INDOT contract B-42838-A bid tabulation

BRIDGE REPLACEMENT. Let by Indiana DOT on September 10, 2025, Allen, Fort Wayne. 5 bids received; low bid $1,296,947 by Milestone Contractors LP.

Owner
Indiana DOT
Letting
10 SEP 2025
Pay items
78
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Milestone Contractors LP$1,296,947Low
2R L McCoy Inc$1,385,298+7.0%
3Miller Bros Construction Inc$1,447,167+12%
4Duncan Robertson Inc$1,568,672+21%
5E & B Paving LLC$1,617,500+25%
INDOT contract B-42838-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Milestone Contractors LP2. R L McCoy Inc3. Miller Bros Construction Inc4. Duncan Robertson Inc5. E & B Paving LLC
0001Construction engineering (105-06845)LS1$22,256$12,000$6,480.00$12,000$20,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$64,847$69,000$72,358$75,000$80,875
0010Clearing right-of-way (201-52370)LS1$25,939$27,500$1,717.40$30,000$32,350
0011Pavement removal (202-02240)SYS667$40.20$43.00$35.67$50.00$15.00
0012Present structure, remove, structure no. 1 (202-51330)LS1$51,375$68,000$92,278$150,000$192,000
0013Excavation, common (203-02000)CYS361$58.48$80.00$105.83$50.00$58.40
0014Borrow (203-02070)CYS1,878$33.00$34.00$55.28$15.00$33.00
0015Excavation, waterway (203-51223)CYS232$43.15$46.00$32.69$30.00$120.00
0016Pump around (205-11626)EACH1$14,400$8,000.00$6,525.03$1.00$15,136
0017Stormwater management budget (205-12108)DOL6,000$1.00$1.00$1.00$1.00$1.00
0018Stormwater management implementation (205-12616)LS1$2,700.00$2,500.00$7,000.00$20,000$35,000
0019SWQCP preparation (205-12618)LS1$665.00$3,200.00$2,600.00$2,300.00$10,000
0020Excavation, foundation, unclassified (206-51230)CYS139$57.15$65.00$64.11$30.00$120.00
0021Cofferdam (206-51235)LS1$6,865.00$15,000$11,157$15,000$7,000.00
0022Subgrade treatment, type IC (207-09935)SYS2,834$26.73$39.00$28.12$32.50$26.73
0023Aggregate for end bent backfill (211-06467)CYS56$114.55$110.00$176.08$115.00$120.00
0024Structure backfill, type 1 (211-09264)CYS8$70.00$45.00$44.99$115.00$70.00
0025Geotextile for pavement, type 2B (214-12239)SYS184$8.63$15.00$10.87$6.00$8.63
0026Subbase for PCCP (302-06464)CYS47$178.65$120.00$180.31$135.00$150.00
0027Compacted aggregate, no. 53 (303-01180)TON400$30.80$45.00$43.14$50.00$55.00
0028Milling, asphalt, 1 1/2 in. (306-08034)SYS362$15.70$14.00$10.23$15.00$25.00
0029QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON239$120.00$120.00$120.00$132.00$150.00
0030QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON356$104.00$104.00$104.00$114.00$118.00
0031QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON867$86.00$86.00$86.00$94.00$103.00
0032Joint adhesive (401-11526)LFT4,062$0.29$0.29$0.29$0.32$1.00
0033Asphalt for tack coat (406-05520)TON2$800.00$800.00$800.00$880.00$1.00
0034Guardrail, remove (601-02241)LFT173$12.00$12.00$12.00$13.00$12.00
0035Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT38$20.00$20.00$20.00$22.00$20.00
0036Guardrail transition, MGS without curb (601-12292)EACH4$3,175.00$3,175.00$3,175.00$3,492.00$3,175.00
0037Guardrail end treatment, type OS (601-94689)EACH4$2,950.00$2,950.00$2,950.00$3,245.00$2,950.00
0038Reinforced concrete bridge approach, 12 in. (609-06259)SYS184$157.55$230.00$185.53$225.00$180.00
0039Right-of-way marker (615-06490)EACH8$150.00$150.00$150.00$165.00$150.00
0040Monument, type B (615-06505)EACH2$1,100.00$1,100.00$1,100.00$1,210.00$1,100.00
0041Monument, type D (615-06515)EACH2$150.00$150.00$150.00$165.00$150.00
0042Benchmark post (615-06530)EACH1$700.00$700.00$700.00$770.00$700.00
0043Riprap, revetment (616-06405)TON698$48.50$65.00$65.10$45.00$50.00
0044Geotextile for riprap, type 1A (616-12246)SYS951$4.10$4.00$4.66$4.00$5.00
0045Mobilization and demobilization for seeding (621-01004)EACH2$500.00$525.00$525.00$577.00$525.00
0046Mulched seeding, type R (621-06559)SYS1,959$2.90$2.88$2.88$3.20$2.88
0047Sodding (621-06574)SYS34$125.00$64.00$64.00$70.00$64.00
0048Field office, type A (628-09401)MOS9$3,494.00$3,200.00$3,549.28$2,250.00$2,200.00
0049Test pile, indicator, production (701-09558)LFT132$118.50$97.00$113.83$100.00$100.00
0050Test pile, indicator, restrike (701-09560)EACH2$2,715.00$1,500.00$795.06$2,000.00$2,500.00
0051Pile shoe, HP 12 X 74 (701-09683)EACH10$208.10$250.00$142.19$250.00$300.00
0052Prebored hole, diameter 18 in. (701-09824)LFT26$171.75$800.00$172.60$250.00$100.00
0053Pile, steel H, HP 12 X 74 (701-95780)LFT445$127.85$76.00$116.49$100.00$95.00
0054Concrete, A, substructure (702-51005)CYS29$1,300.00$800.00$1,353.12$1,000.00$750.00
0055Reinforcing bars (703-06028)LBS46,198$1.73$1.40$1.51$1.50$1.50
0056Threaded tie bar assembly, epoxy coated (703-97936)EACH42$40.05$50.00$68.16$65.00$20.00
0057Concrete, C, superstructure (704-51002)CYS121$1,025.00$1,150.00$911.51$1,300.00$1,300.00
0058Concrete bridge railing transition, type TPF-1 (706-06351)EACH4$2,060.00$6,000.00$9,000.00$2,500.00$2,500.00
0059Railing, concrete type PF-1 (706-09962)LFT142$80.55$145.00$257.00$150.00$150.00
0060Railing, steel type PF-1 (706-11404)LFT160$88.40$72.00$72.00$79.00$72.00
0061Structural member, concrete, box beam, 42 in. X 48 in. (707-08512)LFT350$508.22$515.00$599.59$830.00$575.00
0062Surface seal , bridge no. 1 (709-51821)LS1$1,199.00$500.00$1.00$2,000.00$0.01
0063Pipe, type 3, circular, diameter 12 in. (715-05168)LFT46$115.00$90.00$92.47$60.00$115.00
0064Pipe, end bent drain, diameter 6 in. (715-05407)LFT146$16.23$27.00$15.41$15.00$15.00
0065Pipe end section, diameter 12 in. (715-46000)EACH2$1,000.00$600.00$758.34$500.00$1,000.00
0066Geotextile for underdrains, type 2B (718-12308)SYS147$8.20$8.00$10.55$3.50$10.00
0067Longitudinal grooving (722-12732)SYS391$8.96$20.00$8.95$15.00$20.00
0068Bearing assembly, elastomeric (726-92406)EACH20$266.15$200.00$431.34$400.00$2,500.00
0069Road closure sign assembly (801-04308)EACH3$340.00$340.00$361.00$192.00$340.00
0070Detour route marker assembly (801-06625)EACH31$150.00$150.00$174.00$82.00$150.00
0071Construction sign, type A (801-06640)EACH24$225.00$225.00$261.00$192.00$225.00
0072Construction sign, type B (801-06645)EACH2$150.00$150.00$106.00$82.00$150.00
0073Maintaining traffic (801-06775)LS1$168.60$500.00$6,661.74$25,000$7,500.00
0074Barricade, type III-A (801-07118)LFT72$20.00$20.00$17.04$17.50$20.00
0075Barricade, type III-B (801-07119)LFT72$20.00$20.00$17.04$17.50$20.00
0076Line, multi-component, solid, white, 4 in. (808-10033)LFT1,716$1.50$1.50$1.19$4.40$1.50
0077Line, multi-component, broken, yellow, 4 in. (808-10036)LFT215$1.50$1.50$2.17$4.40$1.50
0078Grooving for pavement markings (808-12032)LFT1,679$1.00$1.00$0.67$4.40$1.00
INDOT contract B-42838-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way