INDOT contract B-43899-A bid tabulation
BRIDGE DECK OVERLAY AND SUPERSTRUCTURE REPAIR. Let by Indiana DOT on October 8, 2025, Cass, LaPorte. 5 bids received; low bid $2,508,000 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 117
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $2,508,000 | Low |
| 2 | Laporte Construction Company Inc | $2,559,246 | +2.0% |
| 3 | Milestone Contractors LP | $2,747,585 | +10% |
| 4 | Superior Construction Co Inc | $2,803,181 | +12% |
| 5 | Rieth-Riley Construction Co., Inc. | $3,076,277 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Laporte Construction Company Inc | 3. Milestone Contractors LP | 4. Superior Construction Co Inc | 5. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $25,000 | $22,175 | $20,000 | $43,679 | $55,500 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $125,344 | $127,000 | $101,900 | $140,000 | $150,000 |
| 0011 | Pavement removal (202-02240) | SYS | 588 | $120.00 | $39.49 | $47.00 | $75.00 | $40.00 |
| 0012 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $187,000 | $224,449 | $65,548 | $300,000 | $150,000 |
| 0013 | Slopewall, remove (202-51368) | SYS | 126 | $35.00 | $50.90 | $92.00 | $148.00 | $400.00 |
| 0014 | Bridge railing, remove (202-62420) | LFT | 35.50 | $200.00 | $200.00 | $220.00 | $160.00 | $135.00 |
| 0015 | Sign, remove (202-74035) | EACH | 3 | $100.00 | $150.00 | $150.00 | $120.00 | $150.00 |
| 0016 | Inlet, remove (202-91385) | EACH | 2 | $250.00 | $1,503.25 | $1,100.00 | $1,350.00 | $2,800.00 |
| 0017 | Excavation, common (203-02000) | CYS | 717 | $120.00 | $48.02 | $58.00 | $40.00 | $80.00 |
| 0018 | Linear grading (203-08607) | LFT | 1,030 | $4.00 | $9.45 | $11.00 | $11.00 | $5.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 11,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $2,000.00 | $10,000 | $8,500.00 | $50,000 | $16,500 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 1,133 | $55.00 | $51.17 | $62.00 | $60.00 | $75.00 |
| 0022 | Aggregate for end bent backfill (211-06467) | CYS | 34 | $120.00 | $88.28 | $180.00 | $120.00 | $179.00 |
| 0023 | Drilled hole for flowable backfill (213-08068) | EACH | 22 | $50.00 | $239.56 | $325.00 | $175.00 | $400.00 |
| 0024 | Flowable backfill, non- removable (213-09269) | CYS | 161 | $240.00 | $234.59 | $180.00 | $154.00 | $345.00 |
| 0025 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,163 | $4.00 | $5.79 | $6.00 | $6.25 | $6.40 |
| 0026 | Compacted aggregate, no. 8 (301-12233) | CYS | 5 | $150.00 | $143.50 | $250.00 | $501.00 | $277.00 |
| 0027 | Compacted aggregate, no. 53 (301-12234) | CYS | 94 | $150.00 | $85.79 | $89.00 | $135.00 | $101.00 |
| 0028 | Subbase for PCCP (302-06464) | CYS | 125 | $150.00 | $106.31 | $165.00 | $155.00 | $143.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 58 | $75.00 | $57.36 | $95.00 | $75.00 | $97.00 |
| 0030 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,849 | $15.00 | $5.28 | $7.00 | $3.00 | $6.00 |
| 0031 | Milling, transition (306-08043) | SYS | 787 | $15.00 | $5.67 | $7.00 | $3.00 | $6.00 |
| 0032 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 213.10 | $149.00 | $220.00 | $340.00 | $220.00 | $220.00 |
| 0033 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 56 | $560.00 | $330.00 | $340.00 | $330.00 | $330.00 |
| 0034 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 83 | $198.00 | $330.00 | $250.00 | $330.00 | $330.00 |
| 0035 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 352 | $130.00 | $170.00 | $180.00 | $170.00 | $170.00 |
| 0036 | Joint adhesive (401-11526) | LFT | 2,738 | $1.00 | $0.05 | $2.00 | $0.05 | $0.05 |
| 0037 | Asphalt for tack coat (406-05521) | SYS | 3,793 | $0.25 | $0.05 | $0.25 | $0.05 | $0.05 |
| 0038 | Retrofitted tie bars (503-03489) | EACH | 12 | $25.00 | $18.49 | $60.00 | $50.00 | $60.00 |
| 0039 | Terminal joint, type HMA (503-12477) | LFT | 171 | $600.00 | $383.16 | $400.00 | $420.00 | $500.00 |
| 0040 | Rcba crack filling, PCC sealer/healer (507-12941) | LFT | 408 | $5.00 | $10.00 | $22.10 | $5.00 | $11.00 |
| 0041 | Guardrail, remove (601-02241) | LFT | 490 | $7.00 | $4.00 | $7.00 | $7.00 | $4.00 |
| 0042 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 25 | $31.00 | $47.00 | $31.00 | $31.00 | $47.00 |
| 0043 | Guardrail height transition, MGS (601-12289) | EACH | 6 | $915.00 | $950.00 | $915.00 | $1,110.00 | $950.00 |
| 0044 | Guardrail transition, MGS without curb (601-12292) | EACH | 6 | $3,300.00 | $3,200.00 | $3,300.00 | $3,300.00 | $3,200.00 |
| 0045 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 585.60 | $250.00 | $187.60 | $218.00 | $180.00 | $223.00 |
| 0046 | Slopewall, concrete, 4 in. (616-51367) | SYS | 126 | $162.06 | $285.80 | $160.00 | $155.00 | $300.00 |
| 0047 | Inspection hole (616-93772) | EACH | 8 | $400.00 | $664.73 | $135.00 | $400.00 | $675.00 |
| 0048 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $30,000 | $18,000 | $18,000 | $45,000 | $18,000 |
| 0049 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0050 | Clean steel bridge, top flanges, type QP-2, bridge no. 1 (619-12506) | LS | 1 | $5,000.00 | $2,000.00 | $2,000.00 | $17,500 | $2,000.00 |
| 0051 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $10,000 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0052 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $275.00 | $275.00 | $500.00 | $275.00 | $275.00 |
| 0053 | Erosion control blanket (621-02770) | SYS | 310 | $2.76 | $2.76 | $1.90 | $2.76 | $2.76 |
| 0054 | Mulched seeding, type U (621-06560) | SYS | 310 | $1.70 | $1.70 | $1.25 | $1.70 | $1.70 |
| 0055 | Field office, type C (628-09403) | MOS | 12 | $3,000.00 | $3,200.00 | $4,500.00 | $2,500.00 | $2,500.00 |
| 0056 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 4 | $1,000.00 | $2,147.23 | $1,300.00 | $2,125.00 | $3,000.00 |
| 0057 | Field drilled hole in concrete (702-51863) | EACH | 476 | $10.00 | $25.14 | $20.00 | $22.00 | $35.00 |
| 0058 | Concrete, C, substructure (702-92857) | CYS | 13.60 | $950.00 | $2,213.12 | $1,990.00 | $1,100.00 | $2,500.00 |
| 0059 | Reinforcing bars, epoxy coated (703-06029) | LBS | 52,287 | $1.50 | $1.32 | $1.75 | $1.75 | $1.62 |
| 0060 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 48 | $20.00 | $44.04 | $60.00 | $50.00 | $50.00 |
| 0061 | Inertial profiler, bridge encounter (704-000080) | LS | 1 | $12,000 | $10,000 | $10,000 | $7,500.00 | $59,200 |
| 0062 | Corrective grinding, bridge encounter (704-000082) | LS | 1 | $15,000 | $32,000 | $59,817 | $12,500 | $30,600 |
| 0063 | Concrete, C, superstructure (704-51002) | CYS | 52.60 | $950.00 | $1,640.82 | $1,000.00 | $1,575.00 | $2,200.00 |
| 0064 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 22 | $1,200.00 | $370.03 | $650.00 | $475.00 | $650.00 |
| 0065 | Railing, concrete type FC (706-11600) | CYS | 2.50 | $900.00 | $4,437.91 | $6,000.00 | $2,800.00 | $2,200.00 |
| 0066 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 8 | $5,000.00 | $2,595.39 | $4,700.00 | $3,250.00 | $5,000.00 |
| 0067 | Railing, concrete type C, modified (706-92612) | LFT | 35.50 | $500.00 | $361.24 | $600.00 | $315.00 | $325.00 |
| 0068 | Surface seal , STR no 1 (709-51821) | LS | 1 | $2,500.00 | $5,100.00 | $5,096.00 | $2,500.00 | $5,096.00 |
| 0069 | Surface seal , STR no 2 (709-51821) | LS | 1 | $2,500.00 | $5,000.00 | $4,974.00 | $2,500.00 | $4,974.00 |
| 0070 | Surface seal , STR no 3 (709-51821) | LS | 1 | $5,000.00 | $12,000 | $11,920 | $5,000.00 | $11,920 |
| 0071 | Surface seal , STR no 4 (709-51821) | LS | 1 | $5,000.00 | $13,927 | $12,752 | $5,000.00 | $12,752 |
| 0072 | Surface seal , STR no 5 (709-51821) | LS | 1 | $4,500.00 | $11,775 | $10,622 | $4,500.00 | $10,622 |
| 0073 | Patching concrete structures (710-09158) | SFT | 100 | $25.00 | $167.94 | $200.00 | $25.00 | $167.00 |
| 0074 | Structural steel (711-51035) | LBS | 377 | $50.00 | $21.45 | $30.00 | $15.00 | $30.00 |
| 0075 | Drilled hole (711-51864) | EACH | 50 | $83.00 | $89.34 | $45.00 | $100.00 | $135.00 |
| 0076 | Jacking and supporting superstructure , STR no 1 (711-90114) | LS | 1 | $16,300 | $36,723 | $48,000 | $100,000 | $105,000 |
| 0077 | Stud shear connectors (711-96800) | EACH | 224 | $10.00 | $17.00 | $11.16 | $10.00 | $25.00 |
| 0078 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 150 | $15.00 | $26.54 | $20.00 | $16.75 | $12.00 |
| 0079 | Pipe, roadway drain casting extension (715-10238) | EACH | 4 | $500.00 | $859.95 | $1,200.00 | $950.00 | $2,500.00 |
| 0080 | Geotextile for underdrains, type 2B (718-12308) | SYS | 106 | $4.00 | $20.34 | $8.00 | $14.00 | $30.00 |
| 0081 | Inlet, type D6 (720-45025) | EACH | 2 | $2,000.00 | $3,326.89 | $9,000.00 | $4,200.00 | $10,000 |
| 0082 | Bridge deck, remove concrete overlay and surface (722-000183) | SYS | 810 | $15.00 | $16.55 | $27.00 | $10.25 | $16.00 |
| 0083 | Hydrodemolition (722-01066) | SYS | 1,602 | $75.00 | $87.06 | $118.00 | $65.00 | $63.00 |
| 0084 | Bridge deck overlay budget (722-12380) | DOL | 35,044 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0085 | Bridge deck, remove concrete surface (722-12464) | SYS | 792 | $15.00 | $12.59 | $20.00 | $7.50 | $15.00 |
| 0086 | Longitudinal grooving (722-12732) | SYS | 2,266.60 | $7.50 | $11.25 | $6.00 | $4.00 | $10.00 |
| 0087 | Bridge deck patching, full depth (722-51401) | SFT | 558 | $10.00 | $55.00 | $51.00 | $25.00 | $1.00 |
| 0088 | Bridge deck overlay, latex modified (722-51842) | SYS | 1,681 | $100.00 | $147.00 | $155.00 | $105.00 | $160.00 |
| 0089 | Bridge deck patching, partial depth (722-51852) | SFT | 957 | $2.00 | $3.95 | $4.50 | $2.00 | $1.00 |
| 0090 | Overlay dam (722-51874) | SFT | 186 | $75.00 | $99.50 | $56.00 | $60.00 | $125.00 |
| 0091 | Bridge expansion joint, type PCF (724-12773) | LFT | 329 | $100.00 | $67.04 | $80.00 | $85.00 | $200.00 |
| 0092 | Bearing assembly, elastomeric (726-92406) | EACH | 14 | $5,000.00 | $2,161.89 | $3,700.00 | $2,250.00 | $3,500.00 |
| 0093 | Straighten steel member , STR no 1 (729-11819) | LS | 1 | $100,000 | $88,000 | $130,000 | $65,000 | $98,000 |
| 0094 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 2,674 | $48.50 | $44.16 | $44.16 | $50.50 | $60.00 |
| 0095 | Construction sign, type D (801-03291) | EACH | 3 | $250.00 | $262.00 | $262.00 | $262.00 | $262.00 |
| 0096 | Road closure sign assembly (801-04308) | EACH | 21 | $325.00 | $244.00 | $244.00 | $244.00 | $244.00 |
| 0097 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 16,593 | $2.01 | $1.89 | $1.89 | $1.89 | $1.89 |
| 0098 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $14.00 | $13.94 | $13.94 | $13.94 | $13.94 |
| 0099 | Detour route marker assembly (801-06625) | EACH | 59 | $130.00 | $161.00 | $161.00 | $161.00 | $161.00 |
| 0100 | Construction sign, type A (801-06640) | EACH | 81 | $190.00 | $197.00 | $197.00 | $197.00 | $197.00 |
| 0101 | Construction sign, type B (801-06645) | EACH | 27 | $100.00 | $104.00 | $104.00 | $104.00 | $104.00 |
| 0102 | Flashing arrow sign (801-06710) | DAY | 90 | $15.00 | $15.00 | $13.00 | $15.00 | $15.00 |
| 0103 | Maintaining traffic (801-06775) | LS | 1 | $10,000 | $41,219 | $79,525 | $250,000 | $75,000 |
| 0104 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 6 | $2,500.00 | $1,666.67 | $5,500.00 | $3,500.00 | $6,905.00 |
| 0105 | Barricade, type III-A (801-07118) | LFT | 156 | $16.00 | $15.24 | $15.24 | $15.24 | $15.24 |
| 0106 | Barricade, type III-B (801-07119) | LFT | 220 | $16.00 | $15.24 | $15.24 | $15.24 | $15.24 |
| 0107 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 1,900 | $35.50 | $35.00 | $51.00 | $25.00 | $45.00 |
| 0108 | Portable changeable message sign (801-11642) | EACH | 1 | $5,313.00 | $4,191.00 | $4,191.00 | $4,191.00 | $4,191.00 |
| 0109 | Portable signal (801-12081) | LS | 1 | $6,500.00 | $7,287.00 | $8,500.00 | $7,287.01 | $7,287.00 |
| 0110 | Law enforcement officer (801-12324) | HRS | 54 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0111 | Driveway assistance device (801-12482) | EACH | 3 | $2,000.00 | $2,181.00 | $2,181.00 | $2,181.00 | $2,181.00 |
| 0112 | Temporary buzz strips (801-97643) | LFT | 1,152 | $22.00 | $19.80 | $20.00 | $19.80 | $19.80 |
| 0113 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 2,870 | $1.50 | $0.91 | $0.91 | $0.91 | $0.91 |
| 0114 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 2,870 | $1.50 | $0.91 | $0.91 | $0.91 | $0.91 |
| 0115 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 454 | $2.00 | $1.55 | $1.55 | $1.55 | $1.55 |
| 0116 | Grooving for pavement markings (808-12032) | LFT | 480 | $2.00 | $3.51 | $3.51 | $3.51 | $3.51 |
| 0117 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 12 | $1.00 | $25.54 | $25.54 | $25.54 | $1.19 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.