $421.10 | $435.00 |
| 45 | Fur STL pile HP14X89 (51201900) | LF | 5,858 | $84.00 | $105.00 | $100.00 | $93.00 |
| 46 | Driving piles (51202305) | LF | 5,858 | $0.01 | $1.00 | $0.10 | $0.01 |
| 47 | Test pile ST HP14X89 (51203900) | EACH | 6 | $9,400.00 | $8,500.00 | $15,000 | $15,000 |
| 48 | Pile shoes (51204650) | EACH | 100 | $166.00 | $175.00 | $170.00 | $145.00 |
| 49 | Name plates (51500100) | EACH | 1 | $975.00 | $1,500.00 | $1,000.00 | $600.00 |
| 50 | Elast bearing assy T1 (52100010) | EACH | 12 | $3,350.00 | $3,800.00 | $3,000.00 | $3,000.00 |
| 51 | Elast bearing assy T2 (52100020) | EACH | 6 | $3,900.00 | $4,800.00 | $3,500.00 | $3,500.00 |
| 52 | Anchor bolts 1 (52100520) | EACH | 36 | $96.00 | $175.00 | $400.00 | $200.00 |
| 53 | Anchor bolts 1 1/2 (52100540) | EACH | 12 | $137.00 | $250.00 | $425.00 | $395.00 |
| 54 | Granular backfill STR (58600101) | CY | 264 | $58.00 | $40.00 | $100.00 | $66.00 |
| 55 | Geocomposite wall DR (59100100) | SY | 111 | $29.00 | $22.00 | $58.00 | $28.00 |
| 56 | P undr for struct SPL 4 (60146305) | LF | 218 | $32.00 | $35.00 | $45.00 | $0.01 |
| 57 | SPBGR TY A 6FT posts (63000001) | LF | 1,563 | $33.75 | $30.00 | $28.14 | $28.14 |
| 58 | Traf bar term T6 (63100085) | EACH | 4 | $2,950.00 | $3,900.00 | $3,515.00 | $3,826.55 |
| 59 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,450.00 | $3,500.00 | $3,111.00 | $3,111.00 |
| 60 | Guardrail remov (63200310) | LF | 2,000 | $4.00 | $8.00 | $6.34 | $6.34 |
| 61 | Non SPL waste disposl (66900200) | CY | 928 | $74.00 | $60.00 | $40.00 | $80.00 |
| 62 | Soil disposal analy (66900530) | EACH | 1 | $1,250.00 | $1,400.00 | $1,750.00 | $1,600.00 |
| 63 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,950.00 | $4,000.00 | $400.00 |
| 64 | Reg sub F con report (66901003) | LS | 1 | $2,000.00 | $2,200.00 | $600.00 | $500.00 |
| 65 | Reg sub mon (66901006) | CAL DAY | 30 | $1,200.00 | $990.00 | $700.00 | $800.00 |
| 66 | Engr field office A (67000400) | CAL MO | 6 | $3,400.00 | $3,500.00 | $6,000.00 | $4,500.00 |
| 67 | Mobilization (67100100) | LS | 1 | $380,446 | $400,000 | $500,000 | $624,087 |
| 68 | Terminal marker - DA (72501000) | EACH | 4 | $60.00 | $40.00 | $35.00 | $35.00 |
| 69 | Paint PVT MK line 4 (78001110) | LF | 3,489 | $1.10 | $1.25 | $1.10 | $1.10 |
| 70 | Raised refl pavt MKR (78100100) | EACH | 20 | $110.00 | $120.00 | $110.00 | $110.00 |
| 71 | Grdrail ref type A (78200005) | EACH | 12 | $25.00 | $20.00 | $12.00 | $12.00 |
| 72 | Barr wall ref type B (78200010) | EACH | 4 | $65.00 | $75.00 | $65.00 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.